2311 1/2 N GLOVER PL 90031

Certificate Information: 2311 1/2 N GLOVER PL 90031

Application / Permit
19010-10000-01557
Plan Check / Job No.
B19LA07510
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 9/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2019 APPLICANT
Green Plans Picked Up 5/1/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 LAMAR DAVIS
Corrections Issued 5/6/2019 LAMAR DAVIS
Quality Review Completed 5/7/2019 FELIX FIGUEROA
Building Plans Picked Up 5/8/2019 APPLICANT
Applicant returned to address corrections 3/5/2020 LAMAR DAVIS
Plan Check Approved 10/9/2020 LAMAR DAVIS
Issued 12/1/2020 APPLICANT
CofO in Progress 8/1/2022 THOMAS LOGRASSO
Permit Finaled 9/2/2022 DEROLD HAUFF
CofO Issued 9/2/2022 DEROLD HAUFF
Permit Finaled 9/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/4/2020 KHEDER ALRAZAA
Address approval Cleared 3/5/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/5/2020 CELINA MORENO
Low Impact Development Cleared 3/5/2020 MITESH PATEL
Permit Cleared 3/5/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 3/5/2020 CELINA MORENO
Sewer availability Cleared 3/5/2020 CELINA MORENO
ZI Cleared 3/5/2020 RUBEN VASQUEZ
Construction near power lines Cleared 3/19/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 9/30/2020 KURT CORRAL
Miscellaneous Cleared 10/9/2020 LAMAR DAVIS

Contact Information

Contractor Owner-Builder       ,
Engineer Jung,, Jason Stanley; Lic. No.: C80569 1032 S PALM AVE      SAN GABRIEL, CA 91776

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/14/2021 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 7/20/2021 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Approved THOMAS LOGRASSO
Pre-Inspection 10/12/2021 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 11/18/2021 Approved THOMAS LOGRASSO
Underground Mechanical 11/18/2021 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 12/15/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 12/15/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 12/15/2021 Approved SCOTT FINNILA
HVAC-Rough 12/15/2021 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 12/15/2021 Partial Approval SCOTT FINNILA
MERV13>=Rough 12/15/2021 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 12/15/2021 Partial Inspection SCOTT FINNILA
Wood Frame 12/15/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/4/2022 Corrections Issued THOMAS LOGRASSO
Insulation 1/4/2022 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/4/2022 Approved THOMAS LOGRASSO
Drywall Nailing 1/12/2022 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 1/14/2022 Approved THOMAS LOGRASSO
Insulation 1/14/2022 Approved THOMAS LOGRASSO
Sewer 5/6/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/7/2022 Approved THOMAS LOGRASSO
Final 7/7/2022 Partial Inspection THOMAS LOGRASSO
Green Building Final 7/7/2022 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 7/7/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 7/7/2022 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 7/7/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 7/25/2022 Approved THOMAS LOGRASSO
Final 7/25/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 7/25/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 7/25/2022 Approved THOMAS LOGRASSO
MERV13>=Final 7/25/2022 Approved THOMAS LOGRASSO
PLUMBING-Final 7/25/2022 Approved THOMAS LOGRASSO
Service/Power Release 7/25/2022 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 7/25/2022 Approved THOMAS LOGRASSO
Final 8/1/2022 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 8/1/2022 Approved THOMAS LOGRASSO
Service/Power Release 8/1/2022 Approved THOMAS LOGRASSO