3341 W ATWATER AVE 90039
Certificate Information: 3341 W ATWATER AVE 90039
- Application / Permit
- 19010-10000-01173
- Plan Check / Job No.
- B19LA05743
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW ADU AT REAR OF (E) SFD PER AB494 AND SB229 per WFPP
- Permit Issued
- Issued on 8/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | MONICA RAMIREZ |
| Corrections Issued | 4/15/2019 | MONICA RAMIREZ |
| Green Plans Picked Up | 4/30/2019 | APPLICANT |
| Quality Review Completed | 5/1/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 5/2/2019 | APPLICANT |
| Plan Check Approved | 8/21/2019 | MONICA RAMIREZ |
| Issued | 8/23/2019 | LADBS |
| CofO in Progress | 8/10/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/14/2020 | DEROLD HAUFF |
| CofO Issued | 8/14/2020 | DEROLD HAUFF |
| Permit Finaled | 8/14/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2019 | ELAINE LEI |
| Sewer availability | Cleared | 5/21/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 6/25/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 7/17/2019 | KHEDER ALRAZAA |
| Roof/Waste drainage to street | Cleared | 7/23/2019 | ELAINE LEI |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3684 E PERCY ST LOS ANGELES, CA 90023 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/15/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/22/2019 | Corrections Issued | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 10/31/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/21/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/21/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/21/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/27/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/27/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/6/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 2/11/2020 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 2/18/2020 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 2/18/2020 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 7/21/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 7/21/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Final | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 7/29/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 7/29/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 8/10/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |