801 E E ST 90744
Certificate Information: 801 E E ST 90744
- Application / Permit
- 19010-10000-01761
- Plan Check / Job No.
- B19LA08448
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- NEW WAREHOUSE W/MEZZANINE FOR COLD STORAGE.
- Permit Issued
- Issued on 8/30/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Green Plans Picked Up | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | JOE VO |
| Disabled Access Plans Picked Up | 5/16/2019 | APPLICANT |
| Corrections Issued | 5/20/2019 | JOE VO |
| Quality Review Completed | 5/21/2019 | GARO TELMI |
| Building Plans Picked Up | 5/22/2019 | APPLICANT |
| Applicant returned to address corrections | 7/8/2019 | JOE VO |
| Plan Check Approved | 8/26/2019 | JOE VO |
| Plan Check Approved | 8/30/2019 | JOE VO |
| Issued | 8/30/2019 | LADBS |
| Permit Finaled | 8/18/2020 | JOEY BUCHANAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2019 | JENNY CEA |
| "Q" conditions | Cleared | 6/18/2019 | BLAYNE SUTTON-WILLS |
| Permit | Cleared | 6/21/2019 | ALINE MILLER |
| DAS Clearance | Cleared | 7/12/2019 | ELIZABETH TOMS |
| Sewer availability | Cleared | 7/15/2019 | ERIK BEASLEY |
| Highway dedication | Cleared | 7/16/2019 | PHILLIP WILSON |
| Roof/Waste drainage to street | Cleared | 7/16/2019 | PHILLIP WILSON |
| Prkng lot landscape/Water mgmt | Cleared | 7/24/2019 | JOE LUCKEY |
| Project located in CRA area | Cleared | 7/25/2019 | JIM URQUHART |
| Abandoned oil well | Cleared | 7/31/2019 | GEORGE SUCHAND |
| Hydrant and Access approval | Cleared | 7/31/2019 | GEORGE SUCHAND |
| Clean Up Green Up | Cleared | 8/1/2019 | JOE LUCKEY |
| Site Plan review | Cleared | 8/1/2019 | JOE LUCKEY |
| ZA Case | Cleared | 8/1/2019 | JOE LUCKEY |
| ZI | Cleared | 8/1/2019 | JOE LUCKEY |
| Low Impact Development | Cleared | 8/2/2019 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 8/6/2019 | KHEDER ALRAZAA |
| Miscellaneous | Cleared | 8/15/2019 | JOE VO |
| Trees in Parkway | Cleared | 8/15/2019 | ADRIAN SANCHEZ |
Contact Information
| Architect | Gillings,, Bruce D; Lic. No.: C14644 | 16 SKYCREST MISSION VIEJO, CA 92692 |
| Contractor | Alston Construction Company Inc; Lic. No.: 759899-B | 3500 LENOX RD STE 501 ATLANTA, GA 30326 |
| Engineer | Jacoby,, Samuel J; Lic. No.: C74309 | 8881 RESEARCH DR IRVINE, CA 92618 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 10/16/2019 | Approved | RAFAEL ESPINOZA |
| Structural Steel Frame | 10/22/2019 | Partial Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 10/30/2019 | Partial Approval | RAFAEL ESPINOZA |
| METHANE-Barrier | 10/30/2019 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Subgrade | 10/30/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 11/15/2019 | Partial Approval | NICK LAROCCA |
| METHANE-Barrier | 11/15/2019 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 1/3/2020 | Approved | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 1/31/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Structural Steel Frame | 1/31/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 2/21/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 2/26/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/4/2020 | Partial Approval | JOEY BUCHANAN |
| T-Bar Ceiling | 3/31/2020 | Partial Approval | JOEY BUCHANAN |
| Final | 4/8/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/8/2020 | Approved | JOEY BUCHANAN |
| Green Building Final | 4/8/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Rough | 4/8/2020 | Approved | JOEY BUCHANAN |
| METHANE-Final | 4/8/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| METHANE-Rough | 4/8/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 4/8/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 4/8/2020 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 4/8/2020 | Approved | JOEY BUCHANAN |
| Deputy Fireproofing | 4/23/2020 | Approved | JOEY BUCHANAN |
| Final | 4/27/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Final | 4/27/2020 | Approved | JOEY BUCHANAN |
| METHANE-Final | 4/27/2020 | No Access for Inspection | JOEY BUCHANAN |
| METHANE-Rough | 4/27/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 4/27/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Pre-Inspection | 5/1/2020 | Approved | JOEY BUCHANAN |
| Final | 5/18/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| METHANE-Final | 5/18/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| METHANE-Rough | 5/18/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 5/18/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| METHANE-Final | 5/22/2020 | Approved | JOEY BUCHANAN |
| METHANE-Rough | 5/22/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 5/22/2020 | Approved | JOEY BUCHANAN |
| Final | 5/26/2020 | Corrections Issued | JOEY BUCHANAN |
| Special/Order Compliance | 5/26/2020 | Approved | JOEY BUCHANAN |
| Final | 6/4/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 6/23/2020 | Corrections Issued | JOEY BUCHANAN |
| Final | 7/16/2020 | Corrections Issued | JOEY BUCHANAN |
| Final | 8/3/2020 | Conditional Approval | JOEY BUCHANAN |