1999 E 102ND ST 90002
Certificate Information: 1999 E 102ND ST 90002
- Application / Permit
- 19010-10000-01460
- Plan Check / Job No.
- B19LA07108
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- NEW 3-STORY MIDDLE SCHOOL WITH PARKING BASEMENT PER CPC-2018-5971-CU-F-SPR
- Permit Issued
- Issued on 3/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 4/29/2019 | APPLICANT |
| Green Plans Picked Up | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | ARMEN JIVALAGIAN |
| Corrections Issued | 5/22/2019 | ARMEN JIVALAGIAN |
| Quality Review Completed | 5/29/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 6/5/2019 | APPLICANT |
| Applicant returned to address corrections | 9/16/2019 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 9/30/2019 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/15/2019 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/28/2020 | ARMEN JIVALAGIAN |
| Plan Check Approved | 3/6/2020 | ARMEN JIVALAGIAN |
| Issued | 3/9/2020 | LADBS |
| TCO Issued (Expire Date: 02-07-2022) | 8/11/2021 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 08-24-2022) | 2/25/2022 | TERRY HERR |
| TCO Issued (Expire Date: 02-07-2023) | 8/11/2022 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 07-31-2023) | 2/1/2023 | ERNESTO CORRAL |
| CofO in Progress | 7/28/2023 | JAMES POWERS |
| CofO Issued | 7/31/2023 | ERNESTO CORRAL |
| Permit Finaled | 7/31/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/15/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/15/2019 | SOPHIE GABEL-SCHEINBAU |
| Address approval | Cleared | 8/7/2019 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 8/7/2019 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 8/7/2019 | JOHN KIM |
| Trees in Parkway | Cleared | 8/7/2019 | JOHN KIM |
| Community Plan Implem. Overlay | Cleared | 8/29/2019 | NADER ISKANDER |
| DAS Clearance | Cleared | 8/29/2019 | SHINE LIN |
| Hydrant and Access approval | Cleared | 8/29/2019 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2019 | ADRIAN CASTRO |
| Highway dedication | Cleared | 9/24/2019 | ADRIAN CASTRO |
| Permit | Cleared | 9/24/2019 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 9/25/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/25/2019 | JEANETTE VONG |
| Excavation more than 5-ft deep | Cleared | 9/30/2019 | CALOSHA APPROVED |
| Green Code | Cleared | 10/9/2019 | NEGAR NEJAD |
| Sewer availability | Cleared | 12/10/2019 | ADRIAN CASTRO |
| Fire Marshall Fire Life Safety | Cleared | 1/13/2020 | VIDAL GARCIA |
| Work Adjacent to Public Way | Cleared | 2/14/2020 | ROSA SILVA |
| Community Plan Implem. Overlay | Cleared | 2/19/2020 | PEDRO AYALA |
| Internal circulation | Cleared | 2/19/2020 | PEDRO AYALA |
| CPC | Cleared | 2/21/2020 | SARAHI ORTEGA |
| Community Plan Implem. Overlay | Cleared | 2/21/2020 | SARAHI ORTEGA |
| Frnt yard landscape/Water mgmt | Cleared | 2/21/2020 | SARAHI ORTEGA |
| Site Plan review | Cleared | 2/21/2020 | SARAHI ORTEGA |
| Building over 3-story or 36-ft | Cleared | 2/28/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Wang,, Johann D; Lic. No.: C27010 | 3375 CANTON WAY STUDIO CITY, CA 91604 |
| Contractor | E P I Construction Inc; Lic. No.: 865616-B | 12345 VENTURA BLVD SUITE H STUDIO CITY, CA 91604 |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
| Engineer | Hill,, Edward Foster; Lic. No.: GE2126 | 27865 AMBERWOOD LANE VALENCIA, CA 91354 |
| Engineer | Wang,, Guan; Lic. No.: C79702 | 135 N SAN GABRIEL BLVD SAN GABRIEL, CA 91775 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2020 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 5/11/2020 | Approved | JAMES POWERS |
| Deputy Reinf. Concrete | 5/20/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 5/21/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/22/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/26/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/27/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/28/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 5/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/1/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Masonry | 6/2/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 6/2/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 6/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/5/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/8/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/8/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/9/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 6/9/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/11/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/12/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/16/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/16/2020 | Partial Approval | JAMES POWERS |
| Pre-Inspection | 6/16/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/17/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/18/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/18/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 6/18/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 6/19/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/22/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/23/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/24/2020 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 6/25/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/30/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 7/31/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 8/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/13/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/17/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/18/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/19/2020 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 8/19/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/20/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/24/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/24/2020 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 8/24/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/25/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/26/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 8/27/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/28/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 8/31/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/1/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Reinforced Concrete Frame | 9/2/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Shotcrete | 9/3/2020 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 9/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/4/2020 | Order to Comply Issued | JAMES POWERS |
