Pre-Inspection
|
1/8/2020
|
Partial Inspection
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
1/27/2020
|
Partial Inspection
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
2/24/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
3/2/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
Footing/Foundation/Slab
|
4/15/2020
|
Partial Approval
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
4/16/2020
|
Partial Approval
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
4/27/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
5/4/2020
|
No Access for Inspection
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
5/5/2020
|
Partial Approval
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
5/11/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
Green Building Rough
|
5/11/2020
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
Reinforced Masonry Frame
|
5/11/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
Verify Sprinkler Sign Off
|
5/11/2020
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
Footing/Foundation/Slab
|
5/18/2020
|
Partial Approval
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
5/19/2020
|
Partial Approval
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
5/20/2020
|
Partial Approval
|
DANIEL COLLINS
|
Green Building Rough
|
6/9/2020
|
Approved
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
6/9/2020
|
Partial Approval
|
DANIEL COLLINS
|
Verify Sprinkler Sign Off
|
6/9/2020
|
Not Ready for Inspection
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
6/11/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
6/12/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
6/15/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
6/15/2020
|
Partial Approval
|
DANIEL COLLINS
|
Verify Sprinkler Sign Off
|
6/15/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
6/16/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
6/17/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
6/19/2020
|
Partial Approval
|
DANIEL COLLINS
|
Verify Sprinkler Sign Off
|
6/19/2020
|
Approved
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
6/22/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
6/24/2020
|
Partial Approval
|
NICK DANERI
|
Deputy Reinf. Masonry
|
6/25/2020
|
Conditional Approval
|
NICK DANERI
|
Reinforced Concrete Frame
|
6/25/2020
|
Partial Approval
|
NICK DANERI
|
Deputy Reinf. Masonry
|
6/26/2020
|
Conditional Approval
|
RONALD PACHECO
|
Deputy Reinf. Masonry
|
6/29/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
6/29/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
6/30/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/1/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/2/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
7/7/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
7/7/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
7/7/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/8/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
7/8/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
7/8/2020
|
Not Ready for Inspection
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/9/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
7/9/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Masonry Wall/Backfill
|
7/9/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/10/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
7/10/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
7/10/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/13/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
7/13/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
7/14/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/15/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
7/16/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/17/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
7/17/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/20/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/21/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
7/22/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
7/22/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/23/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/24/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
7/24/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
7/27/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
7/28/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Drilled-In Anchors
|
7/29/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
7/29/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Steel/Welding
|
7/29/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Drilled-In Anchors
|
7/30/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
7/30/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Steel/Welding
|
7/30/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Drilled-In Anchors
|
7/31/2020
|
Conditional Approval
|
TIMOTHY BUXTON
|
Deputy Reinf. Masonry
|
7/31/2020
|
Conditional Approval
|
TIMOTHY BUXTON
|
Deputy Steel/Welding
|
7/31/2020
|
Conditional Approval
|
TIMOTHY BUXTON
|
Reinforced Masonry Frame
|
7/31/2020
|
Partial Approval
|
TIMOTHY BUXTON
|
Deputy Drilled-In Anchors
|
8/3/2020
|
Conditional Approval
|
TIMOTHY BUXTON
|
Deputy Reinf. Masonry
|
8/3/2020
|
Conditional Approval
|
TIMOTHY BUXTON
|
Deputy Steel/Welding
|
8/3/2020
|
Conditional Approval
|
TIMOTHY BUXTON
|
Deputy Drilled-In Anchors
|
8/4/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
