3800 S FIGUEROA ST 90037

Certificate Information: 3800 S FIGUEROA ST 90037

Application / Permit
19010-10000-01753
Plan Check / Job No.
B19LA08397
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
PROPOSED MIXED USE RETAIL/APARTMENT BUILDING. 7 STORY ABOVE GRADE WITH ONE LEVEL OF BASEMENT PARKING. 79-DWELLING UNITS STEEL STAIRS, RAILS GUARD RAILS, WOOD TRUSSES AND TIEDOWN SYSTEMS ARE DEFERRED STRUCTURALLY
Permit Issued
Issued on 6/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 WING SUEN
Corrections Issued 6/20/2019 WING SUEN
Quality Review Completed 7/5/2019 CHARLES CHANG
Building Plans Picked Up 7/8/2019 APPLICANT
Applicant returned to address corrections 8/20/2019 WING SUEN
Applicant returned to address corrections 9/19/2019 WING SUEN
Applicant returned to address corrections 9/26/2019 JOHN VASQUEZ
Applicant returned to address corrections 10/1/2019 JOHN VASQUEZ
Applicant returned to address corrections 11/15/2019 JOHN VASQUEZ
Applicant returned to address corrections 12/16/2019 JOHN VASQUEZ
Applicant returned to address corrections 1/10/2020 JOHN VASQUEZ
Applicant returned to address corrections 1/24/2020 JOHN VASQUEZ
Applicant returned to address corrections 2/6/2020 JOHN VASQUEZ
Applicant returned to address corrections 2/18/2020 JOHN VASQUEZ
Applicant returned to address corrections 2/26/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/2/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/12/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/13/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/19/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/20/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/26/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/21/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/5/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/13/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/21/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/26/2020 JOHN VASQUEZ
Plan Check Approved 5/29/2020 JOHN VASQUEZ
Issued 6/9/2020 LADBS
TCO Issued (Expire Date: 01-25-2023) 7/29/2022 TERRY HERR
CofO in Progress 1/11/2023 JAMES POWERS
CofO in Progress 1/12/2023 JAMES POWERS
TCO Issued (Expire Date: 07-12-2023) 1/13/2023 ERNESTO CORRAL
CofO in Progress 3/21/2023 JAMES POWERS
CofO Issued 3/22/2023 ERNESTO CORRAL
Permit Finaled 3/22/2023 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/7/2019 ELENA LOPEZ
Highway dedication Cleared 6/19/2019 ELENA LOPEZ
Address approval Cleared 7/17/2019 CELINA MORENO
Project located in CRA area Cleared 7/23/2019 JIM URQUHART
Driveway location Cleared 8/8/2019 COLLINS ALLAN
Internal circulation Cleared 8/8/2019 COLLINS ALLAN
Miscellaneous Cleared 8/8/2019 COLLINS ALLAN
Permit Cleared 8/8/2019 ADRIAN SANCHEZ
Sewer availability Cleared 8/8/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 8/30/2019 JOHN KIM
Work Adjacent to Public Way Cleared 9/25/2019 BOK GOH
Hydrant and Access approval Cleared 10/1/2019 JEREMY CARTER
Building over 3-story or 36-ft Cleared 10/10/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/10/2019 CALOSHA APPROVED
Green Code Cleared 11/13/2019 KHEDER ALRAZAA
Low Impact Development Cleared 12/5/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/6/2019 ELENA LOPEZ
Encroachment in public way Cleared 1/17/2020 ELAINE LEI
Bicycle Parking Cleared 1/29/2020 ELAINE LEI
Stormwater Pollution Mitigatn Cleared 1/29/2020 ORVAL HERNANDEZ-MARCI
DAS Clearance Cleared 2/21/2020 WING SUEN
Fire Marshall Fire Life Safety Cleared 2/25/2020 WILLIAM JOHNS
Density Bonus 12.22.A.25 Cleared 3/25/2020 DORIS KWOK
ZI Cleared 3/25/2020 JOE LUCKEY
ZI Cleared 3/25/2020 JOE LUCKEY
ZI Cleared 3/25/2020 JOE LUCKEY
CPC Cleared 4/15/2020 JOE LUCKEY
Miscellaneous Cleared 4/15/2020 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 4/15/2020 JOE LUCKEY
Site Plan review Cleared 4/15/2020 JOE LUCKEY

Contact Information

Architect Antunovich,, Joseph Michael; Lic. No.: C8708 224 W HURON ST 7TH FL      CHICAGO, IL 606543981
Contractor A & R Corporation Inc; Lic. No.: 951076-B 34 TALMONT      NEWPORT COAST, CA 92657
Engineer Eosakul,, Dissakorn; Lic. No.: S5226 8363 EDGE WOOD ST      CHINO, CA 91708
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Ranta,, Shahrzad; Lic. No.: C77729 1360 S FIGUEROA STREET 513      LOS ANGELES, CA 90015
Landscape Architect Armstrong,, Martin A; Lic. No.: LA4607 126 4TH STREET      DEL MAR, CA 92014

