(N) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AT FRONT OF THE LOT. "Comply with Department Order effective date. SEE COMMENTS 02/06/2018.
Permit Issued
Issued on 8/2/2021
Issuing Office
Current Status
CofO Issued on 3/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 SERGIO GUTIERREZ
Green Plans Picked Up 8/6/2019 APPLICANT
Corrections Issued 8/7/2019 SERGIO GUTIERREZ
Quality Review Completed 8/20/2019 KESETE HAREGOT
Applicant returned to address corrections 5/12/2021 SERGIO GUTIERREZ
Plan Check Approved 5/26/2021 SERGIO GUTIERREZ
Issued 8/2/2021 APPLICANT
Building Plans Picked Up 8/5/2021 APPLICANT
CofO in Progress 3/7/2023 FREDDIE RIVERA
Permit Finaled 3/11/2023 DEROLD HAUFF
CofO Issued 3/11/2023 DEROLD HAUFF
Permit Finaled 3/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/8/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/8/2020 CELINA MORENO
Sewer availability Cleared 12/10/2020 CELINA MORENO
Hydrant and Access approval Cleared 12/15/2020 KURT CORRAL
Low Impact Development Cleared 2/2/2021 SARAH YOUSSEF
Stormwater Pollution Mitigatn Cleared 2/2/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/22/2021 JEANIE LAM
Specific Plan Cleared 4/27/2021 DANIEL CORONADO
Green Code Cleared 5/12/2021 VIVIAN LAO

Contact Information

Contractor S J Cons - Tech Co; Lic. No.: 905983-B 687 S. HOBART BLVD #548      LOS ANGELES, CA 90005
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/15/2021 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 11/22/2021 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 12/10/2021 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 12/21/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/21/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval ALFREDO BALANDRA
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 5/11/2022 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 5/26/2022 Approved FREDDIE RIVERA
Wood Frame 5/26/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 6/7/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 6/7/2022 Conditional Approval FREDDIE RIVERA
Green Building Rough 6/7/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 6/7/2022 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 6/7/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 6/16/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 6/16/2022 Approved FREDDIE RIVERA
HVAC-Rough 7/12/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 7/14/2022 Approved FREDDIE RIVERA
Green Building Rough 7/14/2022 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 7/14/2022 Approved FREDDIE RIVERA
Insulation 7/21/2022 Approved STUART CHAPMAN
Underground Mechanical 7/21/2022 Approved STUART CHAPMAN
Drywall Nailing 8/15/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 8/15/2022 Approved FREDDIE RIVERA
Shower Pan 8/22/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/17/2022 Partial Inspection FREDDIE RIVERA
Gas Test 11/17/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 11/17/2022 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 12/12/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 12/12/2022 Corrections Issued FREDDIE RIVERA
Final 1/25/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 1/25/2023 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved FREDDIE RIVERA
Service/Power Release 1/25/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 1/25/2023 Approved FREDDIE RIVERA
Final 2/23/2023 Conditional Approval FREDDIE RIVERA
Green Building Final 2/23/2023 Approved FREDDIE RIVERA
Service/Power Release 2/23/2023 Approved FREDDIE RIVERA
Final 3/7/2023 OK to Issue CofO FREDDIE RIVERA