5801 W CAMERFORD AVE 90038

Certificate Information: 5801 W CAMERFORD AVE 90038

Application / Permit
19010-10000-02388
Plan Check / Job No.
B19LA11627
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 36 units, 4 stories of Type VA residential units over 1 level of type IA subterranean parking.
Permit Issued
Issued on 5/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2019 APPLICANT
Disabled Access Plans Picked Up 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 7/19/2019 HERNAN ARREOLA
Green Plans Picked Up 7/31/2019 APPLICANT
Corrections Issued 8/1/2019 HERNAN ARREOLA
Quality Review Completed 8/1/2019 SIAVOSH POURSABAHIAN
Applicant returned to address corrections 10/31/2019 HERNAN ARREOLA
Applicant returned to address corrections 11/6/2019 HERNAN ARREOLA
Applicant returned to address corrections 11/22/2019 HERNAN ARREOLA
Plan Check Approved 5/14/2020 HERNAN ARREOLA
Issued 5/18/2020 LADBS
Building Plans Picked Up 1/6/2022 APPLICANT
CofO in Progress 1/24/2023 DAVID BURKHEAD
CofO Issued 1/24/2023 TIMOTHY GRIFFITH
Permit Finaled 1/24/2023 TIMOTHY GRIFFITH

Permit Application Clearance Information

Address approval Cleared 11/7/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/7/2019 CELINA MORENO
Bicycle Parking Cleared 11/8/2019 ELAINE LEI
Sewer availability Cleared 11/15/2019 EMIL KYUPELYAN
Building over 3-story or 36-ft Cleared 11/22/2019 CALOSHA APPROVED
Green Code Cleared 12/11/2019 HERNAN ARREOLA
Highway dedication Cleared 2/6/2020 JUAN ASHTON
DAS Clearance Cleared 2/24/2020 SHINE LIN
Hydrant and Access approval Cleared 2/28/2020 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 3/5/2020 OSCAR SALGADO JR
Low Impact Development Cleared 3/5/2020 ORVAL HERNANDEZ-MARCI
Trees in Parkway Cleared 3/24/2020 JOHN KIM
Density Bonus 12.22.A.25 Cleared 4/14/2020 JACOB COMER
Roof/Waste drainage to street Cleared 4/14/2020 EMIL KYUPELYAN
Work Adjacent to Public Way Cleared 4/17/2020 DANNY MORALES
Frnt yard landscape/Water mgmt Cleared 4/30/2020 SARAHI ORTEGA
Miscellaneous Cleared 4/30/2020 SARAHI ORTEGA
Opn space landscape/Water mgmt Cleared 4/30/2020 SARAHI ORTEGA
Excavation more than 5-ft deep Cleared 5/14/2020 CALOSHA APPROVED

