801-801 1/2 E MANCHESTER AVE 90001
Certificate Information: 801-801 1/2 E MANCHESTER AVE 90001
- Application / Permit
- 19010-10000-02077
- Plan Check / Job No.
- B19LA10294
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW (2)-STORY DUPLEX W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 12/14/2020
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 5/17/2019 | APPLICANT |
Assigned to Plan Check Engineer | 6/6/2019 | KEVIN MORALES |
Corrections Issued | 6/11/2019 | KEVIN MORALES |
Quality Review Completed | 6/17/2019 | JOSE RODRIGUEZ |
Green Plans Picked Up | 6/17/2019 | APPLICANT |
Plan Check Approved | 8/18/2020 | KEVIN MORALES |
Issued | 12/14/2020 | APPLICANT |
Building Plans Picked Up | 1/20/2021 | APPLICANT |
CofO in Progress | 8/25/2022 | ENRIQUE MIRELES |
Permit Finaled | 10/1/2022 | DEROLD HAUFF |
CofO Issued | 10/1/2022 | DEROLD HAUFF |
Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
Community Plan Implem. Overlay | Cleared | 6/25/2019 | EDUARDO HERMOSO |
Community Plan Implem. Overlay | Cleared | 7/22/2019 | JOHN KIM |
Address approval | Cleared | 10/4/2019 | THOMAS LANG |
Green Code | Cleared | 10/11/2019 | DONALD CRICHLOW |
Community Plan Implem. Overlay | Cleared | 11/3/2019 | RIDWAN HARDY |
Community Plan Implem. Overlay | Cleared | 11/26/2019 | STEVE GARCIA |
ZI | Cleared | 11/26/2019 | STEVE GARCIA |
Community Plan Implem. Overlay | Cleared | 12/6/2019 | THAN WIN |
Eng Process Fee Ord 176,300 | Cleared | 12/6/2019 | THAN WIN |
Low Impact Development | Cleared | 12/6/2019 | RYAN HUDSON |
Sewer availability | Cleared | 12/6/2019 | THAN WIN |
Roof/Waste drainage to street | Cleared | 12/13/2019 | THOMAS LANG |
Hydrant and Access approval | Cleared | 1/9/2020 | GEORGE SUCHAND |
ZI | Cleared | 7/24/2020 | GRACIELA ACOSTA |
Contact Information
Contractor | Owner-Builder | , |
Inspector Information
JOHN QUINTANILLA, (213) 482-0325 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 4/16/2021 | Corrections Issued | EUGENE CASSIDY |
Pre-Inspection | 4/16/2021 | Not Ready for Inspection | EUGENE CASSIDY |
Underground Mechanical | 4/16/2021 | Not Ready for Inspection | EUGENE CASSIDY |
Excavation/Setback/Form/Re-Bar | 4/20/2021 | Approved | EUGENE CASSIDY |
Underground Mechanical | 4/20/2021 | Partial Approval | EUGENE CASSIDY |
PLUMBING-Rough | 6/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
Sewer | 6/14/2021 | Approved | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 8/17/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
BUILDING-Rough-Frame | 8/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
PLUMBING-Rough | 9/9/2021 | Partial Approval | EUGENE CASSIDY |
Interior/Exterior Lathing | 10/12/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
BUILDING-Rough-Frame | 11/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
ELECTRICAL-Rough | 11/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
PLUMBING-Rough | 11/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
Wood Frame | 11/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
ELECTRICAL-Rough | 12/9/2021 | Approved | SABAS ALONSO |
Deputy Wood Construction | 12/10/2021 | Conditional Approval | JOAQUIN GREENOUGH |
PLUMBING-Rough | 12/14/2021 | Conditional Approval | ADAM ESCOTO |
HVAC-Rough | 12/22/2021 | Corrections Issued | ADAM ESCOTO |
PLUMBING-Rough | 12/22/2021 | Approved | ADAM ESCOTO |
BUILDING-Rough-Frame | 12/29/2021 | Partial Approval | HORACE FULTZ |
HVAC-Rough | 12/29/2021 | Approved | HORACE FULTZ |
Insulation | 1/12/2022 | Conditional Approval | FREDDIE RIVERA |
Pre-Inspection | 1/12/2022 | Corrections Issued | FREDDIE RIVERA |
Insulation | 1/28/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
Drywall Nailing | 2/4/2022 | Corrections Issued | LILIANA PORTILLO |
Green Building Rough | 2/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
Insulation | 2/4/2022 | Approved | LILIANA PORTILLO |
