705 N BENTON WAY 90026
Certificate Information: 705 N BENTON WAY 90026
- Application / Permit
- 19010-10000-02201
- Plan Check / Job No.
- B19LA10768
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING W/ATTACHED 2-CAR GARAGE. (2 OF 3)
- Permit Issued
- Issued on 8/30/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | KEVIN MORALES |
| Corrections Issued | 6/27/2019 | KEVIN MORALES |
| Green Plans Picked Up | 6/27/2019 | APPLICANT |
| Quality Review Completed | 7/20/2019 | YOUNG KIM |
| Building Plans Picked Up | 7/26/2019 | APPLICANT |
| Plan Check Approved | 8/27/2019 | KEVIN MORALES |
| Issued | 8/30/2019 | LADBS |
| CofO in Progress | 9/28/2021 | ROBERT VORHIS |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/10/2019 | KARAN PATEL |
| BHO/Hillside ordinance | Cleared | 7/10/2019 | KARAN PATEL |
| BHO/Hillside ordinance | Cleared | 7/10/2019 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2019 | KARAN PATEL |
| Hydrant and Access approval | Cleared | 7/11/2019 | JOHN CONNEALLY |
| Green Code | Cleared | 8/21/2019 | KEVIN MORALES |
| BHO/Hillside ordinance | Cleared | 8/22/2019 | ELAINE LEI |
| Frnt yard landscape/Water mgmt | Cleared | 8/22/2019 | DIANA JIMENEZ |
| GPI Written Notices | Cleared | 8/22/2019 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 8/22/2019 | KEVIN MORALES |
| Low Impact Development | Cleared | 8/22/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/22/2019 | ELAINE LEI |
| Sewer availability | Cleared | 8/22/2019 | ELAINE LEI |
Contact Information
| Architect | Gold,, Kerry Daniel; Lic. No.: C13781 | 638 LINDERO CYN RD # 432 OAK PARK, CA 91377 |
| Contractor | M R Handyman Service; Lic. No.: 798417-B | 8038 OAKDALE AVE WINNETKA, CA 91306 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/8/2019 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/8/2019 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Barrier | 11/8/2019 | Approved | ROBERT VORHIS |
| METHANE-Subgrade | 11/8/2019 | Approved | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 1/21/2020 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 3/27/2020 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 3/27/2020 | Partial Approval | ROBERT VORHIS |
| Deputy Wood Construction | 4/3/2020 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2020 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2020 | No Access for Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 4/24/2020 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Gas Test | 6/19/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/19/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/9/2020 | Partial Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Corrections Issued | ROBERT VORHIS |
| HVAC-Rough | 7/24/2020 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 8/6/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2020 | Partial Approval | ROBERT VORHIS |
| HVAC-Rough | 8/6/2020 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 8/12/2020 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 8/12/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 8/12/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| MERV13>=Rough | 8/12/2020 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 8/12/2020 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 8/12/2020 | Approved | JOSEPH MCGARRY |
| Wood Frame | 8/12/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/25/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 9/15/2020 | Partial Approval | ROBERT VORHIS |
| Interior/Exterior Lathing | 9/15/2020 | Partial Approval | ROBERT VORHIS |
| Insulation | 9/22/2020 | Conditional Approval | ROBERT VORHIS |
| BUILDING-Rough-Frame | 10/5/2020 | Corrections Issued | DONALD CRICHLOW |
| Drywall Nailing | 10/5/2020 | Corrections Issued | DONALD CRICHLOW |
| Insulation | 10/8/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/15/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 10/15/2020 | Approved | ROBERT VORHIS |
| Gas Test | 4/14/2021 | Approved | ROBERT VORHIS |
| HVAC-Final | 4/14/2021 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Final | 4/14/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Final | 4/19/2021 | Approved | ROBERT VORHIS |
| Final | 4/19/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 4/19/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 4/19/2021 | Not Ready for Inspection | ROBERT VORHIS |
| MERV13>=Final | 4/19/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Approved | ROBERT VORHIS |
| Service/Power Release | 4/19/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Smoke Detectors | 4/19/2021 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 5/26/2021 | Off-Hour Fees Due | |
| HVAC-Final | 5/26/2021 | Off-Hour Fees Due | |
| PLUMBING-Final | 5/26/2021 | Off-Hour Fees Due | |
| Green Building Final | 5/28/2021 | Approved | ROBERT VORHIS |
| HVAC-Final | 5/28/2021 | Corrections Issued | ROBERT VORHIS |
| PLUMBING-Final | 5/28/2021 | Approved | ROBERT VORHIS |
| Final | 6/8/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Service/Power Release | 6/8/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 7/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 7/14/2021 | Approved | STUART CHAPMAN |
| Service/Power Release | 7/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 8/11/2021 | Partial Inspection | CALEB MEISTER |
| Final | 9/28/2021 | Conditional Approval | ROBERT VORHIS |
| Service/Power Release | 9/28/2021 | Approved | ROBERT VORHIS |