231 S WESTLAKE AVE 90057

Certificate Information: 231 S WESTLAKE AVE 90057

Application / Permit
19010-10000-01816
Plan Check / Job No.
B19LA08688
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW (6)-UNIT APARTMENT BUILDING WITH GARAGE. 5-STORIES. TYPE IIIA. TOC TIER 1
Permit Issued
Issued on 10/22/2020
Issuing Office
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2019 APPLICANT
Assigned to Plan Check Engineer 6/6/2019 VU NGUYEN
Corrections Issued 6/13/2019 VU NGUYEN
Quality Review Completed 6/24/2019 MICHAEL PEREZ
Building Plans Picked Up 6/24/2019 APPLICANT
Disabled Access Plans Picked Up 6/24/2019 APPLICANT
Applicant returned to address corrections 8/14/2019 VU NGUYEN
Applicant returned to address corrections 11/8/2019 VU NGUYEN
Applicant returned to address corrections 12/5/2019 VU NGUYEN
Applicant returned to address corrections 1/9/2020 VU NGUYEN
Applicant returned to address corrections 5/5/2020 VU NGUYEN
Green Plans Picked Up 6/18/2020 APPLICANT
Applicant returned to address corrections 8/27/2020 VU NGUYEN
Plan Check Approved 9/29/2020 VU NGUYEN
Issued 10/22/2020 APPLICANT
CofO in Progress 1/24/2023 NICK DANERI
Permit Finaled 1/25/2023 ERNESTO CORRAL
CofO Issued 1/25/2023 ERNESTO CORRAL
Permit Finaled 1/25/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 6/28/2019 ELAINE LEI
Highway dedication Cleared 6/28/2019 ELAINE LEI
Permit Cleared 6/28/2019 ELAINE LEI
Trees in Parkway Cleared 7/1/2019 JOHN KIM
Low Impact Development Cleared 9/27/2019 MARTIN FRAGOSO
Hydrant and Access approval Cleared 10/3/2019 JEREMY CARTER
Grading Pre-Inspection Cleared 11/19/2019 PATRICK MISCHLICH
Green Code Cleared 12/5/2019 COLIN LOREDO
Fire Marshall Fire Life Safety Cleared 4/21/2020 OSCAR SALGADO JR
Density Bonus 12.22.A.31 Cleared 5/12/2020 NICHOLAS KAWAZOE
Miscellaneous Cleared 5/29/2020 NOAH MCCOY
Miscellaneous Cleared 5/29/2020 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 6/1/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 6/1/2020 JUAN ASHTON
Sewer availability Cleared 6/1/2020 JUAN ASHTON
DAS Clearance Cleared 7/20/2020 VU NGUYEN
Building over 3-story or 36-ft Cleared 8/27/2020 CALOSHA APPROVED
GPI Written Notices Cleared 8/27/2020 VU NGUYEN
Miscellaneous Cleared 8/27/2020 VU NGUYEN

Contact Information

Architect El, Bayar, Sami M; Lic. No.: C26080 22834 BRENFORD STREET      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Heydar,, Ahmad; Lic. No.: S3679 28025 DOROTHY DR STE 104      AGOURA HILLS, CA 91301
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2020 Conditional Approval NICK DANERI
Piling/Pier/Caisson 12/28/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/30/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/8/2021 Conditional Approval NICK DANERI
Piling/Pier/Caisson 1/8/2021 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/3/2021 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 2/19/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/22/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 3/9/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/10/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/11/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/12/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/12/2021 Partial Approval NICK DANERI
Deputy Shotcrete 3/17/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/17/2021 Partial Approval NICK DANERI
Deputy Reinf. Masonry 3/18/2021 Conditional Approval NICK DANERI
Deputy Shotcrete 3/18/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/18/2021 Partial Approval NICK DANERI
Deputy Reinf. Masonry 5/10/2021 Conditional Approval NICK DANERI
Masonry Wall/Backfill 5/13/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/28/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/28/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 5/28/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 5/28/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/1/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/3/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 6/3/2021 Partial Approval NICK DANERI
METHANE-Barrier 6/3/2021 Approved NICK DANERI
METHANE-Subgrade 6/3/2021 Approved NICK DANERI
Excavation/Setback/Form/Re-Bar 6/4/2021 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 6/29/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/6/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/7/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/8/2021 No Access for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 7/9/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/19/2021 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 9/9/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 9/29/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 9/30/2021 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 10/7/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 10/8/2021 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/18/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/25/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/27/2021 Conditional Approval RAFAEL ESPINOZA
Wood Frame 10/27/2021 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/29/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/1/2021 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/28/2021 Conditional Approval NICK DANERI
Drywall Nailing 12/28/2021 Partial Approval NICK DANERI
Wood Frame 12/28/2021 Partial Approval NICK DANERI
Deputy Fireproofing 1/25/2022 Conditional Approval NICK DANERI
Insulation 2/7/2022 Partial Approval NICK DANERI
Deputy Fireproofing 2/8/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval JAMES POWERS
T-Bar Ceiling 3/18/2022 Partial Approval NICK DANERI
Insulation 3/31/2022 Partial Approval NICK DANERI
Drywall Nailing 4/14/2022 Partial Approval NICK DANERI
Drywall Nailing 4/22/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/31/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/10/2022 Partial Approval NICK DANERI
Special/Order Compliance 9/19/2022 Partial Inspection NICK DANERI
Deputy Drilled-In Anchors 9/30/2022 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/30/2022 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 10/3/2022 Partial Approval NICK DANERI
Final 12/20/2022 Partial Inspection NICK DANERI
Footing/Foundation/Slab 12/20/2022 Approved NICK DANERI
Green Building Final 12/20/2022 Not Ready for Inspection NICK DANERI
Green Building Rough 12/20/2022 Approved NICK DANERI
METHANE-Final 12/20/2022 Approved NICK DANERI
METHANE-Rough 12/20/2022 Approved NICK DANERI
Reinforced Masonry Frame 12/20/2022 Partial Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Not Ready NICK DANERI
Smoke Detectors 12/20/2022 Approved NICK DANERI
Structural Steel Frame 12/20/2022 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 12/20/2022 Not Ready for Inspection NICK DANERI
Final 12/28/2022 Partial Inspection NICK DANERI
Green Building Final 12/28/2022 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 12/28/2022 Partial Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved NICK DANERI
Structural Steel Frame 12/28/2022 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 12/28/2022 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 12/29/2022 Approved JONATHAN ALLEN
Final 12/30/2022 Not Ready for Inspection NICK DANERI
Green Building Final 12/30/2022 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 12/30/2022 Approved NICK DANERI
Structural Steel Frame 12/30/2022 Approved NICK DANERI
Final 1/24/2023 OK to Issue CofO NICK DANERI
Green Building Final 1/24/2023 Approved NICK DANERI