1641 N BRUCE CT 90026
Certificate Information: 1641 N BRUCE CT 90026
- Application / Permit
- 19010-10000-02112
- Plan Check / Job No.
- B19LA10434
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW CONSTRUCTION - SINGLE FAMILY DWELLING. TRACT 3634, LOT 30, (3)-STORY WITH GARAGE.
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Issued on 11/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 6/11/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/19/2019 | KESETE HAREGOT |
| Green Plans Picked Up | 7/2/2019 | APPLICANT |
| Plan Check Approved | 3/5/2021 | SERGIO GUTIERREZ |
| Issued | 9/17/2021 | APPLICANT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| CofO in Progress | 11/7/2024 | BRENDAN MORELLI |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
| CofO Issued | 11/16/2024 | DEROLD HAUFF |
| Permit Finaled | 11/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2019 | ELAINE LEI |
| Trees in Parkway | Cleared | 7/30/2019 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 11/5/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | THOMAS LANG |
| Stormwater Pollution Mitigatn | Cleared | 11/5/2019 | RYAN HUDSON |
| Permit | Cleared | 8/19/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/19/2020 | CECILIO NAVARRO |
| Miscellaneous | Cleared | 8/24/2020 | SAM NAVID |
| Hydrant and Access approval | Cleared | 12/11/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 3/3/2021 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 3/3/2021 | SERGIO GUTIERREZ |
| Building over 3-story or 36-ft | Cleared | 3/5/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 3/5/2021 | CALOSHA APPROVED |
| Green Code | Cleared | 3/5/2021 | KHEDER ALRAZAA |
Contact Information
| Architect | Texter,, Christopher S; Lic. No.: C25901 | 2 BUELLTON IRVINE, CA 92602 |
| Contractor | Planet Home Development Inc; Lic. No.: 975236-B | 1048 IRVINE AVENUE #421 NEWPORT BEACH, CA 92660 |
| Engineer | Morris,, Kyle Byron; Lic. No.: C72911 | 1401 DOVE ST STE 520 NEWPORT BEACH, CA 92660 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/18/2021 | Approved | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/9/2021 | Partial Approval | CRAIG DAVIS |
| Deputy Reinf. Concrete | 12/10/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 12/13/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/9/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 2/10/2022 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 2/17/2022 | Conditional Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 3/16/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Partial Approval | CRAIG DAVIS |
| Deputy Reinf. Concrete | 3/22/2022 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Partial Approval | CRAIG DAVIS |
| Deputy Reinf. Concrete | 4/12/2022 | Conditional Approval | CRAIG DAVIS |
| Underground Mechanical | 4/15/2022 | Partial Approval | CRAIG DAVIS |
| Wood Frame | 4/22/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/2/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/11/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/7/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | SCOTT FINNILA |
| Special/Order Compliance | 6/27/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Conditional Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Sewer | 11/4/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/16/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/16/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/19/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 1/19/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/19/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/19/2023 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 1/19/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/24/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Insulation | 1/24/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/10/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 2/15/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/15/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 2/15/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/1/2023 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 5/2/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 9/20/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/14/2024 | Approved | BRENDAN MORELLI |
| HVAC-Final | 2/14/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Final | 2/14/2024 | Approved | BRENDAN MORELLI |
| Service/Power Release | 2/14/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 5/1/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 5/1/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 5/1/2024 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 10/22/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | BRENDAN MORELLI |
| Final | 11/7/2024 | OK to Issue CofO | BRENDAN MORELLI |
| Footing/Foundation/Slab | 11/7/2024 | Approved | BRENDAN MORELLI |
| Green Building Final | 11/7/2024 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 11/7/2024 | Approved | BRENDAN MORELLI |