1110-1112 E LANZIT AVE 90059
Certificate Information: 1110-1112 E LANZIT AVE 90059
- Application / Permit
- 19010-10000-01854
- Plan Check / Job No.
- B19LA27054
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New 21'3"x34'7" detached 4-car garage accessory to two detached single family dwellings under 19010-10000-00404 & 19010-10000-04494. NFPA 13D is provided throughout.
- Permit Issued
- Issued on 7/2/2020
- Issuing Office
- Current Status
- CofO Issued on 7/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | TU HUA |
| Corrections Issued | 5/8/2020 | TU HUA |
| Plan Check Approved | 7/2/2020 | TU HUA |
| Issued | 7/2/2020 | APPLICANT |
| CofO in Progress | 7/26/2023 | KEITH EDGHILL |
| Permit Finaled | 7/27/2023 | PAUL BECKER |
| CofO Issued | 7/27/2023 | PAUL BECKER |
| Permit Finaled | 7/27/2023 | PAUL BECKER |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2019 | ELAINE LEI |
| Permit | Cleared | 5/2/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 6/4/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 11/19/2019 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 3/5/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Special/Order Compliance | 8/27/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 9/1/2020 | Approved | KEITH EDGHILL |
| BUILDING-Rough-Frame | 9/22/2020 | Not Ready for Inspection | PAUL BECKER |
| Footing/Foundation/Slab | 9/22/2020 | Corrections Issued | KEITH EDGHILL |
| Footing/Foundation/Slab | 9/29/2020 | Corrections Issued | KEITH EDGHILL |
| BUILDING-Rough-Frame | 10/7/2020 | Conditional Approval | KEITH EDGHILL |
| Footing/Foundation/Slab | 10/7/2020 | Approved | KEITH EDGHILL |
| Excavation/Setback/Form/Re-Bar | 10/20/2020 | Approved | KEITH EDGHILL |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2020 | Approved | KEITH EDGHILL |
| Wood Frame | 12/17/2020 | Approved | KEITH EDGHILL |
| Underground Mechanical | 3/12/2021 | Approved | KEITH EDGHILL |
| Underground Mechanical | 3/19/2021 | Conditional Approval | KEITH EDGHILL |
| BUILDING-Rough-Frame | 11/16/2022 | Approved | KEITH EDGHILL |
| Drywall Nailing | 11/16/2022 | Approved | KEITH EDGHILL |
| Final | 11/16/2022 | Not Ready for Inspection | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Not Ready | KEITH EDGHILL |
| Service/Power Release | 11/16/2022 | Not Ready for Inspection | KEITH EDGHILL |
| Smoke Detectors | 11/16/2022 | Approved | KEITH EDGHILL |
| Final | 3/30/2023 | Not Ready for Inspection | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | KEITH EDGHILL |
| Service/Power Release | 3/30/2023 | Corrections Issued | KEITH EDGHILL |
| Final | 4/24/2023 | Conditional Approval | KEITH EDGHILL |
| Service/Power Release | 4/24/2023 | Approved | KEITH EDGHILL |
| Final | 5/5/2023 | Conditional Approval | KEITH EDGHILL |
| Final | 7/26/2023 | OK to Issue CofO | KEITH EDGHILL |