738 E PALMS BLVD 90291

Certificate Information: 738 E PALMS BLVD 90291

Application / Permit
19010-10000-02298
Plan Check / Job No.
B19LA11264
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family dwelling with 3 car garage and 2 story with roof deck.
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 SERGIO GUTIERREZ
Corrections Issued 6/25/2019 SERGIO GUTIERREZ
Quality Review Completed 7/1/2019 KESETE HAREGOT
Building Plans Picked Up 7/10/2019 APPLICANT
Green Plans Picked Up 10/29/2020 APPLICANT
Applicant returned to address corrections 2/22/2021 SERGIO GUTIERREZ
Plan Check Approved 3/26/2021 SERGIO GUTIERREZ
Issued 10/28/2021 APPLICANT
CofO in Progress 5/7/2026 RUBEN RIVAS
Permit Finaled 5/14/2026 RICHARD STEINBACH
CofO Issued 5/14/2026 RICHARD STEINBACH
Permit Finaled 5/14/2026 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 8/29/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 8/29/2019 SOPHIE GABEL-SCHEINBAU
ZI Cleared 8/29/2019 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 9/13/2019 JEANETTE VONG
Green Code Cleared 9/13/2019 NEGAR NEJAD
Hydrant and Access approval Cleared 9/13/2019 JEREMY CARTER
Specific Plan Cleared 9/17/2019 VALERIA CEJA
Sewer availability Cleared 5/20/2020 DINAH GARIN
Low Impact Development Cleared 6/11/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/30/2020 DINAH GARIN
Stormwater Pollution Mitigatn Cleared 7/31/2020 ORVAL HERNANDEZ-MARCI
Specific Plan Cleared 9/1/2020 PEDRO AYALA
Coastal Zone Cleared 9/9/2020 KENTON TRINH
Miscellaneous Cleared 9/9/2020 KENTON TRINH
Specific Plan Cleared 9/9/2020 KENTON TRINH
Specific Plan Cleared 9/9/2020 KENTON TRINH
ZI Cleared 9/9/2020 KENTON TRINH

Contact Information

Contractor Go Building Systems Inc; Lic. No.: 1077471-B 933 26TH STREET      SANTA MONICA, CA 90403
Engineer Scott,, Raymond J; Lic. No.: C14356 44263 CHARLOTTE DR      HEMET, CA 92544
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/26/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 6/6/2022 Conditional Approval JESUS RODRIGUEZ
Sewer 6/6/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/15/2022 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 6/24/2022 Partial Inspection KENNETH NAGLE
Footing/Foundation/Slab 6/27/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 7/5/2022 Partial Approval DAVID FEILER
Footing/Foundation/Slab 7/28/2022 Approved DAVID FEILER
Deputy Drilled-In Anchors 8/25/2022 No Access for Inspection DAVID FEILER
Deputy Wood Construction 8/25/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 4/26/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval EVAN COOPER
HVAC-Rough 5/23/2023 Corrections Issued EVAN COOPER
Wood Frame 6/22/2023 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/11/2023 Approved EVAN COOPER
HVAC-Rough 7/11/2023 Approved EVAN COOPER
PLUMBING-Rough 7/11/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 9/11/2023 Corrections Issued HERBERT GIRON
Green Building Rough 9/11/2023 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 9/11/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/18/2023 Conditional Approval HERBERT GIRON
Green Building Rough 9/18/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 9/18/2023 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 9/28/2023 Corrections Issued HERBERT GIRON
Insulation 9/28/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 10/13/2023 Conditional Approval HERBERT GIRON
Drywall Nailing 10/26/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 4/23/2024 Corrections Issued HERBERT GIRON
Insulation 4/25/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 4/25/2024 Approved HERBERT GIRON
Shower Pan 4/25/2024 Approved HERBERT GIRON
Gas Test 1/30/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 1/30/2025 Partial Approval HERBERT GIRON
Gas Test 2/4/2025 Approved HERBERT GIRON
ELECTRICAL-Final 2/20/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/7/2025 Approved HERBERT GIRON
HVAC-Final 3/11/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/11/2025 Approved JESUS RODRIGUEZ
Service/Power Release 6/24/2025 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 7/1/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/19/2026 Approved RUBEN RIVAS
Final 2/19/2026 Corrections Issued RUBEN RIVAS
Green Building Final 2/19/2026 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Not Required RUBEN RIVAS
Smoke Detectors 2/19/2026 Corrections Issued RUBEN RIVAS
Final 4/23/2026 Corrections Issued RUBEN RIVAS
Smoke Detectors 4/23/2026 Approved RUBEN RIVAS
Final 5/6/2026 OK to Issue CofO RUBEN RIVAS