15094 W NURMI ST 91342
Certificate Information: 15094 W NURMI ST 91342
- Application / Permit
- 19010-10000-01961
- Plan Check / Job No.
- B19LA09568
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- PROPOSED NEW 2-CAR GARAGE 21'X25' ALL CONSTRUCTION PER WFPP
- Permit Issued
- Issued on 7/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2019 | SINA KHOSRAVI |
| Corrections Issued | 5/10/2019 | SINA KHOSRAVI |
| Plan Check Approved | 7/25/2019 | GEORGE ALVAREZ |
| Issued | 7/26/2019 | LADBS |
| CofO in Progress | 1/24/2023 | ARAM AVEDISIAN |
| Permit Finaled | 1/25/2023 | MICHAEL SMITH |
| CofO Issued | 1/25/2023 | MICHAEL SMITH |
| Permit Finaled | 1/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2019 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 7/18/2019 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 7/25/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/25/2019 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2020 | Partial Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/13/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | CALEB MEISTER |
| Wood Frame | 10/4/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 10/21/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/24/2023 | Approved | ARAM AVEDISIAN |
| Final | 1/24/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 1/24/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/24/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 1/24/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 1/24/2023 | Approved | ARAM AVEDISIAN |