801-801 1/2 E MANCHESTER AVE 90001

Certificate Information: 801-801 1/2 E MANCHESTER AVE 90001

Application / Permit
19010-10000-02077
Plan Check / Job No.
B19LA10294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW (2)-STORY DUPLEX W/ ATTACHED GARAGE.
Permit Issued
Issued on 12/14/2020
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2019 APPLICANT
Assigned to Plan Check Engineer 6/6/2019 KEVIN MORALES
Corrections Issued 6/11/2019 KEVIN MORALES
Quality Review Completed 6/17/2019 JOSE RODRIGUEZ
Green Plans Picked Up 6/17/2019 APPLICANT
Plan Check Approved 8/18/2020 KEVIN MORALES
Issued 12/14/2020 APPLICANT
Building Plans Picked Up 1/20/2021 APPLICANT
CofO in Progress 8/25/2022 ENRIQUE MIRELES
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 6/25/2019 EDUARDO HERMOSO
Community Plan Implem. Overlay Cleared 7/22/2019 JOHN KIM
Address approval Cleared 10/4/2019 THOMAS LANG
Green Code Cleared 10/11/2019 DONALD CRICHLOW
Community Plan Implem. Overlay Cleared 11/3/2019 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 11/26/2019 STEVE GARCIA
ZI Cleared 11/26/2019 STEVE GARCIA
Community Plan Implem. Overlay Cleared 12/6/2019 THAN WIN
Eng Process Fee Ord 176,300 Cleared 12/6/2019 THAN WIN
Low Impact Development Cleared 12/6/2019 RYAN HUDSON
Sewer availability Cleared 12/6/2019 THAN WIN
Roof/Waste drainage to street Cleared 12/13/2019 THOMAS LANG
Hydrant and Access approval Cleared 1/9/2020 GEORGE SUCHAND
ZI Cleared 7/24/2020 GRACIELA ACOSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 482-0325 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2021 Corrections Issued EUGENE CASSIDY
Pre-Inspection 4/16/2021 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 4/16/2021 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 4/20/2021 Approved EUGENE CASSIDY
Underground Mechanical 4/20/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 6/14/2021 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 6/14/2021 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/26/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 9/9/2021 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 10/12/2021 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 11/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/9/2021 Approved SABAS ALONSO
Deputy Wood Construction 12/10/2021 Conditional Approval JOAQUIN GREENOUGH
PLUMBING-Rough 12/14/2021 Conditional Approval ADAM ESCOTO
HVAC-Rough 12/22/2021 Corrections Issued ADAM ESCOTO
PLUMBING-Rough 12/22/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 12/29/2021 Partial Approval HORACE FULTZ
HVAC-Rough 12/29/2021 Approved HORACE FULTZ
Insulation 1/12/2022 Conditional Approval FREDDIE RIVERA
Pre-Inspection 1/12/2022 Corrections Issued FREDDIE RIVERA
Insulation 1/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Drywall Nailing 2/4/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 2/4/2022 Not Ready for Inspection LILIANA PORTILLO
Insulation 2/4/2022 Approved LILIANA PORTILLO
Drywall Nailing 2/10/2022 Conditional Approval ALIZAH MAYAGOITIA
Green Building Rough 2/10/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/23/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 5/23/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 5/23/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/3/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Final 6/3/2022 Corrections Issued HORACE FULTZ
HVAC-Final 6/3/2022 Corrections Issued HORACE FULTZ
PLUMBING-Final 6/3/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Final 6/17/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Final 6/17/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Final 6/17/2022 Corrections Issued SHAVONNE ESPINOZA
Special/Order Compliance 6/17/2022 Partial Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 6/20/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Drywall Nailing 6/20/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Final 6/20/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 6/20/2022 Approved SHAVONNE ESPINOZA
Green Building Final 6/20/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Rough 6/20/2022 Not Ready for Inspection SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 6/20/2022 SGSOV Not Ready SHAVONNE ESPINOZA
Service/Power Release 6/20/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Smoke Detectors 6/20/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Verify Sprinkler Sign Off 6/20/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 7/5/2022 Corrections Issued HORACE FULTZ
Drywall Nailing 7/5/2022 Partial Approval HORACE FULTZ
ELECTRICAL-Final 7/5/2022 Corrections Issued HORACE FULTZ
Final 7/5/2022 Not Ready for Inspection HORACE FULTZ
Green Building Final 7/5/2022 Not Ready for Inspection HORACE FULTZ
Green Building Rough 7/5/2022 Approved HORACE FULTZ
HVAC-Final 7/5/2022 Not Ready for Inspection HORACE FULTZ
PLUMBING-Final 7/5/2022 Not Ready for Inspection HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Not Ready HORACE FULTZ
Service/Power Release 7/5/2022 Not Ready for Inspection HORACE FULTZ
Smoke Detectors 7/5/2022 Approved HORACE FULTZ
Final 8/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 8/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/9/2022 Partial Approval ENRIQUE MIRELES
Drywall Nailing 8/9/2022 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 8/9/2022 Not Ready for Inspection ENRIQUE MIRELES
Final 8/9/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/9/2022 Approved ENRIQUE MIRELES
HVAC-Final 8/9/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 8/9/2022 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 8/9/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/16/2022 Not Ready for Inspection HORACE FULTZ
Drywall Nailing 8/16/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Final 8/16/2022 Not Ready for Inspection HORACE FULTZ
Final 8/16/2022 Not Ready for Inspection HORACE FULTZ
HVAC-Final 8/16/2022 Not Ready for Inspection HORACE FULTZ
PLUMBING-Final 8/16/2022 Not Ready for Inspection HORACE FULTZ
BUILDING-Rough-Frame 8/24/2022 Approved ENRIQUE MIRELES
Drywall Nailing 8/24/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 8/24/2022 Approved ENRIQUE MIRELES
Final 8/24/2022 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 8/24/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 8/24/2022 Approved ENRIQUE MIRELES