738 E PALMS BLVD 90291
Certificate Information: 738 E PALMS BLVD 90291
- Application / Permit
- 19010-10000-02298
- Plan Check / Job No.
- B19LA11264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single family dwelling with 3 car garage and 2 story with roof deck.
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 6/25/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/1/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 7/10/2019 | APPLICANT |
| Green Plans Picked Up | 10/29/2020 | APPLICANT |
| Applicant returned to address corrections | 2/22/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/26/2021 | SERGIO GUTIERREZ |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 5/7/2026 | RUBEN RIVAS |
| Permit Finaled | 5/14/2026 | RICHARD STEINBACH |
| CofO Issued | 5/14/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/14/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/29/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 8/29/2019 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 8/29/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/13/2019 | NEGAR NEJAD |
| Hydrant and Access approval | Cleared | 9/13/2019 | JEREMY CARTER |
| Specific Plan | Cleared | 9/17/2019 | VALERIA CEJA |
| Sewer availability | Cleared | 5/20/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 6/11/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/30/2020 | DINAH GARIN |
| Stormwater Pollution Mitigatn | Cleared | 7/31/2020 | ORVAL HERNANDEZ-MARCI |
| Specific Plan | Cleared | 9/1/2020 | PEDRO AYALA |
| Coastal Zone | Cleared | 9/9/2020 | KENTON TRINH |
| Miscellaneous | Cleared | 9/9/2020 | KENTON TRINH |
| Specific Plan | Cleared | 9/9/2020 | KENTON TRINH |
| Specific Plan | Cleared | 9/9/2020 | KENTON TRINH |
| ZI | Cleared | 9/9/2020 | KENTON TRINH |
Contact Information
| Contractor | Go Building Systems Inc; Lic. No.: 1077471-B | 933 26TH STREET SANTA MONICA, CA 90403 |
| Engineer | Scott,, Raymond J; Lic. No.: C14356 | 44263 CHARLOTTE DR HEMET, CA 92544 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/26/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Sewer | 6/6/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/15/2022 | Partial Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 6/24/2022 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/27/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 7/5/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 7/28/2022 | Approved | DAVID FEILER |
| Deputy Drilled-In Anchors | 8/25/2022 | No Access for Inspection | DAVID FEILER |
| Deputy Wood Construction | 8/25/2022 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 4/26/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 5/23/2023 | Corrections Issued | EVAN COOPER |
| Wood Frame | 6/22/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 7/11/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 7/11/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/11/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/11/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/11/2023 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 9/11/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/18/2023 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 9/18/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/18/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/28/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 9/28/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/13/2023 | Conditional Approval | HERBERT GIRON |
| Drywall Nailing | 10/26/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/23/2024 | Corrections Issued | HERBERT GIRON |
| Insulation | 4/25/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/25/2024 | Approved | HERBERT GIRON |
| Shower Pan | 4/25/2024 | Approved | HERBERT GIRON |
| Gas Test | 1/30/2025 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 1/30/2025 | Partial Approval | HERBERT GIRON |
| Gas Test | 2/4/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 2/20/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 3/7/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 3/11/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/11/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 6/24/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 7/1/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/19/2026 | Approved | RUBEN RIVAS |
| Final | 2/19/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 2/19/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Not Required | RUBEN RIVAS |
| Smoke Detectors | 2/19/2026 | Corrections Issued | RUBEN RIVAS |
| Final | 4/23/2026 | Corrections Issued | RUBEN RIVAS |
| Smoke Detectors | 4/23/2026 | Approved | RUBEN RIVAS |
| Final | 5/6/2026 | OK to Issue CofO | RUBEN RIVAS |