2404 S WILSON AVE 90291

Certificate Information: 2404 S WILSON AVE 90291

Application / Permit
19010-10000-02391
Plan Check / Job No.
B19LA11636
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 13'3" X 30 RECREATIONAL ROOM W/ HALF BATH AND OUTSIDE STORAGE
Permit Issued
Issued on 3/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 ZAW HAN
Corrections Issued 6/27/2019 ZAW HAN
Quality Review Completed 6/27/2019 HERNAN ARREOLA
Building Plans Picked Up 7/1/2019 APPLICANT
Green Plans Picked Up 7/1/2019 APPLICANT
Plan Check Approved 8/21/2019 HERNAN ARREOLA
Issued 3/9/2020 LADBS
CofO in Progress 4/20/2023 HERBERT GIRON
Permit Finaled 4/20/2023 DANIEL ORRANTE
CofO Issued 4/20/2023 DANIEL ORRANTE
Permit Finaled 4/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 7/3/2019 JEFF KHAU
Coastal Zone Cleared 8/13/2019 TREVOR MARTIN
Green Code Cleared 8/13/2019 SARAH ABOULHOSN
Low Impact Development Cleared 8/13/2019 ANDRES COVARRUBIAS
Miscellaneous Cleared 8/13/2019 TREVOR MARTIN
Miscellaneous Cleared 8/13/2019 TREVOR MARTIN
ZI Cleared 8/13/2019 TREVOR MARTIN
ZI Cleared 8/13/2019 TREVOR MARTIN
Sewer availability Cleared 8/19/2019 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/20/2019 OSCAR GUTIERREZ
Roof/Waste drainage to street Cleared 8/20/2019 OSCAR GUTIERREZ
Specific Plan Cleared 8/21/2019 PEDRO AYALA

Contact Information

Contractor Hoffmann Structure Inc; Lic. No.: 751137-B 15332 ANTIOCH STREET 9      PACIFIC PALISADES, CA 90272
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Shapira,, Ofer; Lic. No.: L7123 434 NORTH VISTA STREET   SURVEYING & DRAFTING SERVICES    LOS ANGELES, CA 90036

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/3/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 4/6/2020 Not Ready for Inspection DAVID HEINE
METHANE-Barrier 4/6/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 4/6/2020 Not Ready for Inspection DAVID HEINE
Footing/Foundation/Slab 4/8/2020 Partial Approval DAVID HEINE
METHANE-Barrier 4/8/2020 Approved DAVID HEINE
METHANE-Subgrade 4/8/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Not Ready for Inspection DAVID HEINE
Underground Mechanical 4/14/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval DAVID HEINE
Underground Mechanical 4/16/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 4/28/2020 Approved DAVID HEINE
PLUMBING-Rough 4/28/2020 Approved DAVID HEINE
Interior/Exterior Lathing 5/5/2020 Partial Approval DAVID HEINE
Insulation 5/7/2020 Not Ready for Inspection DAVID HEINE
Insulation 5/8/2020 Approved DAVID HEINE
Drywall Nailing 5/18/2020 Approved DAVID HEINE
Green Building Rough 5/18/2020 Approved DAVID HEINE
Masonry Wall/Backfill 5/27/2020 Partial Approval DAVID HEINE
Masonry Wall/Backfill 5/28/2020 Partial Approval DAVID HEINE
Masonry Wall/Backfill 5/29/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 8/7/2020 Conditional Approval DAVID HEINE
Final 8/7/2020 Not Ready for Inspection DAVID HEINE
Footing/Foundation/Slab 8/7/2020 Approved DAVID HEINE
Green Building Final 8/7/2020 Not Ready for Inspection DAVID HEINE
METHANE-Final 8/7/2020 Approved DAVID HEINE
METHANE-Rough 8/7/2020 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 8/7/2020 SGSOV Not Ready DAVID HEINE
Service/Power Release 8/7/2020 Not Ready for Inspection DAVID HEINE
Smoke Detectors 8/7/2020 Approved DAVID HEINE
Verify Sprinkler Sign Off 8/7/2020 Not Ready for Inspection DAVID HEINE
BUILDING-Rough-Frame 9/2/2020 Approved DAVID HEINE
Final 9/2/2020 Not Ready for Inspection DAVID HEINE
Green Building Final 9/2/2020 Not Ready for Inspection DAVID HEINE
SGSOV-Seismic Gas S/O Valve 9/2/2020 SGSOV Approved DAVID HEINE
Service/Power Release 9/2/2020 Approved DAVID HEINE
Verify Sprinkler Sign Off 9/2/2020 Approved DAVID HEINE
Green Building Final 9/24/2020 Approved DAVID HEINE
Final 12/22/2022 Corrections Issued EVAN COOPER
Final 4/14/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Final 4/19/2023 Approved HERBERT GIRON
Final 4/19/2023 OK to Issue CofO HERBERT GIRON
HVAC-Final 4/19/2023 Approved HERBERT GIRON
PLUMBING-Final 4/19/2023 Approved HERBERT GIRON