1008-1010 E 49TH PL 90011
Certificate Information: 1008-1010 E 49TH PL 90011
- Application / Permit
- 19010-10000-02067
- Plan Check / Job No.
- B19LA10231
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE. BUILDING SHALL BE EQUIPPED WITH AUTOMATIC FIRESPRINKLER SYSTEM NFPA13-D. COMPLY WITH DEPARTMENT ORDER effective date 01/30/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Current Status
- CofO Issued on 3/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2019 | APPLICANT |
| Green Plans Picked Up | 6/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | JEFFREY MACHADO |
| Corrections Issued | 6/10/2019 | JEFFREY MACHADO |
| Quality Review Completed | 6/14/2019 | ARMEN JIVALAGIAN |
| Plan Check Approved | 8/27/2019 | JEFFREY MACHADO |
| Issued | 10/30/2020 | APPLICANT |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| CofO in Progress | 2/16/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 3/14/2022 | DEROLD HAUFF |
| CofO Issued | 3/14/2022 | DEROLD HAUFF |
| Permit Finaled | 3/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 6/24/2019 | JEREMY CARTER |
| Address approval | Cleared | 6/25/2019 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2019 | ADRIAN SANCHEZ |
| Permit | Cleared | 6/25/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/25/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 7/17/2019 | JEFFREY MACHADO |
| Trees in Parkway | Cleared | 7/17/2019 | STEPHEN DUPREY |
| Community Plan Implem. Overlay | Cleared | 7/19/2019 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 7/30/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/30/2019 | CELINA MORENO |
Contact Information
| Contractor | Moreno Chris; Lic. No.: 973501-B | 1158 W 126TH STREET LOS ANGELES, CA 90044 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2020 | Partial Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 6/16/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/24/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/23/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/23/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/23/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/23/2021 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 8/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 8/23/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/25/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 8/25/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/27/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Insulation | 8/27/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/10/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/10/2021 | Partial Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 9/15/2021 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 2/3/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 2/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 2/3/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 2/3/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 2/3/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 2/3/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 2/3/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 2/7/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Final | 2/16/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| HVAC-Final | 2/16/2022 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 2/16/2022 | Approved | JOAQUIN GREENOUGH |