16008 W CANTLAY ST 91406

Certificate Information: 16008 W CANTLAY ST 91406

Application / Permit
19010-10000-01249
Plan Check / Job No.
B19LA06160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ROOF TOP DECK. (BUILDING A).
Permit Issued
Issued on 1/14/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 EMMANUEL MARTINEZ
Corrections Issued 4/15/2019 EMMANUEL MARTINEZ
Quality Review Completed 4/22/2019 JOSE RODRIGUEZ
Building Plans Picked Up 4/23/2019 APPLICANT
Applicant returned to address corrections 8/6/2019 EMMANUEL MARTINEZ
Applicant returned to address corrections 11/20/2019 EMMANUEL MARTINEZ
Applicant returned to address corrections 1/27/2020 EMMANUEL MARTINEZ
Applicant returned to address corrections 3/11/2020 KESETE HAREGOT
Green Plans Picked Up 8/14/2020 APPLICANT
Plan Check Approved 9/10/2020 KESETE HAREGOT
Issued 1/14/2021 APPLICANT
CofO in Progress 2/28/2023 RAUL OLAGI
CofO Issued 3/15/2023 MICHAEL SMITH
Permit Finaled 3/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/29/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/29/2019 ELENA LOPEZ
Sewer availability Cleared 4/29/2019 ELENA LOPEZ
Green Code Cleared 5/8/2019 KHEDER ALRAZAA
Trees in Parkway Cleared 5/9/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 5/24/2019 JOHN CONNEALLY
Frnt yard landscape/Water mgmt Cleared 6/17/2019 DIANA JIMENEZ
Permit Cleared 11/14/2019 THOMAS LANG
Low Impact Development Cleared 1/17/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/23/2020 ERIK BEASLEY

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790
Engineer Ventura,, Wilfredo Santo Doming; Lic. No.: C66532 27315 JEFFERSON AVE STE J-229      TEMECULA, CA 92590
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2021 No Access for Inspection ARTHUR SARGSYAN
Pre-Inspection 3/22/2021 Not Ready for Inspection ARTHUR SARGSYAN
Underground Mechanical 9/15/2021 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 10/4/2021 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 10/6/2021 Approved JACK KARGODORIAN
Deputy Reinf. Concrete 10/8/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Corrections Issued RAUL OLAGI
Deputy Wood Construction 11/17/2021 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Corrections Issued RAUL OLAGI
HVAC-Rough 1/5/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 1/28/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 1/28/2022 Approved RAUL OLAGI
PLUMBING-Rough 1/28/2022 Approved RAUL OLAGI
Underground Mechanical 2/8/2022 Not Ready for Inspection RAUL OLAGI
Sewer 2/14/2022 Approved RAUL OLAGI
Underground Mechanical 2/14/2022 Corrections Issued RAUL OLAGI
Underground Mechanical 2/18/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 3/25/2022 Approved RAUL OLAGI
Shower Pan 5/19/2022 Corrections Issued RAUL OLAGI
Shower Pan 5/31/2022 Approved DEANDRE HOFFMAN
Deputy Wood Construction 6/7/2022 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval ALAN MORELOS
Interior/Exterior Lathing 6/24/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 6/29/2022 Approved ALAN MORELOS
Green Building Rough 6/29/2022 Approved ALAN MORELOS
Verify Sprinkler Sign Off 6/29/2022 Approved ALAN MORELOS
Insulation 7/7/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 7/15/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 7/21/2022 Approved ALAN MORELOS
HVAC-Final 11/16/2022 Approved RAUL OLAGI
Gas Test 12/2/2022 Approved RAUL OLAGI
PLUMBING-Final 12/2/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Final 12/14/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Final 12/14/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Final 12/21/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Approved RAUL OLAGI
ELECTRICAL-Final 1/19/2023 Corrections Issued RAUL OLAGI
Final 1/31/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 1/31/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Final 1/31/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Service/Power Release 1/31/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 1/31/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/13/2023 Approved RAUL OLAGI
Final 2/13/2023 Corrections Issued RAUL OLAGI
Green Building Final 2/13/2023 Approved RAUL OLAGI
Final 2/28/2023 OK to Issue CofO RAUL OLAGI
Service/Power Release 2/28/2023 Approved RAUL OLAGI