10206 S MAIN ST 90003

Certificate Information: 10206 S MAIN ST 90003

Application / Permit
19010-10000-01498
Plan Check / Job No.
B19LA07315
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW 2 STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 11/12/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/6/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 VU NGUYEN
Corrections Issued 5/7/2019 VU NGUYEN
Quality Review Completed 5/14/2019 MICHAEL PEREZ
Building Plans Picked Up 5/16/2019 APPLICANT
Green Plans Picked Up 5/16/2019 APPLICANT
Applicant returned to address corrections 10/22/2019 VU NGUYEN
Plan Check Approved 10/23/2019 VU NGUYEN
Issued 11/12/2019 LADBS
CofO in Progress 10/29/2020 DAVID FEILER
Permit Finaled 11/6/2020 DEROLD HAUFF
CofO Issued 11/6/2020 DEROLD HAUFF
Permit Finaled 11/6/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/20/2019 KARAN PATEL
CPC Cleared 6/21/2019 ANNA VAN
Green Code Cleared 6/25/2019 VU NGUYEN
Hydrant and Access approval Cleared 6/25/2019 GILBERT URREA
Low Impact Development Cleared 6/27/2019 ORVAL HERNANDEZ-MARCIAL
Eng Process Fee Ord 176,300 Cleared 7/9/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 7/9/2019 ADRIAN SANCHEZ
Sewer availability Cleared 7/9/2019 ADRIAN SANCHEZ
Community Plan Implem. Overlay Cleared 10/1/2019 STEVE GARCIA

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 9036 IMPERIAL HWY      DOWNEY, CA 90242
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/15/2020 Approved WILLIAM ROSE
Underground Mechanical 1/15/2020 Approved WILLIAM ROSE
Footing/Foundation/Slab 1/21/2020 Approved WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/18/2020 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/28/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 4/28/2020 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 4/28/2020 Approved EUGENE CASSIDY
Verify Rec and Parks Fee Memo 4/28/2020 Conditional Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 4/28/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 5/1/2020 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 5/1/2020 Approved EUGENE CASSIDY
Insulation 5/4/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/13/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/13/2020 Approved BRIAN CHRISTIAN
Verify Rec and Parks Fee Memo 5/13/2020 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Final 10/16/2020 Partial Approval DAVID FEILER
Final 10/16/2020 Corrections Issued DAVID FEILER
Gas Test 10/16/2020 Approved DAVID FEILER
Green Building Final 10/16/2020 Corrections Issued DAVID FEILER
HVAC-Final 10/16/2020 Partial Approval DAVID FEILER
PLUMBING-Final 10/16/2020 Partial Approval DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Approved DAVID FEILER
Service/Power Release 10/16/2020 Not Ready for Inspection DAVID FEILER
Smoke Detectors 10/16/2020 Approved DAVID FEILER
ELECTRICAL-Final 10/22/2020 Approved DAVID FEILER
Final 10/22/2020 Partial Inspection DAVID FEILER
Green Building Final 10/22/2020 Approved DAVID FEILER
HVAC-Final 10/22/2020 Approved DAVID FEILER
PLUMBING-Final 10/22/2020 Approved DAVID FEILER
Service/Power Release 10/22/2020 Partial Inspection DAVID FEILER
Final 10/29/2020 OK to Issue CofO DAVID FEILER
Service/Power Release 10/29/2020 Approved DAVID FEILER