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/11/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/12/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/19/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 6/23/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 6/24/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/26/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 6/26/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 6/29/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/30/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/1/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/1/2020 Partial Inspection JAMES POWERS
Deputy Shotcrete 7/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/7/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/7/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 7/8/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/10/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/13/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/22/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/24/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/30/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/4/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/14/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/25/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/28/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/31/2020 Partial Approval JAMES POWERS
Green Building Rough 9/1/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/1/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/2/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/2/2020 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 9/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/18/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/22/2020 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/15/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/19/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/20/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/2/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/4/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/10/2020 Partial Approval JAMES POWERS
Insulation 11/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/24/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/1/2020 Partial Approval JAMES POWERS
Insulation 12/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/2/2020 Partial Approval JAMES POWERS
Insulation 12/2/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/7/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/16/2020 Partial Approval JAMES POWERS
Insulation 12/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/22/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/26/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 1/27/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/2/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/2/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/9/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/10/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/11/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/12/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/19/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/5/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/8/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 3/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/9/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/15/2021 Partial Approval JAMES POWERS
Green Building Rough 3/17/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 3/17/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/17/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/23/2021 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 3/30/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/31/2021 Partial Approval JAMES POWERS
Green Building Rough 3/31/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/31/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/31/2021 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 4/1/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 4/5/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/6/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/7/2021 Partial Approval JAMES POWERS
Structural Steel Frame 4/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/8/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 4/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/9/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/9/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/12/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 4/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/26/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Masonry 4/27/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/27/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/28/2021 Conditional Approval NICK DANERI
Footing/Foundation/Slab 4/28/2021 Partial Approval NICK DANERI
Masonry Wall/Backfill 4/29/2021 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/30/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Wood Construction 4/30/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Steel/Welding 5/3/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/4/2021 Partial Approval JAMES POWERS
Wood Frame 5/4/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/6/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/7/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 5/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/10/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 5/11/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Fireproofing 5/12/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/12/2021 Partial Approval JAMES POWERS
Wood Frame 5/12/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 5/13/2021 Partial Approval JAMES POWERS
Wood Frame 5/17/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/20/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/25/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/27/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 6/1/2021 Partial Approval JAMES POWERS
Wood Frame 6/1/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 6/10/2021 Not Ready for Inspection JAMES POWERS
Insulation 6/29/2021 Partial Approval JAMES POWERS
Wood Frame 7/15/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 7/22/2021 Partial Approval JAMES POWERS
Insulation 8/2/2021 Not Ready for Inspection JAMES POWERS
Insulation 8/6/2021 Partial Approval JAMES POWERS
Wood Frame 8/31/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 9/14/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/4/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/18/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 10/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2021 Partial Approval JAMES POWERS
Insulation 11/8/2021 Partial Approval RUSSELL BONVOULOIR
Insulation 11/12/2021 Partial Approval JAMES POWERS
Insulation 11/17/2021 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 11/22/2021 Partial Approval TED RIES
Insulation 11/30/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/3/2021 Partial Approval NICK DANERI
Pre-Inspection 12/14/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/20/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Partial Approval JAMES POWERS
Wood Frame 1/14/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 1/20/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/21/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 1/25/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/31/2022 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 2/4/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/10/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/15/2022 Partial Approval JAMES POWERS
Drywall Nailing 4/1/2022 Partial Approval TED RIES
Interior/Exterior Lathing 4/14/2022 Partial Approval JAMES POWERS
Pre-Inspection 5/25/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 6/7/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 6/8/2022 Partial Approval JAMES POWERS
Final 6/17/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/17/2022 Approved JAMES POWERS
Green Building Final 6/17/2022 Approved JAMES POWERS
Green Building Rough 6/17/2022 Approved JAMES POWERS
Reinforced Concrete Frame 6/17/2022 Partial Approval JAMES POWERS
Reinforced Masonry Frame 6/17/2022 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Not Ready JAMES POWERS
SUSMP-Std. Urban Storm Water 6/17/2022 Approved JAMES POWERS
Smoke Detectors 6/17/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 6/17/2022 Not Ready for Inspection JAMES POWERS
Final 6/24/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/24/2022 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 6/24/2022 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 6/24/2022 Not Ready for Inspection JAMES POWERS
Final 6/29/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/29/2022 Approved JAMES POWERS
Reinforced Masonry Frame 6/29/2022 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 6/29/2022 Approved JAMES POWERS
Final 7/6/2022 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/6/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Not Ready JAMES POWERS
Final 7/20/2022 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 7/20/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready JAMES POWERS
Final 7/27/2022 OK for TCO JAMES POWERS
Reinforced Masonry Frame 7/27/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved JAMES POWERS
Final 8/10/2022 Not Ready for Inspection JAMES POWERS
Final 8/16/2022 Not Ready for Inspection JAMES POWERS
Final 8/23/2022 Not Ready for Inspection JAMES POWERS
Final 8/29/2022 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 12/28/2022 Approved JAMES POWERS
Final 1/11/2023 Partial Inspection JAMES POWERS
Final 3/21/2023 OK to Issue CofO JAMES POWERS