1110-1112 E LANZIT AVE 90059

Certificate Information: 1110-1112 E LANZIT AVE 90059

Application / Permit
19010-10000-01854
Plan Check / Job No.
B19LA27054
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New 21'3"x34'7" detached 4-car garage accessory to two detached single family dwellings under 19010-10000-00404 & 19010-10000-04494. NFPA 13D is provided throughout.
Permit Issued
Issued on 7/2/2020
Issuing Office
Current Status
CofO Issued on 7/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 TU HUA
Corrections Issued 5/8/2020 TU HUA
Plan Check Approved 7/2/2020 TU HUA
Issued 7/2/2020 APPLICANT
CofO in Progress 7/26/2023 KEITH EDGHILL
Permit Finaled 7/27/2023 PAUL BECKER
CofO Issued 7/27/2023 PAUL BECKER
Permit Finaled 7/27/2023 PAUL BECKER

Permit Application Clearance Information

Address approval Cleared 5/2/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/2/2019 ELAINE LEI
Permit Cleared 5/2/2019 ELAINE LEI
Hydrant and Access approval Cleared 6/4/2019 GEORGE SUCHAND
Green Code Cleared 11/19/2019 KHEDER ALRAZAA
Low Impact Development Cleared 3/5/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 3/5/2020 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2020 Not Ready for Inspection EUGENE CASSIDY
Special/Order Compliance 8/27/2020 Corrections Issued EUGENE CASSIDY
Pre-Inspection 9/1/2020 Approved KEITH EDGHILL
BUILDING-Rough-Frame 9/22/2020 Not Ready for Inspection PAUL BECKER
Footing/Foundation/Slab 9/22/2020 Corrections Issued KEITH EDGHILL
Footing/Foundation/Slab 9/29/2020 Corrections Issued KEITH EDGHILL
BUILDING-Rough-Frame 10/7/2020 Conditional Approval KEITH EDGHILL
Footing/Foundation/Slab 10/7/2020 Approved KEITH EDGHILL
Excavation/Setback/Form/Re-Bar 10/20/2020 Approved KEITH EDGHILL
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Approved KEITH EDGHILL
Wood Frame 12/17/2020 Approved KEITH EDGHILL
Underground Mechanical 3/12/2021 Approved KEITH EDGHILL
Underground Mechanical 3/19/2021 Conditional Approval KEITH EDGHILL
BUILDING-Rough-Frame 11/16/2022 Approved KEITH EDGHILL
Drywall Nailing 11/16/2022 Approved KEITH EDGHILL
Final 11/16/2022 Not Ready for Inspection KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Not Ready KEITH EDGHILL
Service/Power Release 11/16/2022 Not Ready for Inspection KEITH EDGHILL
Smoke Detectors 11/16/2022 Approved KEITH EDGHILL
Final 3/30/2023 Not Ready for Inspection KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved KEITH EDGHILL
Service/Power Release 3/30/2023 Corrections Issued KEITH EDGHILL
Final 4/24/2023 Conditional Approval KEITH EDGHILL
Service/Power Release 4/24/2023 Approved KEITH EDGHILL
Final 5/5/2023 Conditional Approval KEITH EDGHILL
Final 7/26/2023 OK to Issue CofO KEITH EDGHILL