4436-4436 1/2 S LIMA ST 90011
Certificate Information: 4436-4436 1/2 S LIMA ST 90011
- Application / Permit
- 19010-10000-01787
- Plan Check / Job No.
- B19LA08532
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW TWO-STORY DUPLEX 2,486 SQ FT (FRONT BUILDING 1)
- Permit Issued
- Issued on 6/11/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | RACHEL BEYENE |
| Corrections Issued | 5/21/2019 | RACHEL BEYENE |
| Green Plans Picked Up | 5/29/2019 | APPLICANT |
| Quality Review Completed | 6/14/2019 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/8/2019 | RACHEL BEYENE |
| Applicant returned to address corrections | 11/26/2019 | RACHEL BEYENE |
| Applicant returned to address corrections | 12/31/2019 | RACHEL BEYENE |
| Plan Check Approved | 1/2/2020 | RAHEL BEYENE |
| Issued | 6/11/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 8/18/2022 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 8/22/2022 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 8/24/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/25/2022 | DEROLD HAUFF |
| CofO Issued | 8/25/2022 | DEROLD HAUFF |
| Permit Finaled | 8/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2019 | JEANETTE VONG |
| Permit | Cleared | 6/20/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 6/20/2019 | JEANETTE VONG |
| Trees in Parkway | Cleared | 6/20/2019 | JOHN KIM |
| ZI | Cleared | 6/20/2019 | JOE LUCKEY |
| Hydrant and Access approval | Cleared | 6/26/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 7/31/2019 | MARTIN FRAGOSO |
| Green Code | Cleared | 8/8/2019 | KHEDER ALRAZAA |
| Roof/Waste drainage to street | Cleared | 8/8/2019 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Orozco Victor Construction; Lic. No.: 982481-B | 126 W J STREET ONTARIO, CA 91762 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/16/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/16/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 6/30/2021 | Corrections Issued | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 9/16/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 10/1/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Approved | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 10/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/7/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/7/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 10/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 10/8/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 10/8/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/13/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/13/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/13/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/15/2021 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 11/15/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 12/3/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/8/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/4/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 1/4/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 1/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| Underground Mechanical | 2/4/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 3/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 3/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 3/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Sewer | 5/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Sewer | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 6/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/22/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 6/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 6/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/9/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/11/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/11/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/11/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/16/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 8/23/2022 | Approved | ALEJANDRO DE ARTOLA |