| Deputy Reinf. Concrete | 9/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Shotcrete | 9/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/8/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 9/8/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/9/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/11/2020 | Partial Approval | JAMES POWERS |
| Wood Frame | 9/11/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/2/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/16/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/16/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 10/19/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/20/2020 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 10/20/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 10/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 10/26/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 10/27/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 10/28/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 10/28/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 10/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 10/30/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 11/5/2020 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 11/9/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 11/9/2020 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 11/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 11/10/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 11/16/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/23/2020 | Partial Approval | JAMES POWERS |
| Insulation | 12/2/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 12/3/2020 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/3/2020 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 12/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 12/4/2020 | Partial Approval | JAMES POWERS |
| Insulation | 12/7/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/10/2020 | Partial Approval | JAMES POWERS |
| Wood Frame | 12/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 12/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 12/15/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 12/21/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 12/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 12/22/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/22/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 12/23/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/23/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/24/2020 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 1/7/2021 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 1/8/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/15/2021 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/19/2021 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 1/19/2021 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 1/21/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 1/22/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/3/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/4/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/5/2021 | Partial Approval | JAMES POWERS |
| Wood Frame | 2/8/2021 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 2/9/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/10/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/11/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/12/2021 | Partial Approval | JAMES POWERS |
| Wood Frame | 2/12/2021 | Partial Approval | JAMES POWERS |
| Insulation | 2/19/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 2/22/2021 | Partial Approval | JAMES POWERS |
| Insulation | 2/25/2021 | Approved | JAMES POWERS |
| Drywall Nailing | 3/3/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 3/10/2021 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 3/10/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 3/22/2021 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 3/25/2021 | Approved | JAMES POWERS |
| T-Bar Ceiling | 5/10/2021 | Partial Approval | JAMES POWERS |
| Insulation | 5/24/2021 | Not Ready for Inspection | JAMES POWERS |
| Final | 7/20/2021 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 7/20/2021 | Approved | JAMES POWERS |
| Green Building Final | 7/20/2021 | Approved | JAMES POWERS |
| Green Building Rough | 7/20/2021 | Approved | JAMES POWERS |
| Reinforced Masonry Frame | 7/20/2021 | Partial Approval | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Not Ready | JAMES POWERS |
| Smoke Detectors | 7/20/2021 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/20/2021 | Not Ready for Inspection | JAMES POWERS |
| Special/Order Compliance | 7/29/2021 | Approved | JAMES POWERS |
| Final | 8/4/2021 | OK for TCO | JAMES POWERS |
| Reinforced Masonry Frame | 8/4/2021 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/4/2021 | Approved | JAMES POWERS |
| Special/Order Compliance | 1/12/2022 | Approved | JAMES POWERS |
| Special/Order Compliance | 7/26/2022 | Approved | JAMES POWERS |
| Special/Order Compliance | 1/18/2023 | Approved | JAMES POWERS |
| Special/Order Compliance | 7/6/2023 | Approved | JAMES POWERS |
| Final | 7/24/2023 | Not Ready for Inspection | JAMES POWERS |
| Final | 7/28/2023 | OK to Issue CofO | JAMES POWERS |