2631 N ROUND DR 90032
Certificate Information: 2631 N ROUND DR 90032
- Application / Permit
- 19010-10000-02021
- Plan Check / Job No.
- B19LA10010
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FOR NEW 2-STORY SFD W/ATTACHED GARAGE.
- Permit Issued
- Issued on 5/14/2020
- Issuing Office
- Current Status
- CofO Issued on 9/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | RAHEL BEYENE |
| Green Plans Picked Up | 6/6/2019 | APPLICANT |
| Corrections Issued | 6/7/2019 | RAHEL BEYENE |
| Quality Review Completed | 6/14/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 6/20/2019 | APPLICANT |
| Applicant returned to address corrections | 8/27/2019 | RAHEL BEYENE |
| Plan Check Approved | 4/29/2020 | JOHNNY WU |
| Plan Check Approved | 4/29/2020 | JOHNNY WU |
| Issued | 5/14/2020 | APPLICANT |
| CofO in Progress | 9/12/2022 | AMY COLIN |
| Permit Finaled | 9/27/2022 | DEROLD HAUFF |
| CofO Issued | 9/27/2022 | DEROLD HAUFF |
| Permit Finaled | 9/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/26/2019 | ROBERT DUFF |
| Green Code | Cleared | 9/3/2019 | KHEDER ALRAZAA |
| Disturb/Remove Protected Trees | Cleared | 9/11/2019 | ADRIAN SANCHEZ |
| "D" conditions | Cleared | 10/7/2019 | NICOLE SANCHEZ |
| "Q" conditions | Cleared | 10/7/2019 | NICOLE SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 10/16/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/16/2019 | JEANIE LAM |
| Sewer availability | Cleared | 10/16/2019 | JEANIE LAM |
| GPI Written Notices | Cleared | 4/17/2020 | RAHEL BEYENE |
| Grading Pre-Inspection | Cleared | 4/17/2020 | RAHEL BEYENE |
| Excavation more than 5-ft deep | Cleared | 4/22/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | Junior Custom Construction; Lic. No.: 1050935-B | 137 W ASH AVE SHAFTER, CA 93263 |
| Engineer | Adamson,, Edward H; Lic. No.: S5223 | 306 DONAHUE ST SAUSALITO, CA 94965 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1243 21ST AVE NE APT B HICKORY, NC 28601 |
| Engineer | Sanchez,, Pablo Beltran; Lic. No.: C86223 | 1840 S GAFFEY ST 382 SAN PEDRO, CA 90731 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 1423 S BEVERLY GLEN BLVD APT B LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/4/2020 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/9/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 12/18/2020 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/23/2020 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 1/4/2021 | Partial Approval | OSVALDO PARAMO |
| Special/Order Compliance | 1/28/2021 | Partial Inspection | COREY HUPP |
| Footing/Foundation/Slab | 2/24/2021 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 3/8/2021 | Approved | OSVALDO PARAMO |
| Masonry Wall/Backfill | 3/17/2021 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Partial Approval | CRAIG VAUGHAN |
| Reinforced Concrete Frame | 4/19/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 5/5/2021 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/11/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 8/17/2021 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 8/27/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/31/2021 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 8/31/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 8/31/2021 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 8/31/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/7/2021 | Approved | RUBEN SALAS |
| Green Building Rough | 9/7/2021 | Approved | RUBEN SALAS |
| Insulation | 9/24/2021 | Approved | RUBEN SALAS |
| Drywall Nailing | 9/30/2021 | Approved | ROBERT VORHIS |
| Special/Order Compliance | 2/8/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/25/2022 | Approved | AMY COLIN |
| Final | 4/25/2022 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 4/25/2022 | Approved | AMY COLIN |
| Gas Test | 4/25/2022 | Approved | AMY COLIN |
| Green Building Final | 4/25/2022 | Corrections Issued | AMY COLIN |
| HVAC-Final | 4/25/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 4/25/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 4/25/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 4/25/2022 | Approved | AMY COLIN |
| Final | 9/12/2022 | OK to Issue CofO | AMY COLIN |
| Green Building Final | 9/12/2022 | Approved | AMY COLIN |
| Service/Power Release | 9/12/2022 | Approved | AMY COLIN |