3442 W DESCANSO DR 90026
Certificate Information: 3442 W DESCANSO DR 90026
- Application / Permit
- 19010-10000-01612
- Plan Check / Job No.
- B19LA07713
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BUILD NEW 37'-7"x 71' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE AND ROOF DECK
- Permit Issued
- Issued on 9/27/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2019 | VU NGUYEN |
| Corrections Issued | 5/28/2019 | VU NGUYEN |
| Quality Review Completed | 5/29/2019 | MICHAEL PEREZ |
| Green Plans Picked Up | 5/29/2019 | APPLICANT |
| Building Plans Picked Up | 5/30/2019 | APPLICANT |
| Plan Check Approved | 7/30/2019 | VU NGUYEN |
| Issued | 9/27/2019 | LADBS |
| CofO in Progress | 3/16/2021 | ROBERT VORHIS |
| Permit Finaled | 4/6/2021 | DEROLD HAUFF |
| CofO Issued | 4/6/2021 | DEROLD HAUFF |
| Permit Finaled | 4/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2019 | ELAINE LEI |
| Highway dedication | Cleared | 7/8/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 7/8/2019 | ROBERT DUFF |
| Miscellaneous | Cleared | 7/8/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 7/8/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 7/8/2019 | SOPHIE GABEL-SCHEINBAU |
| Permit | Cleared | 7/8/2019 | ELAINE LEI |
| Sewer availability | Cleared | 7/8/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 7/18/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/18/2019 | ELAINE LEI |
| Green Code | Cleared | 7/24/2019 | VU NGUYEN |
| Disturb/Remove Protected Trees | Cleared | 7/26/2019 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 7/30/2019 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 7/30/2019 | VU NGUYEN |
Contact Information
| Architect | Lee,, Wan; Lic. No.: C30792 | 1374 1/2 EDGECLIFFE DR. LOS ANGELES, CA 90026 |
| Contractor | L C Construction & Plumbing Corp; Lic. No.: 538151-B | 10021 E GARVEY AVENUE EL MONTE, CA 91733 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/1/2019 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 10/11/2019 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 10/15/2019 | Approved | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 11/12/2019 | Partial Approval | ROBERT VORHIS |
| Deputy Reinf. Concrete | 11/13/2019 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 11/21/2019 | Partial Approval | ROBERT VORHIS |
| Sewer | 11/21/2019 | Approved | ROBERT VORHIS |
| Deputy Reinf. Concrete | 11/22/2019 | Conditional Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 12/3/2019 | Approved | ROBERT VORHIS |
| Deputy Reinf. Concrete | 12/5/2019 | Conditional Approval | ROBERT VORHIS |
| Deputy Steel/Welding | 12/9/2019 | Conditional Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2020 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 3/13/2020 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 3/17/2020 | Approved | ROBERT VORHIS |
| Deputy Wood Construction | 3/23/2020 | Conditional Approval | ROBERT VORHIS |
| Deputy Steel/Welding | 4/27/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/11/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/3/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 6/25/2020 | Approved | ROBERT VORHIS |
| Green Building Rough | 6/25/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 6/25/2020 | Partial Approval | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 6/25/2020 | Approved | ROBERT VORHIS |
| Insulation | 7/8/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 7/21/2020 | Approved | THOMAS LOGRASSO |
| Shower Pan | 8/17/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/25/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/8/2021 | Partial Inspection | ROBERT VORHIS |
| Service/Power Release | 1/8/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Final | 2/2/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 2/2/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 2/2/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 2/23/2021 | Approved | ROBERT VORHIS |
| HVAC-Final | 2/23/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 2/23/2021 | Approved | ROBERT VORHIS |
| Final | 3/8/2021 | Conditional Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 3/8/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 3/8/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2021 | SGSOV Approved | ROBERT VORHIS |
| Service/Power Release | 3/8/2021 | Approved | ROBERT VORHIS |
| Smoke Detectors | 3/8/2021 | Approved | ROBERT VORHIS |