11831 W CHAPARAL ST 90049
Certificate Information: 11831 W CHAPARAL ST 90049
- Application / Permit
- 19010-10000-01722
- Plan Check / Job No.
- B18WL03974
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) POOL HOUSE WITH FULL BATHROOM ACCESSORY TO POOL
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2018 | LAMAR DAVIS |
| Corrections Issued | 8/13/2018 | LAMAR DAVIS |
| Quality Review Completed | 8/24/2018 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/5/2018 | APPLICANT |
| Green Plans Picked Up | 9/6/2018 | APPLICANT |
| Applicant returned to address corrections | 3/28/2019 | LAMAR DAVIS |
| Applicant returned to address corrections | 4/9/2019 | LAMAR DAVIS |
| Applicant returned to address corrections | 4/24/2019 | LAMAR DAVIS |
| Applicant returned to address corrections | 5/8/2019 | LAMAR DAVIS |
| Plan Check Approved | 5/30/2019 | LAMAR DAVIS |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 10/5/2024 | CARLOS MATAMOROS |
| CofO Issued | 10/30/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/30/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/25/2019 | BRIAN OLSON |
| Grading Pre-Inspection | Cleared | 4/25/2019 | BRIAN OLSON |
| Miscellaneous | Cleared | 4/25/2019 | LAMAR DAVIS |
| Miscellaneous | Cleared | 4/25/2019 | LAMAR DAVIS |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2019 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 5/2/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 5/2/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 5/2/2019 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 5/2/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/2/2019 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 5/2/2019 | NOAH MCCOY |
| Hydrant and Access approval | Cleared | 5/6/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 5/6/2019 | MITESH PATEL |
| Green Code | Cleared | 5/7/2019 | DONALD CRICHLOW |
Contact Information
| Architect | Massara,, Carl; Lic. No.: C22628 | 1211 HOLLOW ROAD BIRCHRUNVILLE, PA 19421 |
| Contractor | Owner-Builder | , |
| Engineer | Daneshfar, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Phillips, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Feffer, Joshua Rafael; Lic. No.: GEO6861 | 12253 GORHAM AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/29/2021 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 6/30/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/19/2021 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/30/2021 | Approved | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 7/30/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 7/20/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/20/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 8/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 9/30/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/30/2024 | Approved | CARLOS MATAMOROS |
| Final | 9/30/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 9/30/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/30/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 9/30/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 9/30/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 9/30/2024 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/30/2024 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/30/2024 | Approved | CARLOS MATAMOROS |