13160 W PINNEY ST 91331

Certificate Information: 13160 W PINNEY ST 91331

Application / Permit
19010-10000-01791
Plan Check / Job No.
B19LA08551
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER AB 494 & SB 229
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 EMMANUEL MARTINEZ
Corrections Issued 6/21/2019 SERGIO GUTIERREZ
Quality Review Completed 6/28/2019 KESETE HAREGOT
Building Plans Picked Up 7/10/2019 APPLICANT
Green Plans Picked Up 9/4/2019 APPLICANT
Applicant returned to address corrections 12/18/2019 SERGIO GUTIERREZ
Plan Check Approved 1/13/2020 SERGIO GUTIERREZ
Issued 1/23/2020 LADBS
CofO in Progress 4/21/2021 MICHEL ABAJAN
CofO Issued 5/22/2021 MICHAEL SMITH
Permit Finaled 5/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/1/2019 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 11/1/2019 MAHELET GEBEYHU
Sewer availability Cleared 11/1/2019 MAHELET GEBEYHU
Green Code Cleared 11/6/2019 SARAH ABOULHOSN
Hydrant and Access approval Cleared 11/14/2019 JOHN CONNEALLY
Low Impact Development Cleared 12/5/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/5/2019 JAMES MORALEZ
Stormwater Pollution Mitigatn Cleared 12/18/2019 JORGE MEJIA LEMUS

Contact Information

Contractor Owner-Builder       ,
Engineer Kiggins,, Shawn Douglas; Lic. No.: C67845 2020 REDESDALE AVE      LOS ANGELES, CA 90039

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/21/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 3/20/2020 Approved MICHEL ABAJAN
Grounding or Bonding 3/20/2020 Partial Approval MICHEL ABAJAN
METHANE-Barrier 3/20/2020 Approved MICHEL ABAJAN
METHANE-Rough 3/20/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 3/20/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 3/20/2020 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 5/22/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Approved MICHEL ABAJAN
Green Building Rough 5/22/2020 Approved MICHEL ABAJAN
METHANE-Rough 5/22/2020 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 5/22/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 5/22/2020 Approved MICHEL ABAJAN
Insulation 5/28/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/26/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/26/2020 Approved MICHEL ABAJAN
Shower Pan 6/26/2020 Approved MICHEL ABAJAN
Sewer 1/6/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/25/2021 Approved MICHEL ABAJAN
Final 3/25/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 3/25/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 3/25/2021 Approved MICHEL ABAJAN
PLUMBING-Final 3/25/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 3/25/2021 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 3/25/2021 Approved MICHEL ABAJAN
Final 4/20/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 4/20/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved MICHEL ABAJAN
Service/Power Release 4/20/2021 Approved MICHEL ABAJAN