2528 S GRAND AVE 90007

Certificate Information: 2528 S GRAND AVE 90007

Application / Permit
19010-10000-02385
Plan Check / Job No.
B19LA11603
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
New construction for 7 story residential / mixed use building with 296 apartment units. 5 stories of Type IIIA residential over 2 stories of over ground type IA retail/restaurant (Core and Shell for the Commercial use) and parking.
Permit Issued
Issued on 12/21/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 SALVADOR QUINTANILLA
Corrections Issued 7/8/2019 SALVADOR QUINTANILLA
Quality Review Completed 7/16/2019 GARO TELMI
Applicant returned to address corrections 9/9/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 11/25/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 12/2/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 12/9/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/20/2020 SUEN LIEU
Building Plans Picked Up 7/28/2020 APPLICANT
Plan Check Approved 12/21/2020 SALVADOR QUINTANILLA
Issued 12/21/2020 APPLICANT
Permit Closed-Status Void 1/6/2023 JAMES POWERS
Re-Activate Permit 1/12/2023 JAMES POWERS
TCO Issued (Expire Date: 01-09-2024) 7/13/2023 TED RIES
CofO in Progress 4/9/2024 JAMES POWERS
CofO Issued 4/9/2024 ERNESTO CORRAL
Permit Finaled 4/9/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/8/2019 ELAINE LEI
ZA Case Cleared 8/8/2019 ANNA VAN
Building over 3-story or 36-ft Cleared 9/9/2019 CALOSHA APPROVED
Project located in CRA area Cleared 9/20/2019 JIM URQUHART
Low Impact Development Cleared 11/22/2019 MARTIN FRAGOSO
Green Code Cleared 1/9/2020 SALVADOR QUINTANILLA
Hydrant and Access approval Cleared 2/13/2020 JEREMY CARTER
Roof/Waste drainage to street Cleared 3/2/2020 THOMAS LANG
DAS Clearance Cleared 3/10/2020 SALVADOR QUINTANILLA
Sewer availability Cleared 4/10/2020 THOMAS LANG
Highway dedication Cleared 4/22/2020 CELINA MORENO
Food Service Establishment Cleared 4/27/2020 KENNETH BROWNE
Community Plan Implem. Overlay Cleared 6/2/2020 HELEN JADALI
Community Plan Implem. Overlay Cleared 6/17/2020 EDUARDO HERMOSO
Driveway location Cleared 6/17/2020 EDUARDO HERMOSO
Permit Cleared 6/22/2020 RENZ SORIANO
DCP conditions approval Cleared 7/31/2020 MICHAEL ZIRBES
Density Bonus 12.22.A.25 Cleared 7/31/2020 MICHAEL ZIRBES
Eng Process Fee Ord 176,300 Cleared 8/11/2020 PAMELA TENEZA
Fire Marshall Fire Life Safety Cleared 8/27/2020 MENOA AGHAJANI
Work Adjacent to Public Way Cleared 10/2/2020 ROSA SILVA
"D" conditions Cleared 10/16/2020 SARAHI ORTEGA
"Q" conditions Cleared 10/16/2020 SARAHI ORTEGA
"T" removal Cleared 10/16/2020 SARAHI ORTEGA
CPC Cleared 10/16/2020 SARAHI ORTEGA
Miscellaneous Cleared 10/16/2020 SARAHI ORTEGA
Opn space landscape/Water mgmt Cleared 10/16/2020 SARAHI ORTEGA
Site Plan review Cleared 10/16/2020 SARAHI ORTEGA

Contact Information

Architect Suarez,, Hugo; Lic. No.: C10561 1959 E OAKWOOD STREET      PASADENA, CA 91104
Contractor Wpic Construction Llc; Lic. No.: 1029691-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Tofani,, Glenn David; Lic. No.: C44229 77 BUNSEN      IRVINE, CA 92618
Engineer Tofani,, Glenn David; Lic. No.: GE2496 77 BUNSEN      IRVINE, CA 92618
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 1/11/2021 No Access for Inspection JAMES POWERS
Pre-Inspection 1/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/24/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/24/2021 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 2/24/2021 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 2/24/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/25/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/1/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/4/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/8/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/8/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/11/2021 Approved JAMES POWERS
Deputy Reinf. Masonry 3/11/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/12/2021 Partial Approval JAMES POWERS
Green Building Rough 3/12/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 3/12/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/12/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/12/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/18/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 3/18/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 3/18/2021 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 3/18/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/22/2021 Partial Approval JAMES POWERS
Insulation 3/22/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 3/23/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 3/23/2021 Order to Comply Issued JAMES POWERS
Deputy Reinf. Concrete 3/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/31/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/31/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/1/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/6/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/6/2021 Partial Approval JAMES POWERS
METHANE-Barrier 4/6/2021 Partial Approval JAMES POWERS
METHANE-Subgrade 4/6/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/7/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 4/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/9/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/13/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/13/2021 Partial Approval JAMES POWERS
Insulation 4/13/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/14/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/19/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/22/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/22/2021 Conditional Approval NICK DANERI
Green Building Rough 4/23/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 4/23/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 4/23/2021 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/23/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/26/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 4/26/2021 Conditional Approval JONATHAN QUACH
Reinforced Concrete Frame 4/26/2021 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 4/27/2021 Conditional Approval DANIEL COLLINS
Pre-Inspection 4/27/2021 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 4/27/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/28/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/3/2021 Partial Approval JAMES POWERS
Green Building Rough 5/3/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/3/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/3/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/3/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/5/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/6/2021 Partial Approval JAMES POWERS
