Excavation/Setback/Form/Re-Bar
|
11/12/2020
|
Conditional Approval
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
12/28/2020
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
12/30/2020
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/8/2021
|
Conditional Approval
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
1/8/2021
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2021
|
Not Ready for Inspection
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/19/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
2/22/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Methane Barrier
|
3/9/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/10/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/11/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/12/2021
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/12/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
3/17/2021
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/17/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/18/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Shotcrete
|
3/18/2021
|
Conditional Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
3/18/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
5/10/2021
|
Conditional Approval
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
5/13/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/28/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/28/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Barrier
|
5/28/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
METHANE-Subgrade
|
5/28/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
6/1/2021
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
6/3/2021
|
Conditional Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
6/3/2021
|
Partial Approval
|
NICK DANERI
|
|
METHANE-Barrier
|
6/3/2021
|
Approved
|
NICK DANERI
|
|
METHANE-Subgrade
|
6/3/2021
|
Approved
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2021
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
6/29/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
7/6/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
7/7/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
7/8/2021
|
No Access for Inspection
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
7/9/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/6/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/11/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
8/19/2021
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/25/2021
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
9/9/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/10/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
9/29/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/30/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
9/30/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Fireproofing
|
10/7/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
10/8/2021
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Excavation/Setback/Form/Re-Bar
|
10/18/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
10/25/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
10/27/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
10/27/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
10/29/2021
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Wood Construction
|
12/1/2021
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/7/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Drilled-In Anchors
|
12/28/2021
|
Conditional Approval
|
NICK DANERI
|
|
Drywall Nailing
|
12/28/2021
|
Partial Approval
|
NICK DANERI
|
|
Wood Frame
|
12/28/2021
|
Partial Approval
|
NICK DANERI
|
|
Deputy Fireproofing
|
1/25/2022
|
Conditional Approval
|
NICK DANERI
|
|
Insulation
|
2/7/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Fireproofing
|
2/8/2022
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
T-Bar Ceiling
|
3/18/2022
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
3/31/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
4/14/2022
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
4/22/2022
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
5/31/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
6/10/2022
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
9/19/2022
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Drilled-In Anchors
|
9/30/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
9/30/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
10/3/2022
|
Partial Approval
|
NICK DANERI
|
|
Final
|
12/20/2022
|
Partial Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
12/20/2022
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
12/20/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
12/20/2022
|
Approved
|
NICK DANERI
|
|
METHANE-Final
|
12/20/2022
|
Approved
|
NICK DANERI
|
|
METHANE-Rough
|
12/20/2022
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
12/20/2022
|
Partial Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
12/20/2022
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
12/20/2022
|
Approved
|
NICK DANERI
|
|
Structural Steel Frame
|
12/20/2022
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
12/20/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Final
|
12/28/2022
|
Partial Inspection
|
NICK DANERI
|
|
Green Building Final
|
12/28/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
12/28/2022
|
Partial Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
12/28/2022
|
SGSOV Approved
|
NICK DANERI
|
|
Structural Steel Frame
|
12/28/2022
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
12/28/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
12/29/2022
|
Approved
|
JONATHAN ALLEN
|
|
Final
|
12/30/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Final
|
12/30/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
12/30/2022
|
Approved
|
NICK DANERI
|
|
Structural Steel Frame
|
12/30/2022
|
Approved
|
NICK DANERI
|
|
Final
|
1/24/2023
|
OK to Issue CofO
|
NICK DANERI
|
|
Green Building Final
|
1/24/2023
|
Approved
|
NICK DANERI
|