1027 1/2 N BROAD AVE 90744
Certificate Information: 1027 1/2 N BROAD AVE 90744
- Application / Permit
- 19010-10000-02318
- Plan Check / Job No.
- B19LA11290
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY DWELLING 1665 SF WITH ATTACHED 2 CAR GARAGE 549 SF (sprinkler sys NFPA 13D required)
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- Current Status
- CofO Issued on 11/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | MONICA RAMIREZ |
| Corrections Issued | 7/24/2019 | MONICA RAMIREZ |
| Quality Review Completed | 7/31/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 8/2/2019 | APPLICANT |
| Applicant returned to address corrections | 4/27/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 6/30/2020 | MONICA RAMIREZ |
| Plan Check Approved | 7/20/2020 | MONICA RAMIREZ |
| Issued | 8/6/2020 | APPLICANT |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| CofO in Progress | 10/15/2022 | EUGENE CASSIDY |
| Permit Finaled | 11/4/2022 | RONALD MYRICK |
| Permit Finaled | 11/4/2022 | RONALD MYRICK |
| CofO Issued | 11/4/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2019 | JEANIE LAM |
| Sewer availability | Cleared | 8/20/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 12/19/2019 | MITESH PATEL |
| Green Code | Cleared | 2/4/2020 | MONICA RAMIREZ |
| "Q" conditions | Cleared | 5/11/2020 | RICHARD REASER |
| Address approval | Cleared | 5/15/2020 | YEGANEH SADEGHI |
| Hydrant and Access approval | Cleared | 5/22/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 5/27/2020 | YEGANEH SADEGHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Estrada,, Jorge; Lic. No.: C87410 | 1344 CLAREMONT PLACE POMONA, CA 91767 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/18/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 8/18/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 8/18/2020 | Partial Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 8/25/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 8/25/2020 | Approved | JOHN KLARIN |
| METHANE-Barrier | 8/25/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 8/25/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/13/2020 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 11/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 11/30/2020 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 12/3/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/3/2020 | Approved | JOHN KLARIN |
| Insulation | 12/3/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/3/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 12/9/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/9/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/18/2021 | Approved | JOHN KLARIN |
| Final | 6/18/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/18/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 6/18/2021 | Approved | JOHN KLARIN |
| METHANE-Final | 6/18/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 6/18/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2021 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 6/18/2021 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 6/18/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/18/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 8/2/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/2/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/2/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 8/2/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/2/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 8/2/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/27/2022 | Approved | EUGENE CASSIDY |
| Final | 9/27/2022 | OK to Issue CofO | EUGENE CASSIDY |
| PLUMBING-Final | 9/27/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 9/27/2022 | Not Required | EUGENE CASSIDY |