1073 W EXPOSITION BLVD 90007
Certificate Information: 1073 W EXPOSITION BLVD 90007
- Application / Permit
- 19010-10000-01944
- Plan Check / Job No.
- B19LA09490
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 4 STORY 15 UNIT APARTMEN WITH 250SQFT OF COMMERCIAL SPACE. TOC TIER 4 AFFORDABLE HOUSING INCENTIVES
- Permit Issued
- Issued on 7/8/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | HERNAN ARREOLA |
| Corrections Issued | 6/10/2019 | HERNAN ARREOLA |
| Quality Review Completed | 6/17/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 6/18/2019 | APPLICANT |
| Applicant returned to address corrections | 8/1/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/15/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/13/2020 | HERNAN ARREOLA |
| Plan Check Approved | 7/1/2020 | HERNAN ARREOLA |
| Issued | 7/8/2020 | APPLICANT |
| CofO in Progress | 7/30/2021 | JAMES POWERS |
| CofO Issued | 7/30/2021 | ERNESTO CORRAL |
| Permit Finaled | 7/30/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 11/21/2019 | HERNAN ARREOLA |
| Construction near power lines | Cleared | 12/6/2019 | RIDWAN HARDY |
| Address approval | Cleared | 12/11/2019 | THOMAS LANG |
| Community Plan Implem. Overlay | Cleared | 12/11/2019 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/11/2019 | THOMAS LANG |
| Trees in Parkway | Cleared | 12/11/2019 | JOHN KIM |
| Low Impact Development | Cleared | 1/8/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/8/2020 | ELENA LOPEZ |
| Hydrant and Access approval | Cleared | 1/15/2020 | JEREMY CARTER |
| Building over 3-story or 36-ft | Cleared | 2/13/2020 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 2/13/2020 | CALOSHA APPROVED |
| Metro Rail approval | Cleared | 2/13/2020 | SHINE LING |
| Community Plan Implem. Overlay | Cleared | 4/1/2020 | MOHAMMAD HASAN |
| DAS Clearance | Cleared | 4/8/2020 | HERNAN ARREOLA |
| Community Plan Implem. Overlay | Cleared | 4/9/2020 | CELINA MORENO |
| Fire Marshall Fire Life Safety | Cleared | 4/9/2020 | WILLIAM JOHNS |
| Highway dedication | Cleared | 4/16/2020 | CELINA MORENO |
| Density Bonus 12.22.A.31 | Cleared | 5/26/2020 | JACOB COMER |
| "D" conditions | Cleared | 6/11/2020 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 6/11/2020 | HELEN JADALI |
| Frnt yard landscape/Water mgmt | Cleared | 6/11/2020 | ANACANY HURTADO |
| Opn space landscape/Water mgmt | Cleared | 6/11/2020 | ANACANY HURTADO |
| ZI | Cleared | 6/11/2020 | HELEN JADALI |
| Miscellaneous | Cleared | 6/12/2020 | ANACANY HURTADO |
Contact Information
| Architect | Chang,, Winston L; Lic. No.: C25009 | 1476 VIA CORONEL PALOS VERDES ESTATES, CA 90274 |
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/20/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 8/20/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 8/21/2020 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 9/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/8/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 9/11/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 10/16/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 11/5/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Partial Approval | NICK DANERI |
| Deputy Wood Construction | 11/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Green Building Rough | 12/7/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/7/2020 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 12/7/2020 | Partial Approval | JAMES POWERS |
| Insulation | 12/18/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/29/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 12/31/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/31/2020 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 12/31/2020 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 1/20/2021 | Partial Approval | JAMES POWERS |
| Insulation | 1/26/2021 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 1/26/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 1/27/2021 | Not Ready for Inspection | JAMES POWERS |
| Light Gage Steel Frame | 1/27/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 2/2/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 2/10/2021 | Partial Approval | JAMES POWERS |
| Insulation | 2/10/2021 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 2/19/2021 | Approved | JAMES POWERS |
| Drywall Nailing | 3/3/2021 | Partial Approval | JAMES POWERS |
| Special/Order Compliance | 4/26/2021 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Special/Order Compliance | 4/27/2021 | Approved | RAFAEL ESPINOZA |
| Final | 7/23/2021 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 7/23/2021 | Approved | JAMES POWERS |
| Green Building Final | 7/23/2021 | Approved | JAMES POWERS |
| Green Building Rough | 7/23/2021 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 7/23/2021 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/23/2021 | Approved | JAMES POWERS |
| Wood Frame | 7/23/2021 | Approved | JAMES POWERS |
| Final | 7/29/2021 | OK to Issue CofO | JAMES POWERS |