923 S KENMORE AVE 1-75 90006

Certificate Information: 923 S KENMORE AVE 1-75 90006

Application / Permit
19010-10000-01542
Plan Check / Job No.
B19LA07460
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 75-unit 5-Story Type III-A Affordable Residential Building Over 1-Story on-grade Type I-A Parking Garage and Common Spaces. 5 extremely low income, 6 very low income and 63 low income units per 12.22.A.31
Permit Issued
Issued on 4/15/2021
Issuing Office
Metro
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 JOE VO
Corrections Issued 7/8/2019 JOE VO
Quality Review Completed 7/16/2019 GARO TELMI
Building Plans Picked Up 7/22/2019 APPLICANT
Applicant returned to address corrections 12/8/2020 JOE VO
Applicant returned to address corrections 2/23/2021 JOE VO
Applicant returned to address corrections 3/8/2021 JOE VO
Plan Check Approved 4/5/2021 JOE VO
Issued 4/15/2021 APPLICANT
TCO Issued (Expire Date: 04-27-2024) 10/30/2023 ADAM BURGESS
CofO in Progress 12/26/2023 NICK DANERI
CofO Issued 12/27/2023 ERNESTO CORRAL
Permit Finaled 12/27/2023 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 11/15/2019 ANNA VAN
Project located in CRA area Cleared 11/15/2019 GISELLE CORELLA
ZI Cleared 11/15/2019 GISELLE CORELLA
Driveway location Cleared 2/4/2020 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 2/4/2020 CELINA MORENO
Permit Cleared 2/4/2020 THOMAS LANG
Housing rent stabilization Cleared 3/9/2020 CHARLES GARCIA
Address approval Cleared 3/16/2020 HOWARD COOPER
Building over 3-story or 36-ft Cleared 3/18/2020 CALOSHA APPROVED
Highway dedication Cleared 5/18/2020 CELINA MORENO
Sewer availability Cleared 7/23/2020 CELINA MORENO
Density Bonus 12.22.A.31 Cleared 11/13/2020 LOUIE MILLER
Work Adjacent to Public Way Cleared 12/14/2020 CHIU TAM
Low Impact Development Cleared 12/15/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/29/2020 TERRY PHAN
Hydrant and Access approval Cleared 1/7/2021 MATTHEW CRAIG
Public Housing Cleared 2/16/2021 RUBEN REYES
DAS Clearance Cleared 2/18/2021 JOE VO
Fire Marshall Fire Life Safety Cleared 2/19/2021 PEJMAN NOORI
Green Code Cleared 3/3/2021 AARON COSTA
Frnt yard landscape/Water mgmt Cleared 3/5/2021 RICHARD REASER
Opn space landscape/Water mgmt Cleared 3/5/2021 RICHARD REASER
Site Plan review Cleared 3/5/2021 RICHARD REASER
ZA Case Cleared 3/5/2021 RICHARD REASER
ZA Case Cleared 3/5/2021 RICHARD REASER
ZA Case Cleared 3/5/2021 RICHARD REASER

Contact Information

Contractor Alpha Construction Co Inc; Lic. No.: 241368-B 14601 AETNA STREET      VAN NUYS, CA 91411

