8317 N ETIWANDA AVE 91325

Certificate Information: 8317 N ETIWANDA AVE 91325

Application / Permit
19010-10000-01906
Plan Check / Job No.
B19LA09205
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
CONSTRUCT NEW CORE AND SHELL CONSTRUCTION OF A 9121SQ FT MEDICAL OFFICE BUILDING. 1 OF 3
Permit Issued
Issued on 1/28/2020
Issuing Office
Valley
Current Status
CofO Corrected on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2019 APPLICANT
Assigned to Plan Check Engineer 6/13/2019 CHON CHIO KUO
Corrections Issued 6/17/2019 CHON CHIO KUO
Quality Review Completed 6/20/2019 STEVEN KIM
Building Plans Picked Up 6/21/2019 APPLICANT
Disabled Access Plans Picked Up 6/21/2019 APPLICANT
Green Plans Picked Up 6/21/2019 APPLICANT
Applicant returned to address corrections 7/11/2019 CHON CHIO KUO
Applicant returned to address corrections 7/18/2019 CHON CHIO KUO
Applicant returned to address corrections 8/1/2019 CHON CHIO KUO
Applicant returned to address corrections 8/29/2019 CHON CHIO KUO
Applicant returned to address corrections 12/20/2019 CHON CHIO KUO
Plan Check Approved 12/20/2019 CHON CHIO KUO
Issued 1/28/2020 LADBS
CofO in Progress 6/7/2022 CAMERON CHABAN
CofO Issued-Status Void 8/1/2022 JEFFREY DURAN
Permit Finaled-Status Void 8/1/2022 JEFFREY DURAN
Re-Activate Permit 8/3/2022 JEFFREY DURAN
CofO Corrected 8/3/2022 JEFFREY DURAN
Permit Finaled 8/3/2022 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/19/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 7/10/2019 GEORGE SUCHAND
DAS Clearance Cleared 7/11/2019 CHON CHIO KUO
Work Adjacent to Public Way Cleared 7/11/2019 MARKOS PEREZ-BRAN
Address approval Cleared 7/18/2019 GUILLERMO PETRA
Sewer availability Cleared 7/18/2019 GUILLERMO PETRA
Green Code Cleared 8/1/2019 CHON CHIO KUO
Highway dedication Cleared 8/1/2019 MARKOS PEREZ-BRAN
Internal circulation Cleared 8/1/2019 SHIRLEY ZAMORA
Construction near power lines Cleared 8/29/2019 RIDWAN HARDY
Trees in Parkway Cleared 9/19/2019 JOHN KIM
Low Impact Development Cleared 9/26/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/26/2019 GUILLERMO PETRA
Permit Cleared 11/26/2019 APEKSHYA BAJRACHARYA
"Q" conditions Cleared 12/5/2019 SARAHI ORTEGA
APC Cleared 12/5/2019 SARAHI ORTEGA
Comm Cor/Mini-Mall Cleared 12/5/2019 SARAHI ORTEGA
Comm Cor/Mini-Mall Cleared 12/5/2019 SARAHI ORTEGA
Comm Cor/Mini-Mall Cleared 12/5/2019 SARAHI ORTEGA
Miscellaneous Cleared 12/5/2019 SARAHI ORTEGA
Prkng lot landscape/Water mgmt Cleared 12/5/2019 SARAHI ORTEGA
"T" removal Cleared 12/6/2019 SARAHI ORTEGA

Contact Information

Architect Osuch,, Edward M; Lic. No.: C32544 6191 ST ALBANS STREET # A      LOS ANGELES, CA 90042
Contractor Vantage Development & Construction Corporation; Lic. No.: 955969-B 18653 VENTURA BLVD #333      TARZANA, CA 91356
Engineer Hoshi,, Hiroshi; Lic. No.: S4996 5607 MULBERRY RIDGE DR      CAMARILLO, CA 93012

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/10/2020 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 2/10/2020 Partial Inspection ROBERT COLE
Pre-Inspection 2/10/2020 Partial Inspection ROBERT COLE
Deputy Reinf. Concrete 2/12/2020 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 2/12/2020 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 2/13/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/18/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/19/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/20/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/21/2020 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 2/24/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/25/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 2/25/2020 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 2/26/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/27/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 2/28/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/3/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/4/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 3/4/2020 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 3/5/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/6/2020 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 3/9/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/10/2020 No Access for Inspection ROBERT COLE
Masonry Wall/Backfill 3/10/2020 No Access for Inspection ROBERT COLE
Deputy Reinf. Masonry 3/11/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/12/2020 Conditional Approval ROBERT COLE
Green Building Rough 3/12/2020 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 3/12/2020 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/12/2020 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 3/13/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/17/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/18/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/19/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/20/2020 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 3/23/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/24/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/25/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/26/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/27/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/1/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/3/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/6/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/7/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/8/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/8/2020 Conditional Approval ROBERT COLE
Masonry Wall/Backfill 4/8/2020 Partial Approval ROBERT COLE
Deputy Reinf. Masonry 4/9/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/10/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/13/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/14/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/15/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 4/16/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/17/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/21/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/27/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/29/2020 Conditional Approval ROBERT COLE
Deputy Steel/Welding 4/30/2020 No Access for Inspection JOE VELASQUEZ
Masonry Wall/Backfill 4/30/2020 Approved JOE VELASQUEZ
Deputy Reinf. Masonry 5/1/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/4/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/5/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/6/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/7/2020 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 5/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 5/7/2020 No Access for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 5/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 5/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/7/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/8/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 5/11/2020 Conditional Approval ROBERT COLE
Reinforced Masonry Frame 5/11/2020 Partial Approval ROBERT COLE
Deputy Steel/Welding 5/27/2020 Conditional Approval ROBERT COLE
Green Building Rough 6/4/2020 Not Ready for Inspection ROBERT COLE
Structural Steel Frame 6/4/2020 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 6/4/2020 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 6/10/2020 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Partial Approval RONALD PACHECO
Special/Order Compliance 9/1/2020 Partial Approval HAMID PISHEHVAR
Interior/Exterior Lathing 11/4/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/11/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 3/11/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 3/11/2022 Not Ready for Inspection DANIEL VARNUM
Structural Steel Frame 3/11/2022 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 3/11/2022 Not Ready for Inspection DANIEL VARNUM
Final 3/14/2022 Not Ready for Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/14/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 3/14/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/14/2022 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 5/27/2022 Approved CAMERON CHABAN
Final 5/27/2022 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/27/2022 Conditional Approval CAMERON CHABAN
Green Building Final 5/27/2022 Partial Inspection CAMERON CHABAN
Green Building Rough 5/27/2022 Approved CAMERON CHABAN
Reinforced Masonry Frame 5/27/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 5/27/2022 Approved CAMERON CHABAN
Structural Steel Frame 5/27/2022 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 5/27/2022 Approved CAMERON CHABAN
Drywall Nailing 5/28/2022 Approved CAMERON CHABAN
Final 5/28/2022 OK to Issue CofO CAMERON CHABAN
Final 5/28/2022 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/28/2022 Approved CAMERON CHABAN
Green Building Final 5/28/2022 Approved CAMERON CHABAN
Green Building Rough 5/28/2022 Approved CAMERON CHABAN
Reinforced Masonry Frame 5/28/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/28/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 5/28/2022 Approved CAMERON CHABAN
Structural Steel Frame 5/28/2022 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 5/28/2022 Approved CAMERON CHABAN
Footing/Foundation/Slab 6/28/2022 Approved CAMERON CHABAN
Green Building Final 6/28/2022 Approved CAMERON CHABAN