974 N MARIPOSA AVE 90029

Certificate Information: 974 N MARIPOSA AVE 90029

Application / Permit
19010-10000-01516
Plan Check / Job No.
B19LA07435
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING, BUILDING "A" (FRONT BUILDING)
Permit Issued
Issued on 3/31/2021
Issuing Office
Current Status
CofO Issued on 5/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 TEODORO DIAZ RODRIGUEZ
Corrections Issued 5/10/2019 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 5/21/2019 QUAN NGHIEM
Green Plans Picked Up 5/28/2019 APPLICANT
Plan Check Approved 12/18/2020 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/13/2021 TEODORO DIAZ RODRIGUEZ
Issued 3/31/2021 APPLICANT
Building Plans Picked Up 4/8/2021 APPLICANT
CofO in Progress 5/11/2023 FREDDIE RIVERA
Permit Finaled 5/20/2023 DEROLD HAUFF
CofO Issued 5/20/2023 DEROLD HAUFF
Permit Finaled 5/20/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/28/2019 ELENA LOPEZ
Highway dedication Cleared 5/28/2019 ELENA LOPEZ
Permit Cleared 5/28/2019 ELENA LOPEZ
Sewer availability Cleared 5/31/2019 KAREN LE
Eng Process Fee Ord 176,300 Cleared 6/3/2019 JEANETTE VONG
Hydrant and Access approval Cleared 6/3/2019 ROBERT DUFF
Trees in Parkway Cleared 6/28/2019 JOHN KIM
Green Code Cleared 7/2/2019 COLIN LOREDO
Frnt yard landscape/Water mgmt Cleared 7/16/2019 KIT AWAKUNI
Low Impact Development Cleared 10/18/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/23/2019 ELAINE LEI
Flood clearance Cleared 6/3/2020 RAYMOND LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2021 Partial Approval AMY COLIN
Underground Mechanical 12/2/2021 Partial Approval AMY COLIN
FLOOD-Elevation Certificate 1/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/18/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 1/19/2022 Approved ARTHUR SARGSYAN
Pre-Inspection 1/19/2022 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 1/19/2022 Approved ALIZAH MAYAGOITIA
FLOOD-Elevation Certificate 1/28/2022 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 1/28/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 1/28/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Corrections Issued ADAM ESCOTO
Deputy Wood Construction 2/17/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Conditional Approval AMY COLIN
ELECTRICAL-Rough 3/18/2022 Approved FREDDIE RIVERA
HVAC-Rough 3/22/2022 Approved STUART CHAPMAN
PLUMBING-Rough 3/22/2022 Corrections Issued STUART CHAPMAN
Underground Mechanical 4/6/2022 Partial Inspection FREDDIE RIVERA
Shower Pan 4/15/2022 Approved FREDDIE RIVERA
Deputy Wood Construction 4/25/2022 Approved FREDDIE RIVERA
Wood Frame 4/25/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 4/26/2022 Approved FREDDIE RIVERA
Wood Frame 4/26/2022 Conditional Approval FREDDIE RIVERA
Interior/Exterior Lathing 5/2/2022 Conditional Approval FREDDIE RIVERA
Wood Frame 6/14/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 6/17/2022 Partial Approval FREDDIE RIVERA
Insulation 6/22/2022 Approved FREDDIE RIVERA
Drywall Nailing 6/29/2022 Partial Inspection FREDDIE RIVERA
Drywall Nailing 7/6/2022 Corrections Issued FREDDIE RIVERA
Drywall Nailing 7/11/2022 Approved FREDDIE RIVERA
Deputy Other (see comments) 8/10/2022 Partial Approval FREDDIE RIVERA
Underground Mechanical 9/20/2022 Conditional Approval ALIZAH MAYAGOITIA
Masonry Wall/Backfill 10/19/2022 Corrections Issued FREDDIE RIVERA
Masonry Wall/Backfill 10/20/2022 Partial Inspection FREDDIE RIVERA
Masonry Wall/Backfill 10/31/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 1/19/2023 Corrections Issued FREDDIE RIVERA
HVAC-Final 1/19/2023 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 1/19/2023 Approved FREDDIE RIVERA
Masonry Wall/Backfill 1/24/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 2/15/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 2/15/2023 Approved FREDDIE RIVERA
Final 2/15/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 2/15/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Approved FREDDIE RIVERA
Service/Power Release 2/15/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 2/15/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 2/15/2023 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 3/21/2023 Conditional Approval FREDDIE RIVERA
Final 3/21/2023 Partial Inspection FREDDIE RIVERA
Service/Power Release 3/21/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 3/21/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 5/11/2023 Approved FREDDIE RIVERA
Final 5/11/2023 OK to Issue CofO FREDDIE RIVERA
Verify Sprinkler Sign Off 5/11/2023 Approved FREDDIE RIVERA