8/4/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
8/4/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
8/4/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
8/7/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
8/14/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Drilled-In Anchors
|
8/18/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
8/18/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Drilled-In Anchors
|
8/19/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
8/19/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Drilled-In Anchors
|
8/20/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
8/20/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Drilled-In Anchors
|
8/21/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
8/21/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Drilled-In Anchors
|
8/24/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
8/24/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Drywall Nailing
|
8/28/2020
|
Partial Approval
|
DANIEL COLLINS
|
Light Gage Steel Frame
|
8/28/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
9/1/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
9/2/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
9/16/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
9/16/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
9/17/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Steel/Welding
|
9/17/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
9/18/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Steel/Welding
|
9/18/2020
|
Conditional Approval
|
KATY RAMIREZ
|
Deputy Reinf. Masonry
|
9/21/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Steel/Welding
|
9/21/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
9/22/2020
|
Conditional Approval
|
NICK DANERI
|
Deputy Steel/Welding
|
9/22/2020
|
Conditional Approval
|
NICK DANERI
|
Light Gage Steel Frame
|
9/29/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
9/29/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
9/30/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
10/8/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
10/9/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
10/19/2020
|
Partial Approval
|
LANNY MERRICK
|
Deputy Reinf. Masonry
|
10/20/2020
|
Conditional Approval
|
LANNY MERRICK
|
Deputy Reinf. Masonry
|
10/21/2020
|
Conditional Approval
|
LANNY MERRICK
|
Deputy Reinf. Masonry
|
10/22/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Drywall Nailing
|
10/22/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
10/22/2020
|
Partial Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
10/23/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
10/26/2020
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
10/27/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
10/29/2020
|
Partial Approval
|
LANNY MERRICK
|
Reinforced Masonry Frame
|
11/2/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
11/10/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
11/10/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
11/13/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
11/19/2020
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
11/23/2020
|
Partial Approval
|
DANIEL COLLINS
|
Light Gage Steel Frame
|
1/21/2021
|
Partial Approval
|
DANIEL COLLINS
|
Drywall Nailing
|
2/16/2021
|
Partial Approval
|
DANIEL COLLINS
|
Light Gage Steel Frame
|
2/16/2021
|
Partial Approval
|
DANIEL COLLINS
|
Insulation
|
2/18/2021
|
Partial Approval
|
DANIEL COLLINS
|
Floor/Roof Diaphrgm/Shear Wall
|
2/22/2021
|
Approved
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
2/23/2021
|
Partial Approval
|
DANIEL COLLINS
|
Drywall Nailing
|
4/8/2021
|
Approved
|
DANIEL COLLINS
|
Light Gage Steel Frame
|
4/8/2021
|
Approved
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
6/1/2021
|
Partial Inspection
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
6/1/2021
|
Partial Inspection
|
DANIEL COLLINS
|
Pre-Inspection
|
6/3/2021
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
6/3/2021
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
6/24/2021
|
Partial Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
7/15/2021
|
Approved
|
DANIEL COLLINS
|
Pre-Inspection
|
9/10/2021
|
Partial Inspection
|
DANIEL COLLINS
|
Footing/Foundation/Slab
|
10/6/2021
|
Approved
|
DANIEL COLLINS
|
T-Bar Ceiling
|
10/6/2021
|
Approved
|
DANIEL COLLINS
|
Reinforced Masonry Frame
|
10/13/2021
|
Approved
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
10/20/2021
|
Approved
|
DANIEL COLLINS
|
Deputy Other (see comments)
|
10/22/2021
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Concrete
|
10/22/2021
|
Conditional Approval
|
DANIEL COLLINS
|
Reinforced Concrete Frame
|
10/22/2021
|
Approved
|
DANIEL COLLINS
|
Deputy Other (see comments)
|
10/26/2021
|
Conditional Approval
|
DANIEL COLLINS
|
Deputy Reinf. Masonry
|
10/26/2021
|
Conditional Approval
|
DANIEL COLLINS
|
Final
|
11/16/2021
|
Conditional Approval
|
DANIEL COLLINS
|
Green Building Final
|
11/16/2021
|
Approved
|
DANIEL COLLINS
|
SGSOV-Seismic Gas S/O Valve
|
11/16/2021
|
SGSOV Approved
|
DANIEL COLLINS
|
Smoke Detectors
|
11/16/2021
|
Approved
|
DANIEL COLLINS
|
Structural Steel Frame
|
11/16/2021
|
Approved
|
DANIEL COLLINS
|
Final
|
11/17/2021
|
Partial Inspection
|
DANIEL COLLINS
|
Final
|
11/18/2021
|
Partial Inspection
|
DANIEL COLLINS
|
Final
|
11/23/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|