1339 N TAMARIND AVE 90028

Certificate Information: 1339 N TAMARIND AVE 90028

Application / Permit
19010-10000-01905
Plan Check / Job No.
B19LA09169
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 5-story with a roof deck, Type IIIA, 44-unit apartment building over two levels, Type IA, basement parking garages. Density bonus project. restricting 4 units for VLI households. Two in menu incentives to increase the building height from 45' to 56' & FAR, 3:1 to 3.95: 1.
Permit Issued
Issued on 2/27/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2019 APPLICANT
Assigned to Plan Check Engineer 6/13/2019 KESETE HAREGOT
Disabled Access Plans Picked Up 7/16/2019 APPLICANT
Corrections Issued 7/18/2019 KESETE HAREGOT
Quality Review Completed 7/25/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 7/31/2019 APPLICANT
Applicant returned to address corrections 10/4/2019 KESETE HAREGOT
Green Plans Picked Up 4/6/2021 APPLICANT
Applicant returned to address corrections 12/1/2021 KESETE HAREGOT
Applicant returned to address corrections 5/11/2022 KESETE HAREGOT
Applicant returned to address corrections 8/19/2022 KESETE HAREGOT
Applicant returned to address corrections 9/26/2022 KESETE HAREGOT
Plan Check Approved 2/23/2023 KESETE HAREGOT
Issued 2/27/2023 APPLICANT
TCO Issued (Expire Date: 10-24-2026) 4/27/2026 ERNESTO CORRAL
CofO in Progress 5/4/2026 DAVID BURKHEAD
Permit Finaled 5/4/2026 ADAM BURGESS
CofO Issued 5/4/2026 ADAM BURGESS
Permit Finaled 5/4/2026 ADAM BURGESS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/6/2019 JEANIE LAM
Address approval Cleared 8/8/2019 ELAINE LEI
Highway dedication Cleared 8/8/2019 ELAINE LEI
Hydrant and Access approval Cleared 8/23/2019 JOHN CONNEALLY
Disturb/Remove Protected Trees Cleared 9/13/2019 ADRIAN SANCHEZ
Project located in CRA area Cleared 10/22/2019 JIM URQUHART
Project located in CRA area Cleared 10/22/2019 JIM URQUHART
Permit Cleared 10/29/2019 ERIK BEASLEY
Trees in Parkway Cleared 5/11/2021 JOHN KIM
Green Code Cleared 5/16/2022 AARON COSTA
DAS Clearance Cleared 6/9/2022 EDDIE GARIN
Historic Resource Verification Cleared 8/16/2022 MAX LODER
DCP conditions approval Cleared 8/18/2022 KENNETH LE
Density Bonus 12.22.A.25 Cleared 8/18/2022 KENNETH LE
"Q" conditions Cleared 8/31/2022 KENTON TRINH
Frnt yard landscape/Water mgmt Cleared 8/31/2022 KENTON TRINH
Miscellaneous Cleared 8/31/2022 KENTON TRINH
Opn space landscape/Water mgmt Cleared 8/31/2022 KENTON TRINH
ZI Cleared 8/31/2022 KENTON TRINH
Sewer availability Cleared 9/7/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 9/21/2022 MARTIN FRAGOSO
Building over 3-story or 36-ft Cleared 9/26/2022 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 9/26/2022 CHRISTOPHER ROCHA
Work Adjacent to Public Way Cleared 10/18/2022 KHOUNG LE
Fire Marshall Fire Life Safety Cleared 1/12/2023 DOMINIQUE MEDINA

Contact Information

Architect Uriu,, Giovanni; Lic. No.: C7487 830 SO GLENDALE AVENUE      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316
Engineer Downey,, Henry Ross; Lic. No.: C30372 7463 VARNA AVE      NORTH HOLLYWOOD, CA 916054011
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 120 W WILSON AVE 1550      GLENDALE, CA 91203

