6658 W FRANKLIN AVE 90028

Certificate Information: 6658 W FRANKLIN AVE 90028

Application / Permit
19010-10000-02186
Plan Check / Job No.
B19LA10708
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5 STORY 64 UNITS 15% (10 UNITS VLI) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA OVER 1 LEVEL TYPE IA SUBTERRANEAN PARKING, 12.22 A25 WITH ADDITIONAL INCENTIVES (SENIOR FACILITY).
Permit Issued
Issued on 9/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 9/2/2022 KEVIN MORALES
Issued 9/12/2022 APPLICANT
TCO Issued (Expire Date: 10-26-2025) 4/29/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 04-25-2026) 10/27/2025 ADAM BURGESS
Permit Finaled 11/5/2025 ADAM BURGESS
CofO Issued 11/5/2025 ADAM BURGESS
Permit Finaled 11/5/2025 ADAM BURGESS

Permit Application Clearance Information

Address approval Cleared 1/19/2022 STEVE MELGAR
City Hist. Cultural Monument Cleared 2/3/2022 LAMBERT GIESSINGER
Historic Resource Verification Cleared 2/3/2022 LAMBERT GIESSINGER
Historic monument Cleared 2/3/2022 LAMBERT GIESSINGER
Green Code Cleared 3/10/2022 KEVIN MORALES
Building over 36-ft Cleared 3/22/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/22/2022 CALOSHA APPROVED
Sewer availability Cleared 3/24/2022 JEANIE LAM
Highway dedication Cleared 4/1/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/5/2022 STEVE MELGAR
Hydrant and Access approval Cleared 4/25/2022 MATTHEW CRAIG
Grading Pre-Inspection Cleared 4/27/2022 KEVIN MORALES
Bicycle Parking Cleared 5/4/2022 JEREMY CHOK
Density Bonus 12.22.A.25 Cleared 5/10/2022 RICHARD TRUONG
GPI Written Notices Cleared 5/25/2022 KEVIN MORALES
Low Impact Development Cleared 6/3/2022 ANDRES COVARRUBIAS
Permit Cleared 6/3/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 6/3/2022 WALLIE JONG
Haul Route Cleared 6/7/2022 KEVIN MORALES
Trees in Parkway Cleared 6/16/2022 ADALBERTO VERA
Work Adjacent to Public Way Cleared 7/19/2022 KHOUNG LE
Fire Marshal Fire Life Safety Cleared 8/8/2022 MENOA AGHAJANI
Public Housing Cleared 8/11/2022 GUS VINDELL
"Q" conditions Cleared 8/30/2022 MARITZA PRZEKOP
CPC Cleared 8/30/2022 MARITZA PRZEKOP
DAS Clearance Cleared 8/30/2022 KEVIN MORALES
Frnt yard landscape/Water mgmt Cleared 8/30/2022 MARITZA PRZEKOP
Miscellaneous Cleared 8/30/2022 MARITZA PRZEKOP
Opn space landscape/Water mgmt Cleared 8/30/2022 MARITZA PRZEKOP
Site Plan review Cleared 8/30/2022 MARITZA PRZEKOP
Tract Map conditions Cleared 8/30/2022 MAYELA VILLA
Tract Map conditions Cleared 8/30/2022 MAYELA VILLA
ZA Case Cleared 8/30/2022 MAYELA VILLA
ZA Case Cleared 8/30/2022 MAYELA VILLA
Tract Map conditions Cleared 8/31/2022 KENTON TRINH
Miscellaneous Cleared 9/1/2022 MARITZA PRZEKOP
Redevelopment Project Area Cleared 9/1/2022 DAVID URITA

