125 1/2 W 73RD ST 90003

Certificate Information: 125 1/2 W 73RD ST 90003

Application / Permit
19010-10000-01399
Plan Check / Job No.
B19LA06822
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 7/9/2019
Issuing Office
Valley
Current Status
Issued on 7/9/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/4/2019 APPLICANT
Green Plans Picked Up 5/8/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 PRANITA SHAH
Corrections Issued 5/24/2019 PRANITA SHAH
Quality Review Completed 6/11/2019 TU HUA
Building Plans Picked Up 6/11/2019 APPLICANT
Plan Check Approved 6/27/2019 PRANITA SHAH
Issued 7/9/2019 LADBS

Permit Application Clearance Information

Address approval Cleared 6/18/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/25/2019 ADRIAN SANCHEZ
Green Code Cleared 6/25/2019 PRANITA SHAH
Hydrant and Access approval Cleared 6/25/2019 ROBERT DUFF
Low Impact Development Cleared 6/25/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 6/25/2019 ADRIAN SANCHEZ
Sewer availability Cleared 6/25/2019 ADRIAN SANCHEZ

Contact Information

Contractor Sky Construction; Lic. No.: 747838-B 11685 LAURELWOOD DRIVE      STUDIO CITY, CA 91604
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2019 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/12/2019 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 7/12/2019 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 7/12/2019 Approved PAUL BECKER
Footing/Foundation/Slab 8/28/2019 Corrections Issued EUGENE CASSIDY
Pre-Inspection 8/30/2019 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 9/4/2019 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/6/2019 Partial Approval EUGENE CASSIDY
Insulation 9/6/2019 Approved EUGENE CASSIDY
PLUMBING-Rough 9/6/2019 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/18/2019 Approved EUGENE CASSIDY
PLUMBING-Rough 9/18/2019 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/16/2019 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 10/16/2019 Corrections Issued EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 10/16/2019 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 10/16/2019 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/5/2019 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/5/2019 Corrections Issued EUGENE CASSIDY
Green Building Rough 11/5/2019 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 11/5/2019 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 11/5/2019 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 3/3/2020 Not Ready for Inspection EUGENE CASSIDY
Insulation 3/3/2020 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 3/3/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 3/19/2020 Corrections Issued EUGENE CASSIDY
HVAC-Rough 3/19/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/19/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/24/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 3/24/2020 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 3/24/2020 Partial Approval SABAS ALONSO
Verify Sprinkler Sign Off 3/24/2020 Approved EUGENE CASSIDY
Green Building Rough 4/9/2020 Approved ROBERT VORHIS
Insulation 4/9/2020 Approved ROBERT VORHIS
Rough-Elec/Plmb/HVAC 4/9/2020 Approved ROBERT VORHIS
Drywall Nailing 4/16/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 7/13/2020 Approved JOSEPH MCGARRY
Final 7/13/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 7/13/2020 Approved JOSEPH MCGARRY
Green Building Final 7/13/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 7/13/2020 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 7/13/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/17/2020 SGSOV Not Ready FREDDIE RIVERA
Final 7/22/2020 Corrections Issued JOSEPH MCGARRY
Gas Test 7/22/2020 Partial Approval JOSEPH MCGARRY
Green Building Final 7/22/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 7/22/2020 Not Required JOSEPH MCGARRY
Sewer 7/22/2020 Approved JOSEPH MCGARRY
Underground Mechanical 7/22/2020 Approved JOSEPH MCGARRY
Final 7/27/2020 Corrections Issued JOSEPH MCGARRY
Gas Test 7/27/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/27/2020 SGSOV Approved JOSEPH MCGARRY
ELECTRICAL-Final 8/3/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 8/3/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 8/3/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 8/25/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 8/31/2020 Corrections Issued COREY HUPP
ELECTRICAL-Final 9/30/2020 Approved FREDDIE RIVERA
Final 9/30/2020 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 9/30/2020 Approved FREDDIE RIVERA
PLUMBING-Final 9/30/2020 Approved FREDDIE RIVERA
Final 1/15/2021 Conditional Approval EUGENE CASSIDY
Service/Power Release 1/15/2021 Conditional Approval EUGENE CASSIDY
Final 3/22/2021 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 3/22/2021 Not Ready for Inspection FREDDIE RIVERA