Deputy Reinf. Concrete
|
9/21/2021
|
Conditional Approval
|
LEOPOLDO MENDOZA
|
|
Footing/Foundation/Slab
|
9/29/2021
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
9/29/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
9/30/2021
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/7/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/12/2021
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Masonry
|
10/12/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
10/13/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/13/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
10/14/2021
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
10/15/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
10/19/2021
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
10/21/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
10/22/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
11/3/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
11/4/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
11/5/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
11/8/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
11/9/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
11/10/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/18/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
12/7/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
12/8/2021
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
12/14/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
12/22/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
12/28/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
1/6/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/28/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
2/10/2022
|
Approved
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2022
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/18/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/17/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/21/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
3/22/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
4/6/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
4/7/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/20/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
4/21/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/17/2022
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Wood Construction
|
5/18/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Insulation
|
5/23/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
5/26/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
6/1/2022
|
Partial Approval
|
TED RIES
|
|
Pre-Inspection
|
6/1/2022
|
Approved
|
TED RIES
|
|
Interior/Exterior Lathing
|
6/8/2022
|
Partial Approval
|
TED RIES
|
|
Insulation
|
6/23/2022
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Insulation
|
6/28/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
7/25/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Insulation
|
7/27/2022
|
Not Ready for Inspection
|
TED RIES
|
|
T-Bar Ceiling
|
7/27/2022
|
Not Ready for Inspection
|
TED RIES
|
|
Interior/Exterior Lathing
|
8/11/2022
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
8/16/2022
|
Partial Inspection
|
TED RIES
|
|
Green Building Rough
|
8/16/2022
|
Approved
|
TED RIES
|
|
Insulation
|
8/16/2022
|
Partial Approval
|
TED RIES
|
|
Interior/Exterior Lathing
|
8/16/2022
|
Partial Approval
|
TED RIES
|
|
T-Bar Ceiling
|
8/16/2022
|
Partial Inspection
|
TED RIES
|
|
Drywall Nailing
|
8/31/2022
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
9/3/2022
|
Off-Hour Fees Due
|
|
|
Drywall Nailing
|
9/3/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
9/9/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
9/13/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
9/21/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
9/22/2022
|
Partial Approval
|
TED RIES
|
|
Drywall Nailing
|
9/28/2022
|
Partial Inspection
|
TED RIES
|
|
Light Gage Steel Frame
|
10/25/2022
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
11/15/2022
|
Partial Approval
|
TED RIES
|
|
Special/Order Compliance
|
11/15/2022
|
Approved
|
TED RIES
|
|
Interior/Exterior Lathing
|
11/28/2022
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
12/1/2022
|
Partial Inspection
|
GREGORY POMISH
|
|
Light Gage Steel Frame
|
1/3/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Light Gage Steel Frame
|
1/10/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
1/13/2023
|
Partial Approval
|
TED RIES
|
|
Special/Order Compliance
|
1/13/2023
|
Approved
|
TED RIES
|
|
Drywall Nailing
|
2/13/2023
|
Approved
|
NICK DANERI
|
|
Final
|
2/13/2023
|
Corrections Issued
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
2/13/2023
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
2/13/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
2/13/2023
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
2/13/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
2/13/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
2/13/2023
|
Partial Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
3/3/2023
|
Corrections Issued
|
NICK DANERI
|
|
Final
|
4/12/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Final
|
4/12/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
4/12/2023
|
Partial Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
4/12/2023
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
4/12/2023
|
Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
4/12/2023
|
Approved
|
NICK DANERI
|
|
Verify Rec and Parks Fee Memo
|
4/12/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/12/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
4/12/2023
|
Partial Inspection
|
NICK DANERI
|
|
Final
|
4/25/2023
|
Partial Inspection
|
NICK DANERI
|
|
Green Building Final
|
4/25/2023
|
Approved
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
4/25/2023
|
SGSOV Not Ready
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/25/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
4/25/2023
|
Partial Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
4/26/2023
|
Partial Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
9/27/2023
|
Conditional Approval
|
NICK DANERI
|
|
Final
|
9/28/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
9/28/2023
|
SGSOV Approved
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/28/2023
|
Approved
|
NICK DANERI
|
|
Wood Frame
|
9/28/2023
|
Approved
|
NICK DANERI
|
|
Final
|
10/18/2023
|
OK to Issue CofO
|
GREGORY POMISH
|
|
Special/Order Compliance
|
10/18/2023
|
Partial Inspection
|
GREGORY POMISH
|