640 S ST ANDREWS PL 90010

Certificate Information: 640 S ST ANDREWS PL 90010

Application / Permit
19010-10000-02374
Plan Check / Job No.
B19LA11554
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 8-STORY W/ 2-LEVELS OF SUBTER. PARKING. TOC TIER 3 APARTMENT BUILDING WITH 230 UNITS W/ 23 EXTREMELY LOW INCOME UNITS.
Permit Issued
Issued on 5/20/2022
Issuing Office
Metro
Current Status
Issued on 5/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/24/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 JOE VO
Corrections Issued 7/30/2019 JOE VO
Quality Review Completed 8/5/2019 GARO TELMI
Building Plans Picked Up 8/6/2019 APPLICANT
Applicant returned to address corrections 8/6/2020 JOE VO
Plan Check Approved 2/10/2022 JOE VO
Issued 5/20/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/15/2019 JEANETTE VONG
Permit Cleared 10/11/2019 ERIK BEASLEY
Address approval Cleared 1/23/2020 CELINA MORENO
Highway dedication Cleared 1/28/2020 EMIL KYUPELYAN
Building over 3-story or 36-ft Cleared 1/31/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/31/2020 CALOSHA APPROVED
Metro Rail approval Cleared 2/11/2020 JOE VO
Density Bonus 12.22.A.31 Cleared 3/10/2020 LOUIE MILLER
"Q" conditions Cleared 3/25/2020 KENTON TRINH
"T" removal Cleared 3/25/2020 KENTON TRINH
CPC Cleared 3/25/2020 KENTON TRINH
ZA Case Cleared 3/25/2020 KENTON TRINH
Project located in CRA area Cleared 4/2/2020 GRACIELA ACOSTA
ZI Cleared 4/2/2020 GRACIELA ACOSTA
Frnt yard landscape/Water mgmt Cleared 4/20/2020 KENTON TRINH
Hydrant and Access approval Cleared 6/10/2020 MATTHEW CRAIG
Green Code Cleared 12/28/2020 JOE VO
DAS Clearance Cleared 1/7/2021 JOE VO
Bicycle Parking Cleared 1/14/2021 EDUARDO HERMOSO
Low Impact Development Cleared 2/8/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/9/2021 ELAINE LEI
Bicycle Parking Cleared 2/19/2021 ELAINE LEI
Encroachment in public way Cleared 3/30/2021 ELAINE LEI
Driveway location Cleared 6/18/2021 EDUARDO HERMOSO
Internal circulation Cleared 6/18/2021 EDUARDO HERMOSO
Opn space landscape/Water mgmt Cleared 7/14/2021 KENTON TRINH
Sewer availability Cleared 7/20/2021 JEANIE LAM
Work Adjacent to Public Way Cleared 7/21/2021 BOK GOH
Site Plan review Cleared 7/22/2021 KENTON TRINH
DCP conditions approval Cleared 8/2/2021 LOUIE MILLER
Fire Marshall Fire Life Safety Cleared 12/17/2021 ANDREW KO

