4867 N WICOPEE AVE 90041

Certificate Information: 4867 N WICOPEE AVE 90041

Application / Permit
19010-10000-02044
Plan Check / Job No.
B19LA10174
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 76'5" X 40'1-1/2" SINGLE FAMILY DWELLING WITH 34'1" X 10' TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/17/2020
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 RARES BODEA
Corrections Issued 6/8/2019 RARES BODEA
Quality Review Completed 6/12/2019 OMID HEDAYAT
Building Plans Picked Up 6/17/2019 APPLICANT
Green Plans Picked Up 7/1/2019 APPLICANT
Plan Check Approved 1/23/2020 RARES BODEA
Issued 6/17/2020 APPLICANT
CofO in Progress 9/24/2022 CRAIG VAUGHAN
CofO in Progress 9/24/2022 CRAIG VAUGHAN
Permit Finaled 10/22/2022 DEROLD HAUFF
CofO Issued 10/22/2022 DEROLD HAUFF
Permit Finaled 10/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/1/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 7/1/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 7/1/2019 ERIK BEASLEY
Miscellaneous Cleared 7/1/2019 ERIK BEASLEY
Permit Cleared 7/1/2019 CELINA MORENO
BHO/Hillside ordinance Cleared 7/19/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/19/2019 ELENA LOPEZ
Sewer availability Cleared 7/19/2019 ELENA LOPEZ
Trees in Parkway Cleared 9/10/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 9/18/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 9/18/2019 THOMAS LANG
Distance to fire station Cleared 9/26/2019 JOHN CONNEALLY
Hydrant and Access approval Cleared 9/26/2019 JOHN CONNEALLY
Green Code Cleared 9/30/2019 KHEDER ALRAZAA
GPI Written Notices Cleared 1/23/2020 RARES BODEA
Grading Pre-Inspection Cleared 1/23/2020 RARES BODEA

Contact Information

Contractor Barron Marco Engineer Contractor Inc; Lic. No.: 834558-B 10172 TUJUNGA CANYON BLVD      TUJUNGA, CA 91042
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732
Engineer Stumpf,, Patricio L; Lic. No.: L5515 10527 SAN VINCENTE AVE      SOUTH GATE, CA 90280

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/11/2020 Partial Approval CRAIG VAUGHAN
Underground Mechanical 8/11/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/14/2020 Approved CRAIG VAUGHAN
Grading Pre-Inspection 8/14/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 8/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/20/2020 Approved CRAIG VAUGHAN
Wood Frame 9/15/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 9/22/2020 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 9/22/2020 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 10/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 10/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 10/8/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/8/2020 Partial Approval CRAIG VAUGHAN
Shower Pan 10/8/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 10/9/2020 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 10/20/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 10/28/2020 No Access for Inspection CRAIG VAUGHAN
HVAC-Rough 10/28/2020 No Access for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 10/28/2020 No Access for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/28/2020 No Access for Inspection CRAIG VAUGHAN
Wood Frame 10/28/2020 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 11/6/2020 Approved CRAIG VAUGHAN
HVAC-Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 11/6/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/6/2020 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/6/2020 Approved CRAIG VAUGHAN
Wood Frame 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/23/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 11/23/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 11/23/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/23/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 11/30/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 11/30/2020 Approved CRAIG VAUGHAN
HVAC-Rough 11/30/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/30/2020 Approved CRAIG VAUGHAN
Insulation 12/3/2020 Approved CRAIG VAUGHAN
Pre-Inspection 12/3/2020 Approved CRAIG VAUGHAN
Drywall Nailing 12/9/2020 Approved HAMIK HARTOUNIAN
Service/Power Release 3/1/2021 Not Ready for Inspection CRAIG VAUGHAN
Sewer 3/10/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/24/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 6/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 6/2/2021 Corrections Issued KATHRYN BUTTERWORTH
Final 6/22/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 6/22/2021 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 6/22/2021 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 6/22/2021 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 6/24/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 7/2/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Final 7/2/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/2/2021 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 7/2/2021 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 7/2/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 7/16/2021 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 7/16/2021 Approved CRAIG VAUGHAN
Service/Power Release 7/20/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Not Ready BRIAN SULLIVAN
Final 11/1/2021 Corrections Issued CRAIG DAVIS
Green Building Final 11/1/2021 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 11/1/2021 Approved CRAIG DAVIS
ELECTRICAL-Final 11/4/2021 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 11/4/2021 Approved CRAIG VAUGHAN
HVAC-Final 11/4/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 11/4/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 11/8/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 11/8/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/15/2021 Approved CRAIG VAUGHAN
Final 11/15/2021 Conditional Approval CRAIG VAUGHAN
HVAC-Final 11/15/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 11/15/2021 Approved CRAIG VAUGHAN
Final 11/19/2021 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 11/24/2021 Approved CRAIG VAUGHAN
Final 11/24/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 11/24/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 11/24/2021 Approved CRAIG VAUGHAN