Deputy Methane Barrier 5/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/11/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Masonry 5/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/13/2021 Partial Approval JAMES POWERS
Green Building Rough 5/13/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/13/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 5/13/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/13/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 5/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/19/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/19/2021 Partial Approval JAMES POWERS
Green Building Rough 5/19/2021 Approved JAMES POWERS
METHANE-Rough 5/19/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 5/19/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/19/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/24/2021 Partial Approval JAMES POWERS
METHANE-Rough 5/24/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/24/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/24/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/25/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/25/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/28/2021 Partial Approval JAMES POWERS
Insulation 5/28/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/28/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/28/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/28/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/4/2021 Partial Approval JAMES POWERS
METHANE-Rough 6/4/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/4/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/4/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/10/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/25/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 6/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/12/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/15/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/15/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/16/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/21/2021 Partial Approval JAMES POWERS
METHANE-Rough 7/21/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/21/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/21/2021 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 7/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/30/2021 Partial Approval JAMES POWERS
METHANE-Rough 7/30/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/30/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/3/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 8/4/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 8/13/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/17/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 8/17/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/18/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/19/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/20/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 8/20/2021 Partial Approval JAMES POWERS
METHANE-Rough 8/20/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/20/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/20/2021 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 8/23/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/24/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/27/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 8/27/2021 Partial Approval JAMES POWERS
Wood Frame 9/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/8/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/8/2021 Partial Approval JAMES POWERS
METHANE-Rough 9/8/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/8/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/8/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/9/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/14/2021 Partial Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Partial Approval MARK FERRARI
Deputy Steel/Welding 9/16/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/21/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/21/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/23/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/29/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/1/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 10/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/4/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/4/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/6/2021 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 10/6/2021 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 10/7/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/12/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/18/2021 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 10/20/2021 Conditional Approval BRUCE CAMPBELL
Deputy Wood Construction 10/20/2021 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Masonry 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Wood Construction 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 10/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 10/22/2021 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 10/22/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/26/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/27/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/27/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/28/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/28/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/2/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 11/2/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/22/2021 Approved TED RIES
Wood Frame 11/29/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/1/2021 Partial Approval JAMES POWERS
Insulation 12/1/2021 Partial Approval JAMES POWERS
Wood Frame 12/6/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/8/2021 Partial Approval JAMES POWERS
Insulation 12/16/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Partial Approval JAMES POWERS
Insulation 1/12/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/2/2022 Partial Approval JAMES POWERS
Wood Frame 2/2/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval JAMES POWERS
Insulation 2/10/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 2/14/2022 Partial Approval JAMES POWERS
Structural Steel Frame 2/15/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/16/2022 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 2/17/2022 Partial Approval NICK DANERI
Insulation 2/18/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/23/2022 Partial Approval JAMES POWERS
Wood Frame 2/24/2022 Partial Approval JAMES POWERS