Contact Information

Architect Levin,, Edward S; Lic. No.: C14361 1305 N HARPER AVENUE APT D      WEST HOLLYWOOD, CA 90046
Contractor H M S Investments Inc; Lic. No.: 484663-B 11620 WILSHIRE BLVD SUITE 900      LOS ANGELES, CA 90025
Engineer Ekmekji,, Steve Eli; Lic. No.: C66727 19281 BERCLAIR LANE      TARZANA, CA 91356
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/28/2020 Partial Inspection DANIEL MC AULIFFE
Pre-Inspection 6/17/2020 Approved DAVID BURKHEAD
Piling/Pier/Caisson 7/1/2020 Partial Inspection DAVID BURKHEAD
Piling/Pier/Caisson 8/24/2020 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Approval DAVID BURKHEAD
METHANE-Barrier 8/26/2020 Not Ready for Inspection DAVID BURKHEAD
METHANE-Subgrade 8/26/2020 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 9/2/2020 Partial Approval DAVID BURKHEAD
METHANE-Barrier 9/2/2020 Approved DAVID BURKHEAD
METHANE-Subgrade 9/2/2020 Approved DAVID BURKHEAD
Piling/Pier/Caisson 9/4/2020 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/21/2020 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 9/22/2020 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 9/25/2020 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/28/2020 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 9/29/2020 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/5/2020 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/6/2020 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/6/2020 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 10/7/2020 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/8/2020 Conditional Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 10/14/2020 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/19/2020 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/20/2020 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/22/2020 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/23/2020 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 10/26/2020 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 10/27/2020 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/4/2020 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 12/14/2020 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/4/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 1/12/2021 Conditional Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 1/13/2021 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/15/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 2/10/2021 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 2/11/2021 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 3/10/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Steel/Welding 3/11/2021 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/11/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 3/12/2021 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 3/12/2021 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 3/12/2021 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/30/2021 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 3/30/2021 Approved DAVID BURKHEAD
Deputy Reinf. Masonry 3/31/2021 Conditional Approval DAVID BURKHEAD
Deputy Wood Construction 4/13/2021 Approved DAVID BURKHEAD
Green Building Rough 4/13/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 4/13/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/13/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/13/2021 Partial Inspection DAVID BURKHEAD
Green Building Rough 5/11/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 5/11/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/11/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/11/2021 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 5/12/2021 Conditional Approval DAVID BURKHEAD
Green Building Rough 6/15/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 6/15/2021 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Partial Approval DAVID BURKHEAD
Deputy Fireproofing 6/22/2021 Conditional Approval DAVID BURKHEAD
Green Building Rough 7/16/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 7/16/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/16/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/16/2021 Corrections Issued DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval DAVID BURKHEAD
Green Building Rough 7/20/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 7/20/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/20/2021 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 7/30/2021 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval DAVID BURKHEAD
Green Building Rough 8/5/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 8/5/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/5/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 8/13/2021 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval DAVID BURKHEAD
Green Building Rough 8/13/2021 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 8/13/2021 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 8/13/2021 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/17/2021 Partial Approval DAVID BURKHEAD
Green Building Rough 9/17/2021 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 10/8/2021 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 10/18/2021 Conditional Approval DANIEL MC AULIFFE
Deputy Wood Construction 10/21/2021 Conditional Approval DANIEL MC AULIFFE
Insulation 11/1/2021 Partial Inspection DAVID BURKHEAD
Insulation 11/12/2021 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 11/18/2021 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval DAVID BURKHEAD
Drywall Nailing 11/24/2021 Partial Approval DANIEL MC AULIFFE
Green Building Rough 11/24/2021 Approved DANIEL MC AULIFFE
Drywall Nailing 12/13/2021 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 12/20/2021 Partial Approval DAVID BURKHEAD
Wood Frame 12/20/2021 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 1/4/2022 Partial Approval DAVID BURKHEAD
Wood Frame 1/4/2022 Partial Inspection DAVID BURKHEAD
Interior/Exterior Lathing 1/19/2022 Partial Approval DAVID BURKHEAD
Wood Frame 2/8/2022 Partial Approval DAVID BURKHEAD
Insulation 2/15/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 2/24/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 2/28/2022 Partial Approval DAVID BURKHEAD
Insulation 3/1/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/3/2022 Partial Approval DAVID BURKHEAD
Insulation 3/7/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 3/18/2022 Partial Approval DAVID BURKHEAD
Insulation 3/18/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 3/29/2022 Partial Approval DAVID BURKHEAD
Insulation 3/29/2022 Partial Approval DAVID BURKHEAD
Insulation 4/19/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 4/26/2022 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 4/28/2022 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 5/18/2022 Approved DAVID BURKHEAD
Pre-Inspection 5/19/2022 Corrections Issued DAVID BURKHEAD
Drywall Nailing 5/20/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 6/2/2022 Partial Approval TED RIES
Masonry Wall/Backfill 7/12/2022 Partial Approval DAVID BURKHEAD
Grading Pre-Inspection 8/9/2022 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 8/24/2022 Approved TED RIES
Pre-Inspection 12/13/2022 Approved DAVID BURKHEAD
Special/Order Compliance 12/14/2022 Corrections Issued DAVID BURKHEAD
Drywall Nailing 12/21/2022 Approved DAVID BURKHEAD
Final 12/21/2022 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 12/21/2022 Approved DAVID BURKHEAD
Green Building Final 12/21/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 12/21/2022 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 12/21/2022 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 12/21/2022 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 12/21/2022 Approved DAVID BURKHEAD
Wood Frame 12/21/2022 Partial Approval DAVID BURKHEAD
Special/Order Compliance 12/22/2022 Corrections Issued DAVID BURKHEAD
Final 12/23/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 12/23/2022 Not Ready for Inspection DAVID BURKHEAD
Smoke Detectors 12/23/2022 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 12/23/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 12/23/2022 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 12/28/2022 Partial Inspection DAVID BURKHEAD
Green Building Final 12/29/2022 Approved DAVID BURKHEAD
Smoke Detectors 12/29/2022 Approved DAVID BURKHEAD
Special/Order Compliance 12/29/2022 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 1/6/2023 Approved DAVID BURKHEAD
Final 1/6/2023 Partial Inspection DAVID BURKHEAD
Wood Frame 1/6/2023 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 1/17/2023 Corrections Issued DAVID BURKHEAD
Final 1/18/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/18/2023 Approved DAVID BURKHEAD
Final 1/23/2023 OK to Issue CofO DAVID BURKHEAD