Drywall Nailing | 2/10/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
Green Building Rough | 2/10/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
ELECTRICAL-Final | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
HVAC-Final | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
PLUMBING-Final | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
BUILDING-Rough-Frame | 6/3/2022 | Corrections Issued | HORACE FULTZ |
ELECTRICAL-Final | 6/3/2022 | Corrections Issued | HORACE FULTZ |
HVAC-Final | 6/3/2022 | Corrections Issued | HORACE FULTZ |
PLUMBING-Final | 6/3/2022 | Not Ready for Inspection | HORACE FULTZ |
ELECTRICAL-Final | 6/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
HVAC-Final | 6/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
PLUMBING-Final | 6/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
Special/Order Compliance | 6/17/2022 | Partial Inspection | LILIANA PORTILLO |
BUILDING-Rough-Frame | 6/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
Drywall Nailing | 6/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
Final | 6/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
Footing/Foundation/Slab | 6/20/2022 | Approved | SHAVONNE ESPINOZA |
Green Building Final | 6/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
Green Building Rough | 6/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
SGSOV-Seismic Gas S/O Valve | 6/20/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
Service/Power Release | 6/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
Smoke Detectors | 6/20/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
Verify Sprinkler Sign Off | 6/20/2022 | Approved | SHAVONNE ESPINOZA |
BUILDING-Rough-Frame | 7/5/2022 | Corrections Issued | HORACE FULTZ |
Drywall Nailing | 7/5/2022 | Partial Approval | HORACE FULTZ |
ELECTRICAL-Final | 7/5/2022 | Corrections Issued | HORACE FULTZ |
Final | 7/5/2022 | Not Ready for Inspection | HORACE FULTZ |
Green Building Final | 7/5/2022 | Not Ready for Inspection | HORACE FULTZ |
Green Building Rough | 7/5/2022 | Approved | HORACE FULTZ |
HVAC-Final | 7/5/2022 | Not Ready for Inspection | HORACE FULTZ |
PLUMBING-Final | 7/5/2022 | Not Ready for Inspection | HORACE FULTZ |
SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | HORACE FULTZ |
Service/Power Release | 7/5/2022 | Not Ready for Inspection | HORACE FULTZ |
Smoke Detectors | 7/5/2022 | Approved | HORACE FULTZ |
Final | 8/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
Service/Power Release | 8/1/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
BUILDING-Rough-Frame | 8/9/2022 | Partial Approval | ENRIQUE MIRELES |
Drywall Nailing | 8/9/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
ELECTRICAL-Final | 8/9/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
Final | 8/9/2022 | Corrections Issued | ENRIQUE MIRELES |
Green Building Final | 8/9/2022 | Approved | ENRIQUE MIRELES |
HVAC-Final | 8/9/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
PLUMBING-Final | 8/9/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | ENRIQUE MIRELES |
Service/Power Release | 8/9/2022 | Approved | ENRIQUE MIRELES |
BUILDING-Rough-Frame | 8/16/2022 | Not Ready for Inspection | HORACE FULTZ |
Drywall Nailing | 8/16/2022 | Not Ready for Inspection | HORACE FULTZ |
ELECTRICAL-Final | 8/16/2022 | Not Ready for Inspection | HORACE FULTZ |
Final | 8/16/2022 | Not Ready for Inspection | HORACE FULTZ |
HVAC-Final | 8/16/2022 | Not Ready for Inspection | HORACE FULTZ |
PLUMBING-Final | 8/16/2022 | Not Ready for Inspection | HORACE FULTZ |
BUILDING-Rough-Frame | 8/24/2022 | Approved | ENRIQUE MIRELES |
Drywall Nailing | 8/24/2022 | Approved | ENRIQUE MIRELES |
ELECTRICAL-Final | 8/24/2022 | Approved | ENRIQUE MIRELES |
Final | 8/24/2022 | OK to Issue CofO | ENRIQUE MIRELES |
HVAC-Final | 8/24/2022 | Approved | ENRIQUE MIRELES |
PLUMBING-Final | 8/24/2022 | Approved | ENRIQUE MIRELES |