Excavation/Setback/Form/Re-Bar
|
4/28/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/28/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
5/5/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
5/5/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
5/12/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
5/15/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/19/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
6/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
6/2/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
6/5/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/20/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
6/30/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
7/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
7/26/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/2/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
10/3/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
10/4/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
10/4/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/13/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
10/16/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
10/17/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
10/19/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
10/31/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
11/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
12/8/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
1/25/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
1/25/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
1/25/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
1/26/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Masonry Wall/Backfill
|
2/8/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
2/13/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
2/16/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Masonry Wall/Backfill
|
2/21/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
2/22/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
2/22/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
2/22/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Green Building Rough
|
2/26/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
2/26/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wall Anchors
|
2/26/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
2/26/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
2/29/2024
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
2/29/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
2/29/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
2/29/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
3/1/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
3/5/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
3/5/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
3/5/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
3/15/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
3/20/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
3/20/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
3/20/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/3/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
4/11/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/22/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/25/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
4/29/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/16/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
5/22/2024
|
Approved
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/23/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
5/24/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
5/24/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
5/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2024
|
Partial Inspection
|
TIMOTHY POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/31/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
6/3/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
6/3/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/4/2024
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
6/11/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
6/11/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/13/2024
|
Partial Approval
|
TIMOTHY POWELL
|
|
Drywall Nailing
|
6/14/2024
|
Partial Approval
|
TIMOTHY POWELL
|
|
Green Building Rough
|
6/14/2024
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
|
Verify Sprinkler Sign Off
|
6/17/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
6/17/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
6/18/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
6/21/2024
|
Conditional Approval
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
6/21/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
6/21/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
6/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
6/26/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
7/2/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
7/9/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
7/11/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
7/15/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
7/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
7/16/2024
|
Partial Inspection
|
TIMOTHY POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/18/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
7/23/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
7/24/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Green Building Rough
|
7/24/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
7/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
7/25/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
7/25/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
7/30/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
7/30/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
8/1/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
8/1/2024
|
Approved
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
8/2/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Wood Frame
|
8/2/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
8/6/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
8/7/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
8/8/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
8/8/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
8/9/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
8/12/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
8/12/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
8/13/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
8/14/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
8/15/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
8/15/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
8/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
8/21/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
8/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/22/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/28/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
9/3/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/3/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
9/9/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
9/9/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
9/10/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
9/13/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
9/13/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
9/17/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/17/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
9/19/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/20/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/20/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/24/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
9/24/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/24/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/26/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Interior/Exterior Lathing
|
10/2/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
10/10/2024
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
|
Wood Frame
|
10/10/2024
|
Partial Approval
|
TIMOTHY POWELL
|
|
Insulation
|
10/16/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
10/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
10/21/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
10/21/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
10/24/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/29/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
11/7/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Excavation/Setback/Form/Re-Bar
|
12/12/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
2/20/2025
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
|
Special/Order Compliance
|
3/24/2025
|
Approved
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
2/17/2026
|
Approved
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
3/20/2026
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
3/20/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
3/20/2026
|
Approved
|
DAVID BURKHEAD
|
|
Green Building Final
|
3/20/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
3/20/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Reinforced Masonry Frame
|
3/20/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
SGSOV-Seismic Gas S/O Valve
|
3/20/2026
|
SGSOV Approved
|
DAVID BURKHEAD
|
|
Smoke Detectors
|
3/20/2026
|
Approved
|
DAVID BURKHEAD
|
|
Structural Steel Frame
|
3/20/2026
|
Approved
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
3/20/2026
|
Approved
|
DAVID BURKHEAD
|
|
Wood Frame
|
3/20/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
3/24/2026
|
Approved
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
3/26/2026
|
Corrections Issued
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
3/31/2026
|
Corrections Issued
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
4/3/2026
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
4/6/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Green Building Final
|
4/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
4/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Reinforced Masonry Frame
|
4/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Wood Frame
|
4/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
4/8/2026
|
Approved
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
4/24/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Final
|
5/4/2026
|
OK to Issue CofO
|
DAVID BURKHEAD
|