1503 W 207TH ST #5 90501

Certificate Information: 1503 W 207TH ST #5 90501

Application / Permit
19010-10000-01872
Plan Check / Job No.
B19LA08960
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Small lot subdivision pursuant to Tentative Tract Map No VTT-82057-SL .A Certificate of Occupancy (temporary or final) shall not be issued until after the final map has been recorded. Lot 5 of 9. NFPA-13D Sprinkler system required.
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 1/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 ZAW HAN
Corrections Issued 5/28/2019 ZAW HAN
Quality Review Completed 6/4/2019 BILL STUTSMAN
Green Plans Picked Up 6/7/2019 APPLICANT
Building Plans Picked Up 6/10/2019 APPLICANT
Applicant returned to address corrections 6/9/2020 ZAW HAN
Applicant returned to address corrections 6/10/2020 ZAW HAN
Applicant returned to address corrections 6/22/2020 ZAW HAN
Applicant returned to address corrections 6/26/2020 ZAW HAN
Applicant returned to address corrections 7/9/2020 ZAW HAN
Applicant returned to address corrections 9/23/2020 ZAW HAN
Plan Check Approved 9/29/2020 ZAW HAN
Issued 2/9/2021 APPLICANT
CofO in Progress 1/16/2024 EUGENE CASSIDY
Permit Finaled 1/16/2024 ANSON MAGLASANG
CofO Issued 1/16/2024 ANSON MAGLASANG
Permit Finaled 1/16/2024 ANSON MAGLASANG

Permit Application Clearance Information

Trees in Parkway Cleared 11/20/2019 ADRIAN SANCHEZ
Address approval Cleared 11/22/2019 PHILLIP WILSON
Disturb/Remove Protected Trees Cleared 11/22/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 11/22/2019 PHILLIP WILSON
Highway dedication Cleared 11/22/2019 PHILLIP WILSON
Permit Cleared 11/22/2019 PHILLIP WILSON
Roof/Waste drainage to street Cleared 11/22/2019 PHILLIP WILSON
Green Code Cleared 3/17/2020 COLIN LOREDO
Low Impact Development Cleared 5/20/2020 ORVAL HERNANDEZ-MARCI
Frnt yard landscape/Water mgmt Cleared 5/27/2020 JOE LUCKEY
Miscellaneous Cleared 5/27/2020 JOE LUCKEY
Miscellaneous Cleared 5/27/2020 JOE LUCKEY
Hydrant and Access approval Cleared 9/22/2020 KURT CORRAL
Building over 3-story or 36-ft Cleared 9/29/2020 CALOSHA APPROVED

Contact Information

Architect Schneider,, Matthew P; Lic. No.: C31660 2110 ARTESIA BLVD STE B430      REDONDO BEACH, CA 90278
Contractor Golden State Builder Inc; Lic. No.: 986172-B 18554 VINE STREET      ORANGE, CA 92869

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/2/2021 Partial Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 6/14/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 8/6/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 12/30/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 4/4/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 4/4/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 4/4/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/8/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 4/8/2022 No Access for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 4/8/2022 No Access for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/15/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 5/20/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 5/20/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Final 5/20/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 6/13/2022 Approved EUGENE CASSIDY
Deputy Wood Construction 7/6/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 7/21/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 7/21/2022 Approved EUGENE CASSIDY
Green Building Rough 7/21/2022 Approved EUGENE CASSIDY
HVAC-Rough 7/21/2022 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 7/21/2022 Approved EUGENE CASSIDY
Insulation 7/26/2022 Approved EUGENE CASSIDY
Drywall Nailing 8/2/2022 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 8/16/2022 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 8/23/2022 Partial Approval EUGENE CASSIDY
Shower Pan 8/23/2022 Not Ready for Inspection EUGENE CASSIDY
Shower Pan 8/29/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/6/2022 Approved EUGENE CASSIDY
Drywall Nailing 9/20/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/20/2022 Approved EUGENE CASSIDY
Underground Mechanical 12/14/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 11/8/2023 Not Ready for Inspection EUGENE CASSIDY
Gas Test 11/8/2023 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 11/8/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 11/8/2023 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 11/8/2023 Not Ready for Inspection EUGENE CASSIDY
Gas Test 11/17/2023 Approved JAMES CHAVEZ
Green Building Final 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Final 11/17/2023 Conditional Approval JAMES CHAVEZ
HVAC-Final 12/5/2023 Approved EUGENE CASSIDY
PLUMBING-Final 12/5/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/18/2023 Approved EUGENE CASSIDY
Final 12/18/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 12/18/2023 Approved EUGENE CASSIDY
Service/Power Release 12/18/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 12/18/2023 Approved EUGENE CASSIDY
Final 1/8/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 1/8/2024 Approved EUGENE CASSIDY
PLUMBING-Final 1/8/2024 Approved EUGENE CASSIDY
Service/Power Release 1/8/2024 Not Required EUGENE CASSIDY
Final 1/16/2024 OK to Issue CofO EUGENE CASSIDY