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2023 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 4/28/2023 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 5/5/2023 Partial Approval GREGORY POMISH
Green Building Rough 5/5/2023 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/15/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 6/2/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 6/2/2023 Partial Inspection GREGORY POMISH
Masonry Wall/Backfill 6/5/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/20/2023 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 6/30/2023 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 7/11/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/26/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/2/2023 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/3/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/4/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 10/4/2023 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/13/2023 Partial Approval GREGORY POMISH
Deputy Shotcrete 10/16/2023 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 10/17/2023 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 10/19/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 10/31/2023 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 11/14/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 12/8/2023 Partial Approval LARRY ARNICK
Green Building Rough 1/25/2024 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 1/25/2024 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 1/25/2024 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 1/26/2024 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 2/8/2024 Partial Approval DAVID BURKHEAD
Deputy Steel/Welding 2/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 2/21/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 2/22/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/22/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/22/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 2/26/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/26/2024 Not Ready for Inspection DAVID BURKHEAD
Wall Anchors 2/26/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/26/2024 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 2/29/2024 Conditional Approval DAVID BURKHEAD
Green Building Rough 2/29/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/29/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/29/2024 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/1/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 3/5/2024 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 3/5/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 3/5/2024 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 3/15/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 3/20/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/20/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/20/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 4/11/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 4/29/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval DAVID BURKHEAD
Special/Order Compliance 5/22/2024 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 5/24/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/24/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/24/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Partial Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 6/3/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 6/3/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/11/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 6/11/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval TIMOTHY POWELL
Drywall Nailing 6/14/2024 Partial Approval TIMOTHY POWELL
Green Building Rough 6/14/2024 Not Ready for Inspection TIMOTHY POWELL
Verify Sprinkler Sign Off 6/17/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 6/17/2024 Partial Approval DAVID BURKHEAD
Insulation 6/18/2024 Partial Approval LARRY ARNICK
Deputy Wood Construction 6/21/2024 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 6/21/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 6/21/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/21/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 6/26/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 7/2/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval EDWIN GREGORYONA
Insulation 7/9/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 7/11/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/15/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 7/15/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 7/16/2024 Partial Inspection TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Partial Approval DAVID BURKHEAD
Insulation 7/23/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 7/24/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/24/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 7/24/2024 Partial Approval DAVID BURKHEAD
Insulation 7/25/2024 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 7/25/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 7/30/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 7/30/2024 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 8/1/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 8/1/2024 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 8/2/2024 Partial Approval DAVID BURKHEAD
Wood Frame 8/2/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/6/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/7/2024 Partial Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/8/2024 Partial Inspection DAVID BURKHEAD
Wood Frame 8/8/2024 Partial Approval DAVID BURKHEAD
Insulation 8/9/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 8/12/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 8/12/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/13/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 8/14/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/15/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 8/15/2024 Partial Approval DAVID BURKHEAD
Insulation 8/21/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/21/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/21/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 8/28/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/3/2024 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/9/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 9/9/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/10/2024 Partial Approval EDWIN GREGORYONA
Insulation 9/13/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 9/13/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/17/2024 Partial Inspection JEFFREY FULTON
Wood Frame 9/17/2024 Partial Inspection JEFFREY FULTON
Insulation 9/19/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/20/2024 Partial Inspection JEFFREY FULTON
Wood Frame 9/20/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/24/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 9/24/2024 Partial Inspection JEFFREY FULTON
Wood Frame 9/24/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/26/2024 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 10/2/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/10/2024 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 10/10/2024 Partial Approval TIMOTHY POWELL
Insulation 10/16/2024 Partial Inspection JEFFREY FULTON
Insulation 10/21/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/21/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 10/21/2024 Partial Inspection JEFFREY FULTON
Insulation 10/24/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/29/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 11/7/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/12/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/20/2025 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 3/24/2025 Approved DAVID BURKHEAD
Pre-Inspection 2/17/2026 Approved DAVID BURKHEAD
Drywall Nailing 3/20/2026 Approved DAVID BURKHEAD
Final 3/20/2026 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 3/20/2026 Approved DAVID BURKHEAD
Green Building Final 3/20/2026 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/20/2026 Partial Inspection DAVID BURKHEAD
Reinforced Masonry Frame 3/20/2026 Partial Approval DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 3/20/2026 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 3/20/2026 Approved DAVID BURKHEAD
Structural Steel Frame 3/20/2026 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 3/20/2026 Approved DAVID BURKHEAD
Wood Frame 3/20/2026 Partial Inspection DAVID BURKHEAD
Pre-Inspection 3/24/2026 Approved DAVID BURKHEAD
Pre-Inspection 3/26/2026 Corrections Issued DAVID BURKHEAD
Pre-Inspection 3/31/2026 Corrections Issued DAVID BURKHEAD
Pre-Inspection 4/3/2026 Approved DAVID BURKHEAD
Final 4/6/2026 Partial Inspection DAVID BURKHEAD
Green Building Final 4/6/2026 Approved DAVID BURKHEAD
Reinforced Concrete Frame 4/6/2026 Approved DAVID BURKHEAD
Reinforced Masonry Frame 4/6/2026 Approved DAVID BURKHEAD
Wood Frame 4/6/2026 Approved DAVID BURKHEAD
Pre-Inspection 4/8/2026 Approved DAVID BURKHEAD
Pre-Inspection 4/24/2026 Partial Inspection DAVID BURKHEAD
Final 5/4/2026 OK to Issue CofO DAVID BURKHEAD