Contact Information

Architect Withee,, Dan Richard; Lic. No.: C9049 2251 W 190TH STREET      TORRANCE, CA 90504
Contractor Lena Construction Inc; Lic. No.: 1073212-B 1112 S SAN JULIAN ST      LOS ANGELES, CA 90015
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Harris,, William Donald; Lic. No.: S5121 26344 DUNWOOD RD      ROLLING HILLS ESTATES, CA 90274
Engineer Labib,, Youhanna T.; Lic. No.: S4549       ,
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/2/2022 Approved JAMES POWERS
Pre-Inspection 2/23/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/17/2023 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 3/17/2023 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/12/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 4/12/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/12/2023 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 4/12/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 4/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/27/2023 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 4/27/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 4/28/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/28/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 5/3/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/5/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 5/5/2023 Partial Approval GREGORY POMISH
Deputy Shotcrete 5/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/12/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/12/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/15/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 5/15/2023 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/16/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/17/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/18/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 5/18/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/18/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 6/21/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/21/2023 Partial Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 6/30/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/3/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/14/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/14/2023 Partial Approval DAVID BURKHEAD
Drywall Nailing 7/18/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/25/2023 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 8/8/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/11/2023 Conditional Approval DAVID BURKHEAD
Deputy Wood Construction 8/23/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 9/6/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/20/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/1/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 11/1/2023 Partial Approval DAVID BURKHEAD
Insulation 11/8/2023 Partial Approval EDWIN GREGORYONA
Insulation 11/13/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Partial Approval EDWIN GREGORYONA
Insulation 11/27/2023 Partial Approval LUIS CCAMACHO
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 1/29/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 2/16/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 2/23/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Partial Inspection JEFFREY FULTON
Insulation 2/27/2024 Not Ready for Inspection JEFFREY FULTON
Deputy Wood Construction 3/4/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Approval EDWIN GREGORYONA
Insulation 3/4/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Approval EDWIN GREGORYONA
Insulation 3/11/2024 Partial Inspection EDWIN GREGORYONA
Insulation 3/19/2024 Partial Inspection DAVID BURKHEAD
Drywall Nailing 4/2/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 4/2/2024 Partial Approval DAVID BURKHEAD
Reinforced Concrete Frame 4/4/2024 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/4/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 4/5/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 4/5/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 4/10/2024 Partial Inspection EDWIN GREGORYONA
Insulation 4/10/2024 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/10/2024 Partial Inspection EDWIN GREGORYONA
Insulation 4/24/2024 Partial Approval DAVID BURKHEAD
Insulation 4/26/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/29/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 4/29/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 4/29/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 5/3/2024 Partial Approval DAVID BURKHEAD
Insulation 5/8/2024 Partial Approval DAVID BURKHEAD
Insulation 5/10/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 5/14/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 5/15/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 5/15/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 5/15/2024 Partial Approval DAVID BURKHEAD
Wood Frame 5/15/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 5/17/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/17/2024 Partial Approval DAVID BURKHEAD
Wood Frame 5/17/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/20/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 5/20/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/22/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/22/2024 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/22/2024 Approved EDWIN GREGORYONA
Wood Frame 5/22/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 5/24/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/30/2024 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 5/30/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 6/4/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 6/4/2024 Partial Approval EDWIN GREGORYONA
Insulation 6/5/2024 Partial Approval JACOB MYERS
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 6/17/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/24/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/27/2024 Partial Inspection DAVID BURKHEAD
Pre-Inspection 7/3/2024 Approved DAVID BURKHEAD
Drywall Nailing 7/16/2024 Not Ready for Inspection EDWIN GREGORYONA
Structural Steel Frame 7/16/2024 Not Ready for Inspection EDWIN GREGORYONA
Wall Anchors 7/19/2024 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/2/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 8/2/2024 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 8/5/2024 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 8/8/2024 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Approval DAVID BURKHEAD
Insulation 8/10/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/10/2024 Off-Hour Fees Due
Drywall Nailing 8/12/2024 Partial Approval EDWIN GREGORYONA
Insulation 8/12/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/12/2024 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 No Access for Inspection MARTIN TAVITIAN
Insulation 8/19/2024 No Access for Inspection MARTIN TAVITIAN
Drywall Nailing 9/9/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/9/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/26/2024 Partial Approval DAVID BURKHEAD
Reinforced Masonry Frame 9/26/2024 Partial Inspection DAVID BURKHEAD
Drywall Nailing 10/1/2024 Partial Approval DAVID BURKHEAD
Insulation 10/1/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 10/1/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 10/3/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/7/2024 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 10/16/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 10/18/2024 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 10/18/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 10/18/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 10/23/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/31/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 11/6/2024 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/4/2024 Partial Approval DAVID BURKHEAD
Wood Frame 12/4/2024 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 12/12/2024 Approved DAVID BURKHEAD
Reinforced Concrete Frame 12/31/2024 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 1/22/2025 Partial Approval EDWIN GREGORYONA
Pre-Inspection 2/7/2025 Approved DAVID BURKHEAD
Pre-Inspection 2/28/2025 Approved DAVID BURKHEAD
Pre-Inspection 3/6/2025 Partial Inspection DAVID BURKHEAD
Drywall Nailing 3/20/2025 Approved DAVID BURKHEAD
Final 3/20/2025 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 3/20/2025 Approved DAVID BURKHEAD
Green Building Final 3/20/2025 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/20/2025 Conditional Approval DAVID BURKHEAD
Reinforced Masonry Frame 3/20/2025 Conditional Approval DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 3/20/2025 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 3/20/2025 Not Ready for Inspection DAVID BURKHEAD
Verify Rec and Parks Fee Memo 3/20/2025 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/20/2025 Conditional Approval DAVID BURKHEAD
Pre-Inspection 3/21/2025 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved DAVID BURKHEAD
Final 4/16/2025 Not Ready for Inspection DAVID BURKHEAD
Green Building Final 4/16/2025 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/16/2025 Conditional Approval DAVID BURKHEAD
Reinforced Masonry Frame 4/16/2025 Conditional Approval DAVID BURKHEAD
Smoke Detectors 4/16/2025 Approved DAVID BURKHEAD
Wood Frame 4/16/2025 Conditional Approval DAVID BURKHEAD
Final 4/18/2025 Partial Inspection DAVID BURKHEAD
Green Building Final 4/18/2025 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 4/18/2025 Conditional Approval DAVID BURKHEAD
Reinforced Masonry Frame 4/18/2025 Conditional Approval DAVID BURKHEAD
Wood Frame 4/18/2025 Approved DAVID BURKHEAD
Pre-Inspection 4/24/2025 Approved EDWIN GREGORYONA
Final 4/29/2025 OK for TCO DAVID BURKHEAD
Green Building Final 4/29/2025 Approved DAVID BURKHEAD
Reinforced Concrete Frame 4/29/2025 Approved DAVID BURKHEAD
Reinforced Masonry Frame 4/29/2025 Approved DAVID BURKHEAD
Pre-Inspection 5/29/2025 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/10/2025 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 9/30/2025 Approved DAVID BURKHEAD