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/29/2021 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/9/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/27/2021 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 7/28/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 8/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 8/12/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 8/12/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/31/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/10/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/22/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 9/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/24/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/12/2021 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 10/13/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 10/21/2021 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Masonry 10/22/2021 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 11/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 11/1/2021 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 11/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/18/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/23/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/24/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/29/2021 Conditional Approval ERNESTO CORRAL
Reinforced Concrete Frame 11/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/1/2021 Conditional Approval NICK DANERI
Wood Frame 1/6/2022 Partial Approval NICK DANERI
Deputy Wood Construction 1/7/2022 Conditional Approval NICK DANERI
Wood Frame 1/25/2022 Partial Approval NICK DANERI
Wood Frame 2/7/2022 Partial Inspection NICK DANERI
Deputy Wood Construction 2/9/2022 Conditional Approval NICK DANERI
Wood Frame 2/9/2022 Partial Approval NICK DANERI
Wood Frame 2/15/2022 Partial Approval NICK DANERI
Deputy Wood Construction 2/24/2022 Conditional Approval NICK DANERI
Wood Frame 2/28/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/11/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 3/11/2022 Partial Approval NICK DANERI
Wood Frame 3/14/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/15/2022 Conditional Approval NICK DANERI
Deputy Wood Construction 3/15/2022 Conditional Approval NICK DANERI
Deputy Wood Construction 3/24/2022 Conditional Approval NICK DANERI
Wood Frame 3/24/2022 Partial Approval NICK DANERI
Deputy Wood Construction 4/8/2022 Conditional Approval NICK DANERI
Insulation 4/12/2022 Partial Inspection RAFAEL ESPINOZA
Wood Frame 4/12/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/20/2022 Partial Inspection NICK DANERI
Deputy Wood Construction 4/27/2022 Conditional Approval NICK DANERI
Drywall Nailing 5/11/2022 Corrections Issued RAFAEL ESPINOZA
Deputy Steel/Welding 5/19/2022 Partial Approval JAMES POWERS
Insulation 5/19/2022 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 5/25/2022 Conditional Approval NICK DANERI
Wood Frame 5/25/2022 Partial Approval NICK DANERI
Deputy Steel/Welding 5/31/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 5/31/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/7/2022 Conditional Approval ERNESTO CORRAL
Insulation 6/7/2022 Partial Inspection DAVID BURKHEAD
Wood Frame 6/7/2022 Partial Approval DAVID BURKHEAD
Insulation 6/28/2022 Partial Approval NICK DANERI
Insulation 6/30/2022 Partial Approval NICK DANERI
Deputy Steel/Welding 7/8/2022 Conditional Approval NICK DANERI
Insulation 7/8/2022 Partial Approval NICK DANERI
Drywall Nailing 7/15/2022 Partial Approval NICK DANERI
Insulation 7/15/2022 Partial Approval NICK DANERI
Insulation 7/18/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 7/18/2022 Partial Approval NICK DANERI
Insulation 7/26/2022 Partial Approval NICK DANERI
Drywall Nailing 8/1/2022 Partial Approval NICK DANERI
Insulation 8/1/2022 Partial Approval NICK DANERI
Drywall Nailing 8/10/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 8/10/2022 Partial Approval NICK DANERI
Drywall Nailing 8/25/2022 Partial Approval NICK DANERI
Drywall Nailing 11/1/2022 Partial Approval NICK DANERI
Footing/Foundation/Slab 12/9/2022 Partial Approval NICK DANERI
Reinforced Masonry Frame 12/20/2022 Partial Approval NICK DANERI
Reinforced Masonry Frame 12/28/2022 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 3/1/2023 Partial Approval NICK DANERI
Pre-Inspection 4/4/2023 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 5/10/2023 Conditional Approval NICK DANERI
Footing/Foundation/Slab 5/10/2023 Corrections Issued NICK DANERI
Reinforced Masonry Frame 5/17/2023 Partial Approval LARRY ARNICK
Green Building Rough 5/23/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/23/2023 Partial Approval NICK DANERI
Reinforced Masonry Frame 5/23/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 5/23/2023 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/9/2023 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 6/21/2023 Approved NICK DANERI
Light Gage Steel Frame 7/19/2023 Approved LARRY ARNICK
T-Bar Ceiling 7/19/2023 Approved LARRY ARNICK
Final 9/28/2023 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 9/28/2023 Approved NICK DANERI
Green Building Final 9/28/2023 Not Ready for Inspection NICK DANERI
Green Building Rough 9/28/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/28/2023 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved NICK DANERI
Smoke Detectors 9/28/2023 Approved NICK DANERI
Verify Sprinkler Sign Off 9/28/2023 Approved NICK DANERI
Special/Order Compliance 9/29/2023 Partial Approval NICK DANERI
Special/Order Compliance 10/2/2023 Partial Approval NICK DANERI
Final 10/27/2023 OK for TCO NICK DANERI
Green Building Final 10/27/2023 Approved NICK DANERI
Green Building Rough 10/27/2023 Approved NICK DANERI
Reinforced Concrete Frame 10/27/2023 Approved NICK DANERI
Special/Order Compliance 10/30/2023 Partial Inspection NICK DANERI