9412 S BEACH ST 90002

Certificate Information: 9412 S BEACH ST 90002

Application / Permit
19010-10000-02415
Plan Check / Job No.
B19LA11784
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 12/18/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Assigned to Plan Check Engineer 7/23/2019 LAMAR DAVIS
Corrections Issued 8/1/2019 LAMAR DAVIS
Quality Review Completed 8/6/2019 HERNAN ARREOLA
Building Plans Picked Up 8/12/2019 APPLICANT
Applicant returned to address corrections 10/1/2019 LAMAR DAVIS
Green Plans Picked Up 10/29/2019 APPLICANT
Applicant returned to address corrections 12/3/2019 LAMAR DAVIS
Applicant returned to address corrections 12/12/2019 LAMAR DAVIS
Plan Check Approved 12/18/2019 LAMAR DAVIS
Issued 12/18/2019 LADBS
CofO in Progress 9/23/2020 EUGENE CASSIDY
Permit Finaled 10/2/2020 DEROLD HAUFF
CofO Issued 10/2/2020 DEROLD HAUFF
Permit Finaled 10/2/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/7/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/29/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/29/2019 EMIL KYUPELYAN
Miscellaneous Cleared 11/1/2019 LAMAR DAVIS
Green Code Cleared 11/14/2019 COLIN LOREDO
Miscellaneous Cleared 12/12/2019 LAMAR DAVIS
Low Impact Development Cleared 12/13/2019 RYAN HUDSON
Hydrant and Access approval Cleared 12/16/2019 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 12/16/2019 JEANIE LAM

Contact Information

Architect Spencer,, William K; Lic. No.: C4943 71946 ELEANORA LANE      RANCHO MIRAGE, CA 92270
Contractor Owner-Builder       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/3/2020 Partial Approval WILLIAM ROSE
Footing/Foundation/Slab 2/7/2020 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 2/28/2020 Corrections Issued WILLIAM ROSE
Footing/Foundation/Slab 3/6/2020 Approved WILLIAM ROSE
Sewer 3/6/2020 Approved WILLIAM ROSE
BUILDING-Rough-Frame 4/16/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/16/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 4/16/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 4/16/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/16/2020 Not Ready for Inspection EUGENE CASSIDY
Sewer 4/16/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/16/2020 Approved EUGENE CASSIDY
Deputy Wood Construction 4/20/2020 Conditional Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 4/21/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/21/2020 Approved EUGENE CASSIDY
Green Building Rough 4/21/2020 Approved EUGENE CASSIDY
HVAC-Rough 4/21/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 4/21/2020 Approved EUGENE CASSIDY
Insulation 4/27/2020 Corrections Issued BRIAN CHRISTIAN
Interior/Exterior Lathing 4/27/2020 Corrections Issued BRIAN CHRISTIAN
Insulation 4/29/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/29/2020 Partial Approval BRIAN CHRISTIAN
Drywall Nailing 5/5/2020 Approved BRIAN CHRISTIAN
Final 6/16/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 6/16/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/16/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 6/16/2020 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/16/2020 Not Ready for Inspection EUGENE CASSIDY
Final 6/29/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 6/29/2020 Corrections Issued EUGENE CASSIDY
Pre-Inspection 6/29/2020 Partial Inspection MICHAEL PELHAM
Service/Power Release 6/29/2020 Corrections Issued EUGENE CASSIDY
Smoke Detectors 6/29/2020 Approved EUGENE CASSIDY
Final 7/2/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 7/2/2020 Corrections Issued EUGENE CASSIDY
Service/Power Release 7/2/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/8/2020 Approved EUGENE CASSIDY
Final 7/8/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 7/8/2020 Approved EUGENE CASSIDY
HVAC-Final 7/8/2020 Approved EUGENE CASSIDY
PLUMBING-Final 7/8/2020 Approved EUGENE CASSIDY
Service/Power Release 7/8/2020 Approved EUGENE CASSIDY
Final 9/23/2020 OK to Issue CofO EUGENE CASSIDY