801 E E ST 90744

Certificate Information: 801 E E ST 90744

Application / Permit
19010-10000-01761
Plan Check / Job No.
B19LA08448
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
NEW WAREHOUSE W/MEZZANINE FOR COLD STORAGE.
Permit Issued
Issued on 8/30/2019
Issuing Office
Metro
Current Status
Permit Finaled on 8/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2019 APPLICANT
Green Plans Picked Up 5/13/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 JOE VO
Disabled Access Plans Picked Up 5/16/2019 APPLICANT
Corrections Issued 5/20/2019 JOE VO
Quality Review Completed 5/21/2019 GARO TELMI
Building Plans Picked Up 5/22/2019 APPLICANT
Applicant returned to address corrections 7/8/2019 JOE VO
Plan Check Approved 8/26/2019 JOE VO
Plan Check Approved 8/30/2019 JOE VO
Issued 8/30/2019 LADBS
Permit Finaled 8/18/2020 JOEY BUCHANAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/6/2019 JENNY CEA
"Q" conditions Cleared 6/18/2019 BLAYNE SUTTON-WILLS
Permit Cleared 6/21/2019 ALINE MILLER
DAS Clearance Cleared 7/12/2019 ELIZABETH TOMS
Sewer availability Cleared 7/15/2019 ERIK BEASLEY
Highway dedication Cleared 7/16/2019 PHILLIP WILSON
Roof/Waste drainage to street Cleared 7/16/2019 PHILLIP WILSON
Prkng lot landscape/Water mgmt Cleared 7/24/2019 JOE LUCKEY
Project located in CRA area Cleared 7/25/2019 JIM URQUHART
Abandoned oil well Cleared 7/31/2019 GEORGE SUCHAND
Hydrant and Access approval Cleared 7/31/2019 GEORGE SUCHAND
Clean Up Green Up Cleared 8/1/2019 JOE LUCKEY
Site Plan review Cleared 8/1/2019 JOE LUCKEY
ZA Case Cleared 8/1/2019 JOE LUCKEY
ZI Cleared 8/1/2019 JOE LUCKEY
Low Impact Development Cleared 8/2/2019 ORVAL HERNANDEZ-MARCI
Green Code Cleared 8/6/2019 KHEDER ALRAZAA
Miscellaneous Cleared 8/15/2019 JOE VO
Trees in Parkway Cleared 8/15/2019 ADRIAN SANCHEZ

Contact Information

Architect Gillings,, Bruce D; Lic. No.: C14644 16 SKYCREST      MISSION VIEJO, CA 92692
Contractor Alston Construction Company Inc; Lic. No.: 759899-B 3500 LENOX RD STE 501      ATLANTA, GA 30326
Engineer Jacoby,, Samuel J; Lic. No.: C74309 8881 RESEARCH DR      IRVINE, CA 92618

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 10/16/2019 Approved RAFAEL ESPINOZA
Structural Steel Frame 10/22/2019 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 10/30/2019 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 10/30/2019 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 10/30/2019 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 11/15/2019 Partial Approval NICK LAROCCA
METHANE-Barrier 11/15/2019 Approved NICK LAROCCA
Deputy Steel/Welding 1/3/2020 Approved RAFAEL ESPINOZA
Light Gage Steel Frame 1/31/2020 Conditional Approval RAFAEL ESPINOZA
Structural Steel Frame 1/31/2020 Approved RAFAEL ESPINOZA
Deputy Reinf. Masonry 2/21/2020 Approved JOEY BUCHANAN
Drywall Nailing 2/26/2020 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 3/4/2020 Partial Approval JOEY BUCHANAN
T-Bar Ceiling 3/31/2020 Partial Approval JOEY BUCHANAN
Final 4/8/2020 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 4/8/2020 Approved JOEY BUCHANAN
Green Building Final 4/8/2020 Not Ready for Inspection JOEY BUCHANAN
Green Building Rough 4/8/2020 Approved JOEY BUCHANAN
METHANE-Final 4/8/2020 Not Ready for Inspection JOEY BUCHANAN
METHANE-Rough 4/8/2020 Approved JOEY BUCHANAN
Reinforced Masonry Frame 4/8/2020 Not Ready for Inspection JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 4/8/2020 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 4/8/2020 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 4/8/2020 Approved JOEY BUCHANAN
Deputy Fireproofing 4/23/2020 Approved JOEY BUCHANAN
Final 4/27/2020 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 4/27/2020 Approved JOEY BUCHANAN
METHANE-Final 4/27/2020 No Access for Inspection JOEY BUCHANAN
METHANE-Rough 4/27/2020 Approved JOEY BUCHANAN
Reinforced Masonry Frame 4/27/2020 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 5/1/2020 Approved JOEY BUCHANAN
Final 5/18/2020 Not Ready for Inspection JOEY BUCHANAN
METHANE-Final 5/18/2020 Not Ready for Inspection JOEY BUCHANAN
METHANE-Rough 5/18/2020 Approved JOEY BUCHANAN
Reinforced Masonry Frame 5/18/2020 Not Ready for Inspection JOEY BUCHANAN
METHANE-Final 5/22/2020 Approved JOEY BUCHANAN
METHANE-Rough 5/22/2020 Approved JOEY BUCHANAN
Reinforced Masonry Frame 5/22/2020 Approved JOEY BUCHANAN
Final 5/26/2020 Corrections Issued JOEY BUCHANAN
Special/Order Compliance 5/26/2020 Approved JOEY BUCHANAN
Final 6/4/2020 Not Ready for Inspection JOEY BUCHANAN
Final 6/23/2020 Corrections Issued JOEY BUCHANAN
Final 7/16/2020 Corrections Issued JOEY BUCHANAN
Final 8/3/2020 Conditional Approval JOEY BUCHANAN