3775 E MAYFAIR DR 90065

Certificate Information: 3775 E MAYFAIR DR 90065

Application / Permit
19010-10000-01459
Plan Check / Job No.
B19LA07105
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW SFD (2343 SQ FT)
Permit Issued
Issued on 8/20/2021
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 RAHEL BEYENE
Corrections Issued 5/20/2019 RAHEL BEYENE
Quality Review Completed 6/5/2019 QUAN NGHIEM
Applicant returned to address corrections 1/8/2021 RAHEL BEYENE
Applicant returned to address corrections 3/2/2021 RAHEL BEYENE
Green Plans Picked Up 3/2/2021 APPLICANT
Applicant returned to address corrections 4/19/2021 RAHEL BEYENE
Applicant returned to address corrections 5/20/2021 RAHEL BEYENE
Plan Check Approved 8/3/2021 RAHEL BEYENE
Issued 8/20/2021 APPLICANT
Building Plans Picked Up 8/23/2021 APPLICANT
CofO in Progress 2/12/2025 ALIZAH MAYAGOITIA
CofO in Progress 2/14/2025 DEROLD HAUFF
Permit Finaled 2/18/2025 DEROLD HAUFF
CofO Issued 2/18/2025 DEROLD HAUFF
Permit Finaled 2/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/1/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/3/2020 WALLIE JONG
Miscellaneous Cleared 3/11/2021 ANNA VIDAL
ZA Case Cleared 3/11/2021 ANNA VIDAL
Hydrant and Access approval Cleared 3/15/2021 JOHN CONNEALLY
Specific Plan Cleared 4/1/2021 ANNA VIDAL
ZA Case Cleared 4/1/2021 ANNA VIDAL
ZI Cleared 4/1/2021 ANNA VIDAL
ZA Case Cleared 4/6/2021 ANNA VIDAL
Private sewage disp. approval Cleared 4/14/2021 PATRICK MISCHLICH
Green Code Cleared 5/6/2021 DONALD CRICHLOW
Sewer availability Cleared 5/26/2021 WALLIE JONG
Low Impact Development Cleared 6/2/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/8/2021 THAN WIN

Contact Information

Architect Jeevanjee,, Ali Akbar; Lic. No.: C30267 453 S SPRING STREET #1126      LOS ANGELES, CA 90013
Contractor D & L Construction Group Inc; Lic. No.: 759737-B 659 PUMA CYN LANE      GLENDORA, CA 91740
Engineer Garcia,, Lionel Jesus; Lic. No.: C58475 24702 NARBONNE AVE      LOMITA, CA 90717
Engineer Polon,, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/11/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 4/12/2022 Approved OSVALDO PARAMO
Piling/Pier/Caisson 4/12/2022 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 5/5/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/17/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/27/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 6/1/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/24/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/18/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 8/2/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/10/2022 Not Ready for Inspection OSVALDO PARAMO
Piling/Pier/Caisson 8/24/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/6/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 9/9/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/13/2022 Corrections Issued OSVALDO PARAMO
Piling/Pier/Caisson 10/11/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/26/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 11/18/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 11/21/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/12/2022 Partial Inspection OSVALDO PARAMO
Footing/Foundation/Slab 12/23/2022 Partial Approval OSVALDO PARAMO
Sewer 2/16/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval OSVALDO PARAMO
Underground Mechanical 7/5/2023 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 10/26/2023 Conditional Approval JOSH MEISTER
Deputy Wood Construction 11/6/2023 Conditional Approval ALIZAH MAYAGOITIA
Deputy Wood Construction 11/14/2023 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Partial Approval OSVALDO PARAMO
HVAC-Rough 12/18/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 12/18/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/21/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 12/29/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Deputy Wood Construction 1/10/2024 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 2/2/2024 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 2/2/2024 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 2/2/2024 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/9/2024 Approved OSVALDO PARAMO
ELECTRICAL-Rough 2/9/2024 Approved OSVALDO PARAMO
Green Building Rough 2/9/2024 Approved OSVALDO PARAMO
Insulation 3/6/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/6/2024 Partial Approval OSVALDO PARAMO
Drywall Nailing 3/19/2024 Partial Approval OSVALDO PARAMO
Shower Pan 3/19/2024 Approved OSVALDO PARAMO
Interior/Exterior Lathing 4/24/2024 Approved JOSEPH MCGARRY
Drywall Nailing 6/26/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 1/17/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 1/17/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 1/22/2025 Corrections Issued OSVALDO PARAMO
Gas Test 1/22/2025 Approved OSVALDO PARAMO
HVAC-Final 1/22/2025 Corrections Issued OSVALDO PARAMO
Service/Power Release 1/22/2025 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 1/22/2025 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 1/30/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 1/30/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 1/30/2025 Approved ALIZAH MAYAGOITIA
Final 2/5/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/5/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 2/5/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 2/5/2025 Approved ALIZAH MAYAGOITIA
Final 2/7/2025 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 2/7/2025 Approved ALIZAH MAYAGOITIA
Final 2/12/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Service/Power Release 2/12/2025 Approved ALIZAH MAYAGOITIA