728 N SYCAMORE AVE 90038

Certificate Information: 728 N SYCAMORE AVE 90038

Application / Permit
19010-10000-02269
Plan Check / Job No.
B19LA11106
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT WITH TWO-CAR GARAGE PER AB 494 AND SB 229.
Permit Issued
Issued on 3/5/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 6/14/2019 KEVIN MORALES
Corrections Issued 6/18/2019 KEVIN MORALES
Green Plans Picked Up 6/19/2019 APPLICANT
Quality Review Completed 7/1/2019 JOSE RODRIGUEZ
Building Plans Picked Up 7/8/2019 APPLICANT
Plan Check Approved 12/19/2019 KEVIN MORALES
Issued 3/5/2020 LADBS
CofO in Progress 12/10/2022 JOAQUIN GREENOUGH
Permit Finaled 12/15/2022 DEROLD HAUFF
CofO Issued 12/15/2022 DEROLD HAUFF
Permit Finaled 12/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2019 MAHELET GEBEYHU
Construction near power lines Cleared 11/3/2019 RIDWAN HARDY
Low Impact Development Cleared 12/13/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/13/2019 EMIL KYUPELYAN
Green Code Cleared 12/18/2019 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/19/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/19/2019 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/31/2020 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 8/4/2020 Partial Approval BRIAN SULLIVAN
METHANE-Rough 8/18/2020 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 8/18/2020 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 8/26/2020 Corrections Issued BRIAN SULLIVAN
METHANE-Barrier 8/26/2020 Approved BRIAN SULLIVAN
METHANE-Subgrade 8/26/2020 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 9/3/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 9/10/2020 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/7/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 10/7/2020 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Rough 10/7/2020 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 10/7/2020 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 12/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 12/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 12/18/2020 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval BRIAN SULLIVAN
Special/Order Compliance 4/5/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/14/2021 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 6/14/2021 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 6/14/2021 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 6/14/2021 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 6/14/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 6/30/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 6/30/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/31/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 8/31/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 8/31/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 8/31/2021 Not Ready for Inspection RAUL BARAJAS
Insulation 8/31/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 8/31/2021 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 8/31/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 9/2/2021 Partial Approval RAUL BARAJAS
Insulation 9/2/2021 Approved RAUL BARAJAS
Rough-Elec/Plmb/HVAC 9/2/2021 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 9/16/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 9/28/2021 Partial Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 9/30/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 10/6/2021 Approved BRIAN SULLIVAN
Drywall Nailing 10/6/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/6/2021 Approved BRIAN SULLIVAN
Green Building Rough 10/6/2021 Approved BRIAN SULLIVAN
Insulation 10/6/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 10/6/2021 Approved BRIAN SULLIVAN
Drywall Nailing 11/8/2021 Approved BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 11/8/2021 Approved BRIAN SULLIVAN
Underground Mechanical 11/8/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 12/8/2021 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 12/8/2021 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 10/17/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 11/22/2022 Approved JOAQUIN GREENOUGH
Final 11/22/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 11/22/2022 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 11/22/2022 Approved JOAQUIN GREENOUGH
Smoke Detectors 11/22/2022 Approved JOAQUIN GREENOUGH
Final 12/7/2022 OK to Issue CofO JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved JOAQUIN GREENOUGH