Contact Information

Architect Kim,, Mark Sung-Eun; Lic. No.: C31002 1900 MAIN ST. STE 800      IRVINE, CA 92612
Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 1010      LOS ANGELES, CA 90010
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/9/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 6/10/2022 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 7/6/2022 Partial Approval EDWIN GREGORYONA
Pre-Inspection 12/9/2022 Approved EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/24/2023 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/24/2023 Partial Inspection EDWIN GREGORYONA
Deputy Shotcrete 4/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/4/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/5/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 5/19/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/19/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/19/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 5/24/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/24/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/21/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 6/21/2023 Partial Inspection GREGORY POMISH
Green Building Rough 6/22/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 6/22/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 6/22/2023 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 7/12/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 7/12/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/12/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 7/17/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 7/17/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/18/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 7/18/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/18/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 8/3/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/4/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/4/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/10/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 8/10/2023 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 8/11/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 8/11/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/14/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/16/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/21/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/23/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/23/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 8/23/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/23/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 8/24/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/24/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/25/2023 Conditional Approval RAFAEL CORTES
Deputy Shotcrete 8/25/2023 Conditional Approval RAFAEL CORTES
Footing/Foundation/Slab 8/25/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 8/25/2023 Not Ready for Inspection RAFAEL CORTES
Reinforced Concrete Frame 8/25/2023 Partial Approval RAFAEL CORTES
Verify Sprinkler Sign Off 8/25/2023 Not Ready for Inspection RAFAEL CORTES
Deputy Other (see comments) 8/28/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/28/2023 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 8/29/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/30/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 8/30/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/30/2023 Not Ready for Inspection LARRY ARNICK
Green Building Rough 8/30/2023 Off-Hour Fees Due
Reinforced Concrete Frame 8/30/2023 Off-Hour Fees Due
Reinforced Concrete Frame 8/30/2023 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 8/30/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 8/30/2023 Off-Hour Fees Due
Deputy Shotcrete 9/1/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/18/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 9/19/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/22/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/25/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/26/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/26/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/27/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/29/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/4/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/5/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/6/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/10/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/11/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/12/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 10/12/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 10/12/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/12/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 10/13/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 10/13/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/16/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 10/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/18/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/19/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/19/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/19/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/20/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 10/24/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/9/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/9/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 11/9/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 11/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/16/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/27/2023 Conditional Approval GREGORY POMISH
Green Building Rough 11/27/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 11/27/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 11/27/2023 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 11/28/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 11/29/2023 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/30/2023 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 11/30/2023 Not Ready for Inspection GREGORY POMISH
Pre-Inspection 11/30/2023 Not Ready for Inspection GREGORY POMISH
Green Building Rough 12/1/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 12/1/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 12/1/2023 Not Ready for Inspection GREGORY POMISH
Deputy Shotcrete 12/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/6/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/6/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 12/6/2023 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 12/6/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/6/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 12/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 12/14/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/14/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 12/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 12/14/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 12/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 12/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 12/18/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 12/18/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/18/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 12/18/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 12/26/2023 No Access for Inspection MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/2/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/3/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/4/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/5/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/8/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 1/8/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/10/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/12/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/18/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/19/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/23/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/25/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 1/25/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/26/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/26/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/29/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/29/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/30/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 1/31/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/5/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 2/9/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 2/12/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/12/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/13/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/13/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 2/14/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 2/14/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/14/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/14/2024 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/14/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/6/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 3/6/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 3/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 3/12/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/12/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 3/12/2024 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/12/2024 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 3/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 3/14/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 3/26/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 4/4/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/4/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 4/4/2024 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/4/2024 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 4/19/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/19/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/19/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/26/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/26/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/26/2024 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/3/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/3/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/3/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/11/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 6/11/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/11/2024 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/13/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/13/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 6/27/2024 Approved EDWIN GREGORYONA
Wood Frame 7/15/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/18/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 7/18/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/24/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 7/24/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 8/5/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/14/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 8/14/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/27/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 8/27/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/29/2024 Partial Approval JEROME BLACKWOOD
Wood Frame 8/29/2024 Partial Approval JEROME BLACKWOOD
Wood Frame 9/5/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 9/9/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/24/2024 Partial Approval MARTIN TAVITIAN
Green Building Rough 9/24/2024 Partial Approval MARTIN TAVITIAN
Reinforced Concrete Frame 9/24/2024 Partial Approval MARTIN TAVITIAN
Wood Frame 9/24/2024 Partial Approval MARTIN TAVITIAN
Deputy Reinf. Concrete 9/25/2024 Partial Approval JAMES POWERS
Deputy Shotcrete 9/25/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 9/25/2024 Partial Approval JAMES POWERS
Special/Order Compliance 10/2/2024 Approved CHRISTOPHER BLACKWOOD
Wood Frame 10/2/2024 Partial Approval MARTIN TAVITIAN
Special/Order Compliance 10/3/2024 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 10/8/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 10/16/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 10/17/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 11/4/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/5/2024 Not Ready for Inspection EDWIN GREGORYONA
Structural Steel Frame 11/5/2024 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 11/13/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/14/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 11/14/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 11/15/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/18/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/21/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 11/27/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 12/2/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/4/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 12/10/2024 No Access for Inspection EDWIN GREGORYONA
Structural Steel Frame 12/10/2024 No Access for Inspection EDWIN GREGORYONA
Insulation 1/7/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 1/24/2025 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 2/3/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/10/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/12/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 2/13/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/18/2025 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 2/20/2025 Partial Approval EDWIN GREGORYONA
Insulation 2/25/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 2/27/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/6/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 3/6/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 3/7/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 3/7/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 3/11/2025 Partial Approval EDWIN GREGORYONA
Insulation 3/18/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/25/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/1/2025 Partial Approval EDWIN GREGORYONA
Insulation 4/1/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/10/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/17/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/18/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 4/21/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/24/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/1/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/2/2025 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 5/16/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/20/2025 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 5/27/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 6/11/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/24/2025 Partial Approval MARTIN TAVITIAN
Wood Frame 6/25/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/3/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/9/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/22/2025 Corrections Issued EDWIN GREGORYONA
Light Gage Steel Frame 7/22/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/19/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/8/2025 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 10/8/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/24/2025 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 4/21/2026 Partial Approval MARTIN TAVITIAN
Special/Order Compliance 4/29/2026 Approved MARTIN TAVITIAN
Special/Order Compliance 5/26/2026 Approved MARTIN TAVITIAN
Pre-Inspection 6/2/2026 Approved MARTIN TAVITIAN
Special/Order Compliance 6/3/2026 Approved MARTIN TAVITIAN
Pre-Inspection 6/4/2026 Approved MARTIN TAVITIAN
Special/Order Compliance 6/8/2026 Partial Approval MARTIN TAVITIAN