723-725 E 80TH ST 90001

Certificate Information: 723-725 E 80TH ST 90001

Application / Permit
19010-10000-01278
Plan Check / Job No.
B19LA06289
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 2/19/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/13/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2019 APPLICANT
Green Plans Picked Up 4/10/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 GEORGE ALVAREZ
Corrections Issued 4/17/2019 GEORGE ALVAREZ
Quality Review Completed 4/23/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 4/25/2019 APPLICANT
Plan Check Approved 1/23/2020 GEORGE ALVAREZ
Issued 2/19/2020 LADBS
CofO in Progress 9/17/2020 DAVID FEILER
Permit Finaled 11/13/2020 DEROLD HAUFF
CofO Issued 11/13/2020 DEROLD HAUFF
Permit Finaled 11/13/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/1/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 5/1/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 5/1/2019 ROBERT DUFF
Permit Cleared 5/1/2019 ADRIAN SANCHEZ
Sewer availability Cleared 5/1/2019 ADRIAN SANCHEZ
Community Plan Implem. Overlay Cleared 1/6/2020 ANNA VIDAL
Trees in Parkway Cleared 1/13/2020 ADRIAN SANCHEZ
Low Impact Development Cleared 1/14/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/14/2020 EMIL KYUPELYAN
Green Code Cleared 1/17/2020 COLIN LOREDO
Green Code Cleared 1/17/2020 GEORGE ALVAREZ

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/26/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/17/2020 Partial Approval BRIAN CHRISTIAN
PLUMBING-Rough 4/17/2020 Partial Approval BRIAN CHRISTIAN
Insulation 4/21/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 6/8/2020 Conditional Approval BRIAN CHRISTIAN
HVAC-Rough 6/22/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/22/2020 Approved ALEJANDRO DE ARTOLA
Sewer 6/22/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/26/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 6/26/2020 Approved EUGENE CASSIDY
Green Building Rough 6/26/2020 Approved EUGENE CASSIDY
HVAC-Rough 6/26/2020 Conditional Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 6/26/2020 Approved EUGENE CASSIDY
HVAC-Rough 7/2/2020 Approved OSVALDO PARAMO
Insulation 7/2/2020 Approved OSVALDO PARAMO
Drywall Nailing 7/13/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/13/2020 Partial Approval SABAS ALONSO
ELECTRICAL-Final 9/11/2020 Corrections Issued DAVID FEILER
Final 9/11/2020 Not Ready for Inspection DAVID FEILER
Gas Test 9/11/2020 Approved DAVID FEILER
Green Building Final 9/11/2020 Approved DAVID FEILER
HVAC-Final 9/11/2020 Corrections Issued DAVID FEILER
PLUMBING-Final 9/11/2020 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/11/2020 SGSOV Approved DAVID FEILER
Service/Power Release 9/11/2020 Not Ready for Inspection DAVID FEILER
Smoke Detectors 9/11/2020 Approved DAVID FEILER
ELECTRICAL-Final 9/16/2020 Approved DAVID FEILER
Final 9/16/2020 OK to Issue CofO DAVID FEILER
HVAC-Final 9/16/2020 Approved DAVID FEILER
Pre-Inspection 9/16/2020 Approved DAVID FEILER
Service/Power Release 9/16/2020 Approved DAVID FEILER