1637 N BRUCE CT 90026

Certificate Information: 1637 N BRUCE CT 90026

Application / Permit
19010-10000-02115
Plan Check / Job No.
B19LA10439
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 11/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 6/6/2019 EMMANUEL MARTINEZ
Corrections Issued 6/11/2019 EMMANUEL MARTINEZ
Quality Review Completed 6/17/2019 JOSE RODRIGUEZ
Building Plans Picked Up 6/19/2019 APPLICANT
Green Plans Picked Up 7/2/2019 APPLICANT
Applicant returned to address corrections 8/27/2019 EMMANUEL MARTINEZ
Applicant returned to address corrections 10/29/2019 EMMANUEL MARTINEZ
Applicant returned to address corrections 10/13/2020 VU NGUYEN
Applicant returned to address corrections 10/23/2020 VU NGUYEN
Applicant returned to address corrections 10/29/2020 VU NGUYEN
Plan Check Approved 2/26/2021 VU NGUYEN
Issued 9/17/2021 APPLICANT
CofO in Progress 11/7/2024 BRENDAN MORELLI
Permit Finaled 11/16/2024 DEROLD HAUFF
CofO Issued 11/16/2024 DEROLD HAUFF
Permit Finaled 11/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 7/30/2019 JOHN KIM
Permit Cleared 8/2/2019 LINDA MARGARET
Eng Process Fee Ord 176,300 Cleared 10/31/2019 JEANIE LAM
Hydrant and Access approval Cleared 11/5/2019 JEREMY CARTER
Low Impact Development Cleared 11/5/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 11/5/2019 THOMAS LANG
Sewer availability Cleared 11/5/2019 JEANIE LAM
Stormwater Pollution Mitigatn Cleared 11/5/2019 RYAN HUDSON
Green Code Cleared 12/16/2019 KHEDER ALRAZAA
GPI Written Notices Cleared 8/11/2020 EMMANUEL MARTINEZ
Grading Pre-Inspection Cleared 8/11/2020 EMMANUEL MARTINEZ
Building over 3-story or 36-ft Cleared 8/13/2020 CALOSHA APPROVED
Address approval Cleared 8/17/2020 ELAINE LEI
Disturb/Remove Protected Trees Cleared 9/16/2020 STEPHEN DUPREY

Contact Information

Architect Texter,, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Planet Home Development Inc; Lic. No.: 975236-B 1048 IRVINE AVENUE #421      NEWPORT BEACH, CA 92660
Engineer Morris,, Kyle Byron; Lic. No.: C72911 1401 DOVE ST STE 520      NEWPORT BEACH, CA 92660
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/18/2021 Not Ready for Inspection ROBERT VORHIS
Deputy Reinf. Concrete 11/23/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 11/23/2021 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 11/23/2021 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/30/2021 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 12/1/2021 Approved CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 12/1/2021 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 12/1/2021 Approved CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 12/6/2021 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/4/2022 Corrections Issued CRAIG DAVIS
Underground Mechanical 1/4/2022 Not Ready for Inspection CRAIG DAVIS
Deputy Wood Construction 1/10/2022 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/11/2022 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/19/2022 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/21/2022 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/26/2022 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 3/9/2022 Conditional Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 4/11/2022 Partial Approval CRAIG DAVIS
Underground Mechanical 4/15/2022 Partial Approval CRAIG DAVIS
Wood Frame 4/22/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/2/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/11/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 6/7/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Conditional Approval SCOTT FINNILA
Sewer 11/4/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 11/16/2022 Approved STUART CHAPMAN
PLUMBING-Rough 11/16/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 1/19/2023 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 1/19/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/19/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 1/19/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 1/19/2023 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/24/2023 Conditional Approval ALIZAH MAYAGOITIA
Insulation 1/24/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/6/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/15/2023 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/1/2023 Approved ALIZAH MAYAGOITIA
Pre-Inspection 5/2/2023 Partial Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/1/2023 Partial Approval ALIZAH MAYAGOITIA
HVAC-Final 11/1/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 11/1/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 12/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 12/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 12/1/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 1/3/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/14/2024 Approved BRENDAN MORELLI
HVAC-Final 2/14/2024 Not Ready for Inspection BRENDAN MORELLI
Service/Power Release 2/14/2024 Approved BRENDAN MORELLI
Gas Test 5/1/2024 Approved JOSEPH MCGARRY
HVAC-Final 5/1/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 5/1/2024 Approved JOSEPH MCGARRY
Pre-Inspection 10/22/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved BRENDAN MORELLI
BUILDING-Rough-Frame 11/7/2024 Approved BRENDAN MORELLI
Final 11/7/2024 OK to Issue CofO BRENDAN MORELLI
Green Building Final 11/7/2024 Approved BRENDAN MORELLI
Smoke Detectors 11/7/2024 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 11/7/2024 Approved BRENDAN MORELLI