728 N SYCAMORE AVE 90038
Certificate Information: 728 N SYCAMORE AVE 90038
- Application / Permit
- 19010-10000-02269
- Plan Check / Job No.
- B19LA11106
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT WITH TWO-CAR GARAGE PER AB 494 AND SB 229.
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2019 | KEVIN MORALES |
| Corrections Issued | 6/18/2019 | KEVIN MORALES |
| Green Plans Picked Up | 6/19/2019 | APPLICANT |
| Quality Review Completed | 7/1/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 7/8/2019 | APPLICANT |
| Plan Check Approved | 12/19/2019 | KEVIN MORALES |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 12/10/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/15/2022 | DEROLD HAUFF |
| CofO Issued | 12/15/2022 | DEROLD HAUFF |
| Permit Finaled | 12/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2019 | MAHELET GEBEYHU |
| Construction near power lines | Cleared | 11/3/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/13/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 12/18/2019 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/19/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/31/2020 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 8/4/2020 | Partial Approval | BRIAN SULLIVAN |
| METHANE-Rough | 8/18/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Subgrade | 8/18/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/26/2020 | Corrections Issued | BRIAN SULLIVAN |
| METHANE-Barrier | 8/26/2020 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 8/26/2020 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/3/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/10/2020 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/7/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Rough | 10/7/2020 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 10/7/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 12/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 12/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 12/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 12/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2021 | Partial Approval | BRIAN SULLIVAN |
| Special/Order Compliance | 4/5/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/14/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/14/2021 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 6/14/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/14/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 6/30/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 8/31/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/2/2021 | Partial Approval | RAUL BARAJAS |
| Insulation | 9/2/2021 | Approved | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 9/2/2021 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 9/16/2021 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/28/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 9/30/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 10/6/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/6/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/6/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 10/6/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/6/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 11/8/2021 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 11/8/2021 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 11/8/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/8/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 12/8/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 10/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 11/22/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 11/22/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 11/22/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 11/22/2022 | Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/22/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 12/7/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Approved | JOAQUIN GREENOUGH |