Wood Frame 2/24/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Partial Approval JAMES POWERS
Insulation 3/3/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Partial Approval JAMES POWERS
Wood Frame 3/11/2022 Partial Approval JAMES POWERS
Insulation 3/15/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval JAMES POWERS
Wood Frame 3/23/2022 Partial Approval JAMES POWERS
Insulation 3/24/2022 Partial Approval JAMES POWERS
Insulation 4/4/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/4/2022 Partial Approval JAMES POWERS
Wood Frame 4/4/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/5/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/13/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 4/13/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/14/2022 Partial Approval JAMES POWERS
Wood Frame 4/14/2022 Partial Approval JAMES POWERS
Drywall Nailing 4/26/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Not Ready for Inspection JAMES POWERS
Insulation 4/26/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/26/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Partial Approval JAMES POWERS
Insulation 4/27/2022 Partial Approval JAMES POWERS
Insulation 4/28/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 4/28/2022 Partial Approval JAMES POWERS
Insulation 4/29/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/29/2022 Partial Approval JAMES POWERS
Wood Frame 5/4/2022 Partial Approval JAMES POWERS
Insulation 5/6/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/6/2022 Partial Approval JAMES POWERS
Wood Frame 5/6/2022 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 5/9/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/13/2022 Partial Approval JAMES POWERS
Insulation 5/13/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/13/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/18/2022 Partial Approval JAMES POWERS
Insulation 5/18/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/19/2022 Partial Approval JAMES POWERS
Special/Order Compliance 5/20/2022 Partial Approval JAMES POWERS
Special/Order Compliance 5/24/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 5/25/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/26/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/31/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 6/2/2022 Partial Approval JAMES POWERS
Insulation 6/2/2022 Partial Approval JAMES POWERS
Wood Frame 6/2/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 6/3/2022 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 6/3/2022 Partial Approval JAMES POWERS
Wood Frame 6/3/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/8/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/13/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/14/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/15/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/22/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/24/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/24/2022 Partial Approval JAMES POWERS
Insulation 6/29/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/29/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/6/2022 Partial Approval JAMES POWERS
Insulation 7/11/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/13/2022 Partial Approval JAMES POWERS
Insulation 7/13/2022 Partial Approval JAMES POWERS
Insulation 7/18/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/20/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/21/2022 Partial Approval JAMES POWERS
Drywall Nailing 7/26/2022 Partial Approval JAMES POWERS
Insulation 7/26/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/28/2022 Partial Approval JAMES POWERS
Insulation 8/1/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/2/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/3/2022 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 8/8/2022 Partial Approval JAMES POWERS
Drywall Nailing 8/12/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/19/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/12/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/14/2022 Partial Approval JAMES POWERS
Drywall Nailing 9/20/2022 Not Ready for Inspection JAMES POWERS
Insulation 9/20/2022 Partial Approval JAMES POWERS
Drywall Nailing 9/28/2022 Partial Approval JAMES POWERS
Drywall Nailing 10/3/2022 Partial Approval JAMES POWERS
Drywall Nailing 10/7/2022 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/17/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 12/30/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/4/2023 Partial Approval JAMES POWERS
Special/Order Compliance 1/4/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 1/5/2023 Partial Approval JAMES POWERS
Special/Order Compliance 1/6/2023 Partial Inspection JAMES POWERS
Drywall Nailing 1/12/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 1/19/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/19/2023 Partial Approval JAMES POWERS
Drywall Nailing 1/23/2023 Approved JAMES POWERS
Interior/Exterior Lathing 1/27/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/14/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 3/28/2023 Partial Approval JAMES POWERS
Special/Order Compliance 4/7/2023 Partial Approval JAMES POWERS
Pre-Inspection 5/8/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 5/8/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 5/9/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 5/10/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 5/11/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 5/16/2023 Partial Approval JAMES POWERS
Special/Order Compliance 5/17/2023 Partial Approval JAMES POWERS
Special/Order Compliance 5/18/2023 Partial Approval JAMES POWERS
Special/Order Compliance 5/24/2023 Partial Approval JAMES POWERS
Special/Order Compliance 5/25/2023 Partial Approval JAMES POWERS
Special/Order Compliance 6/6/2023 Partial Approval JAMES POWERS
Special/Order Compliance 6/16/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 6/21/2023 Partial Approval JAMES POWERS
Special/Order Compliance 7/20/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 12/12/2023 Approved JAMES POWERS
Final 4/9/2024 OK to Issue CofO JAMES POWERS
Footing/Foundation/Slab 4/9/2024 Approved JAMES POWERS
Green Building Final 4/9/2024 Approved JAMES POWERS
METHANE-Barrier 4/9/2024 Approved JAMES POWERS
METHANE-Final 4/9/2024 Approved JAMES POWERS
METHANE-Rough 4/9/2024 Approved JAMES POWERS
METHANE-Subgrade 4/9/2024 Approved JAMES POWERS
Reinforced Concrete Frame 4/9/2024 Approved JAMES POWERS
Reinforced Masonry Frame 4/9/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/9/2024 SGSOV Approved JAMES POWERS
Smoke Detectors 4/9/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 4/9/2024 Approved JAMES POWERS