9412 S BEACH ST 90002
Certificate Information: 9412 S BEACH ST 90002
- Application / Permit
- 19010-10000-02415
- Plan Check / Job No.
- B19LA11784
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 12/18/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2019 | LAMAR DAVIS |
| Corrections Issued | 8/1/2019 | LAMAR DAVIS |
| Quality Review Completed | 8/6/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/12/2019 | APPLICANT |
| Applicant returned to address corrections | 10/1/2019 | LAMAR DAVIS |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Applicant returned to address corrections | 12/3/2019 | LAMAR DAVIS |
| Applicant returned to address corrections | 12/12/2019 | LAMAR DAVIS |
| Plan Check Approved | 12/18/2019 | LAMAR DAVIS |
| Issued | 12/18/2019 | LADBS |
| CofO in Progress | 9/23/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/2/2020 | DEROLD HAUFF |
| CofO Issued | 10/2/2020 | DEROLD HAUFF |
| Permit Finaled | 10/2/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 10/29/2019 | EMIL KYUPELYAN |
| Miscellaneous | Cleared | 11/1/2019 | LAMAR DAVIS |
| Green Code | Cleared | 11/14/2019 | COLIN LOREDO |
| Miscellaneous | Cleared | 12/12/2019 | LAMAR DAVIS |
| Low Impact Development | Cleared | 12/13/2019 | RYAN HUDSON |
| Hydrant and Access approval | Cleared | 12/16/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 12/16/2019 | JEANIE LAM |
Contact Information
| Architect | Spencer,, William K; Lic. No.: C4943 | 71946 ELEANORA LANE RANCHO MIRAGE, CA 92270 |
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/3/2020 | Partial Approval | WILLIAM ROSE |
| Footing/Foundation/Slab | 2/7/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 2/28/2020 | Corrections Issued | WILLIAM ROSE |
| Footing/Foundation/Slab | 3/6/2020 | Approved | WILLIAM ROSE |
| Sewer | 3/6/2020 | Approved | WILLIAM ROSE |
| BUILDING-Rough-Frame | 4/16/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/16/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 4/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 4/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 4/16/2020 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 4/16/2020 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 4/20/2020 | Conditional Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 4/21/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/21/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/21/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/21/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/21/2020 | Approved | EUGENE CASSIDY |
| Insulation | 4/27/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/27/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Insulation | 4/29/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/29/2020 | Partial Approval | BRIAN CHRISTIAN |
| Drywall Nailing | 5/5/2020 | Approved | BRIAN CHRISTIAN |
| Final | 6/16/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/16/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 6/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 6/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/29/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 6/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 6/29/2020 | Partial Inspection | MICHAEL PELHAM |
| Service/Power Release | 6/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Smoke Detectors | 6/29/2020 | Approved | EUGENE CASSIDY |
| Final | 7/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 7/2/2020 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 7/2/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/8/2020 | Approved | EUGENE CASSIDY |
| Final | 7/8/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/8/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 7/8/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 7/8/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 7/8/2020 | Approved | EUGENE CASSIDY |
| Final | 9/23/2020 | OK to Issue CofO | EUGENE CASSIDY |