1649 N BRUCE CT 90026

Certificate Information: 1649 N BRUCE CT 90026

Application / Permit
19010-10000-02109
Plan Check / Job No.
B19LA10427
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPSOED 3-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 7/23/2021
Issuing Office
Current Status
CofO Issued on 1/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 6/6/2019 MICHAEL LOPEZ
Corrections Issued 6/10/2019 MICHAEL LOPEZ
Quality Review Completed 6/17/2019 KESETE HAREGOT
Building Plans Picked Up 6/19/2019 APPLICANT
Green Plans Picked Up 7/2/2019 APPLICANT
Applicant returned to address corrections 11/18/2019 MICHAEL LOPEZ
Applicant returned to address corrections 1/7/2020 MICHAEL LOPEZ
Applicant returned to address corrections 9/3/2020 MICHAEL LOPEZ
Applicant returned to address corrections 11/9/2020 MICHAEL LOPEZ
Applicant returned to address corrections 3/2/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/28/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/29/2021 MICHAEL LOPEZ
Plan Check Approved 7/1/2021 MICHAEL LOPEZ
Issued 7/23/2021 APPLICANT
CofO in Progress 1/3/2025 BRENDAN MORELLI
Permit Finaled 1/3/2025 DEROLD HAUFF
Permit Finaled 1/3/2025 DEROLD HAUFF
CofO Issued 1/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/25/2019 ELAINE LEI
Trees in Parkway Cleared 7/30/2019 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 8/2/2019 JEANETTE VONG
Permit Cleared 8/2/2019 LINDA MARGARET
Roof/Waste drainage to street Cleared 8/2/2019 LINDA MARGARET
Low Impact Development Cleared 11/19/2019 RYAN HUDSON
Green Code Cleared 1/23/2020 KHEDER ALRAZAA
Sewer availability Cleared 5/21/2020 CELINA MORENO
GPI Written Notices Cleared 8/18/2020 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 8/18/2020 MICHAEL LOPEZ
Miscellaneous Cleared 8/24/2020 SAM NAVID
Excavation more than 5-ft deep Cleared 9/3/2020 CALOSHA APPROVED
Hydrant and Access approval Cleared 9/25/2020 KURT CORRAL

Contact Information

Architect Texter,, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Planet Home Development Inc; Lic. No.: 975236-B 1048 IRVINE AVENUE #421      NEWPORT BEACH, CA 92660
Engineer Morris,, Kyle Byron; Lic. No.: C72911 1401 DOVE ST STE 520      NEWPORT BEACH, CA 92660
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/23/2021 Conditional Approval THOMAS LOGRASSO
Underground Mechanical 12/6/2021 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 1/10/2022 Partial Approval CRAIG DAVIS
Deputy Reinf. Concrete 1/11/2022 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 2/14/2022 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 2/17/2022 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 3/2/2022 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 3/17/2022 Partial Approval CRAIG DAVIS
Deputy Reinf. Concrete 3/22/2022 Conditional Approval CRAIG DAVIS
Deputy Reinf. Concrete 4/12/2022 Conditional Approval CRAIG DAVIS
Wood Frame 4/22/2022 Not Ready for Inspection STUART CHAPMAN
Wood Frame 4/28/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/3/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/4/2022 Partial Approval STUART CHAPMAN
Underground Mechanical 5/4/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/23/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/1/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/13/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 1/20/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/20/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 1/20/2023 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/6/2023 Conditional Approval ALIZAH MAYAGOITIA
Green Building Rough 2/6/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 2/6/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 2/8/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/15/2023 Approved ALIZAH MAYAGOITIA
Insulation 2/15/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/24/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/8/2023 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/1/2023 Approved ALIZAH MAYAGOITIA
Gas Test 9/20/2023 Approved ALIZAH MAYAGOITIA
Sewer 10/5/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 3/14/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 3/14/2024 Approved JOSEPH MCGARRY
Service/Power Release 3/14/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Final 5/2/2024 Approved JOSEPH MCGARRY
HVAC-Final 5/2/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 5/2/2024 Approved JOSEPH MCGARRY
Pre-Inspection 10/22/2024 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved BRENDAN MORELLI
Final 11/7/2024 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 11/7/2024 Approved BRENDAN MORELLI
Green Building Final 11/7/2024 Approved BRENDAN MORELLI
Smoke Detectors 11/7/2024 Approved BRENDAN MORELLI
Final 12/17/2024 Conditional Approval BRENDAN MORELLI
Final 1/3/2025 OK to Issue CofO BRENDAN MORELLI