17081 W DEVONSHIRE ST 91325

Certificate Information: 17081 W DEVONSHIRE ST 91325

Application / Permit
19010-10000-01180
Plan Check / Job No.
B19LA05761
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
1 STORY TYPE IIA LOCKER ROOM BLDG
Permit Issued
Issued on 11/4/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2019 APPLICANT
Green Plans Picked Up 4/3/2019 APPLICANT
Disabled Access Plans Picked Up 4/9/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 HERNAN ARREOLA
Corrections Issued 5/2/2019 HERNAN ARREOLA
Quality Review Completed 5/14/2019 MINYE PAK
Building Plans Picked Up 5/15/2019 APPLICANT
Applicant returned to address corrections 5/31/2019 HERNAN ARREOLA
Applicant returned to address corrections 8/19/2019 HERNAN ARREOLA
Plan Check Approved 9/24/2019 HERNAN ARREOLA
Issued 11/4/2019 LADBS
TCO Issued (Expire Date: 03-16-2022) 9/17/2021 RICKEY JACKSON
CofO in Progress 3/23/2022 DANNY RODRIGUEZ
Permit Finaled 5/11/2022 RICKEY JACKSON
CofO Issued 5/11/2022 RICKEY JACKSON
Permit Finaled 5/11/2022 RICKEY JACKSON

Permit Application Clearance Information

"Q" conditions Cleared 5/21/2019 ANNA VAN
Driveway location Cleared 5/21/2019 BRANDON WILSON
Miscellaneous Cleared 5/21/2019 ANNA VAN
ZA Case Cleared 5/21/2019 ANNA VAN
ZA Case Cleared 5/21/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 6/3/2019 CELINA MORENO
Hydrant and Access approval Cleared 6/3/2019 ROBERT DUFF
Sewer availability Cleared 6/3/2019 CELINA MORENO
Trees in Parkway Cleared 6/26/2019 JOHN KIM
Green Code Cleared 7/24/2019 HERNAN ARREOLA
DAS Clearance Cleared 7/25/2019 HERNAN ARREOLA
DAS Clearance Cleared 7/25/2019 WAI LAU
Miscellaneous Cleared 8/1/2019 NOAH MCCOY
Site Plan review Cleared 8/1/2019 NOAH MCCOY
Highway dedication Cleared 8/21/2019 LEE GUILBEAUX
Low Impact Development Cleared 9/11/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 9/11/2019 ERIK BEASLEY
Fire Marshall Fire Life Safety Cleared 9/18/2019 VIDAL GARCIA
Building over 3-story or 36-ft Cleared 9/24/2019 CALOSHA APPROVED

Contact Information

Architect Di, Camillo, James P; Lic. No.: C15937 8163 ROCHESTER AVE. STE. 100      RANCHO CUCAMONGA, CA 91730
Contractor C W Driver Llc; Lic. No.: 1009002-B 468 NORTH ROSEMEAD BLVD      PASADENA, CA 91107
Engineer Byrd,, Richard Martin; Lic. No.: S3350 19716 GOLDEN BOUGH DR      COVINA, CA 91724

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/22/2020 Conditional Approval ROBERT COLE
Pre-Inspection 6/12/2020 Not Ready for Inspection ROBERT COLE
Light Gage Steel Frame 6/15/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 6/23/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 6/30/2020 Partial Inspection ROBERT COLE
Footing/Foundation/Slab 7/9/2020 Partial Approval ROBERT COLE
Reinforced Masonry Frame 7/9/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 7/22/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 7/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/27/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/27/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/30/2020 Partial Approval HAMID PISHEHVAR
Reinforced Masonry Frame 7/30/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 7/30/2020 Not Ready for Inspection HAMID PISHEHVAR
Green Building Rough 8/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 8/5/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/5/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 8/11/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Masonry Frame 8/11/2020 Partial Approval HAMID PISHEHVAR
Verify Sprinkler Sign Off 8/11/2020 Not Ready for Inspection HAMID PISHEHVAR
Footing/Foundation/Slab 8/13/2020 Approved HAMID PISHEHVAR
Green Building Rough 8/17/2020 Not Ready for Inspection ROBERT DAVIS
Reinforced Masonry Frame 8/17/2020 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 8/17/2020 Not Ready for Inspection ROBERT DAVIS
Masonry Wall/Backfill 8/18/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 10/6/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/7/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/8/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/9/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/13/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 10/26/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/27/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/28/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/29/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 10/30/2020 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 11/2/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/4/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/5/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/6/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/9/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/12/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/13/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/16/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/17/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/19/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/20/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/23/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/24/2020 Approved JEFF BYTHEWAY
Deputy Steel/Welding 11/25/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/2/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/3/2020 Approved HAMID PISHEHVAR
Deputy Drilled-In Anchors 12/4/2020 Approved HAMID PISHEHVAR
Drywall Nailing 1/12/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/12/2021 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/15/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/20/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/20/2021 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 2/3/2021 Partial Approval DANNY RODRIGUEZ
Insulation 2/10/2021 Partial Approval DANNY RODRIGUEZ
Insulation 2/17/2021 Approved DANNY RODRIGUEZ
Drywall Nailing 2/22/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 2/22/2021 Approved DANNY RODRIGUEZ
Drywall Nailing 2/25/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/3/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/8/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/11/2021 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 4/8/2021 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 4/12/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/16/2021 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 5/6/2021 Not Ready for Inspection HAMID PISHEHVAR
Light Gage Steel Frame 5/7/2021 Approved HAMID PISHEHVAR
Drywall Nailing 5/11/2021 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 5/13/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/17/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/27/2021 Corrections Issued DANNY RODRIGUEZ
Green Building Final 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/27/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/2/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 9/3/2021 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 2/16/2022 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 3/23/2022 Approved DANNY RODRIGUEZ
Final 3/23/2022 OK to Issue CofO DANNY RODRIGUEZ
Green Building Final 3/23/2022 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 3/23/2022 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 3/23/2022 Approved DANNY RODRIGUEZ
Structural Steel Frame 3/23/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/23/2022 Approved DANNY RODRIGUEZ