319 N WESTLAKE AVE 90026

Certificate Information: 319 N WESTLAKE AVE 90026

Application / Permit
19010-10000-01166
Plan Check / Job No.
B19LA05715
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW MODULAR, FACTORY-BUILT APARTMENT BUILDING. 4-STORIES OVER 1-LEVEL SUBTERRANEAN GARAGE 28% AFFORDABLE UNITS. See Comments.
Permit Issued
Issued on 8/14/2020
Issuing Office
Current Status
Issued on 8/14/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/20/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 EUGENE BARBEAU
Corrections Issued 4/2/2019 EUGENE BARBEAU
Quality Review Completed 4/2/2019 SIAVOSH POURSABAHIAN
Building Plans Picked Up 4/3/2019 APPLICANT
Plan Check Approved 4/29/2020 EUGENE BARBEAU
Issued 8/14/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/3/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/3/2019 ELAINE LEI
Permit Cleared 4/3/2019 ELAINE LEI
Sewer availability Cleared 4/15/2019 KAREN LE
Density Bonus 12.22.A.31 Cleared 5/15/2019 NICHOLAS KAWAZOE
Trees in Parkway Cleared 7/8/2019 HECTOR BANUELOS
CPC Cleared 7/18/2019 ANNA VAN
Frnt yard landscape/Water mgmt Cleared 7/18/2019 ANNA VAN
Miscellaneous Cleared 7/18/2019 ANNA VAN
Miscellaneous Cleared 7/18/2019 ANNA VAN
Opn space landscape/Water mgmt Cleared 7/18/2019 ANNA VAN
Low Impact Development Cleared 7/25/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/25/2019 ERIK BEASLEY
Building over 3-story or 36-ft Cleared 7/29/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/29/2019 CALOSHA APPROVED
Hydrant and Access approval Cleared 2/10/2020 JEREMY CARTER
Fire Marshall Fire Life Safety Cleared 2/24/2020 WILLIAM JOHNS
Work Adjacent to Public Way Cleared 4/24/2020 ROSA SILVA

Contact Information

Architect Azimi,, Babak; Lic. No.: C31944 4940 CALVIN AVENUE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Lothrop,, Shawn Duane; Lic. No.: S5627 40810 COUNTY CENTER DR STE 110      TEMECULA, CA 92563
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2020 Partial Approval RAFAEL ESPINOZA
Deputy Methane Barrier 11/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 11/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 11/19/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/23/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/24/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 11/24/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 11/24/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 11/24/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Subgrade 11/24/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Shotcrete 11/30/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 12/2/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/3/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Shotcrete 12/4/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 12/9/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/9/2020 Partial Approval RAFAEL ESPINOZA
Deputy Methane Barrier 12/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 12/16/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 12/18/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 12/18/2020 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 12/22/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/22/2020 Partial Approval NICK DANERI
Deputy Shotcrete 12/23/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/23/2020 Partial Approval NICK DANERI
Deputy Methane Barrier 1/20/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 1/21/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/22/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 1/22/2021 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 2/3/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/8/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/5/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 3/5/2021 Partial Inspection RAFAEL ESPINOZA
METHANE-Subgrade 3/5/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 4/5/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 4/6/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/9/2021 Conditional Approval NICK DANERI
Deputy Wood Construction 4/9/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 4/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Final 4/9/2021 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 4/9/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 4/9/2021 Approved RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/12/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/14/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/1/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 6/2/2021 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 6/4/2021 Approved RAFAEL ESPINOZA
METHANE-Barrier 6/4/2021 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/7/2021 Conditional Approval RAFAEL ESPINOZA
Pre-Inspection 8/30/2021 Partial Inspection RAFAEL ESPINOZA
Wall Anchors 5/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 5/24/2022 Approved RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 7/1/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 7/15/2022 Conditional Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 8/26/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/18/2022 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/18/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval NICK DANERI
Deputy Wood Construction 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/21/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Partial Approval NICK DANERI
Drywall Nailing 2/14/2023 Partial Approval GREGORY POMISH
Pre-Inspection 2/14/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 2/21/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/21/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 2/22/2023 Not Ready for Inspection TED RIES
Drywall Nailing 3/1/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/1/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/8/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 3/16/2023 Partial Approval NICK DANERI
Insulation 3/29/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 4/10/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval JAMES POWERS
Drywall Nailing 4/17/2023 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 4/17/2023 Partial Inspection RAFAEL ESPINOZA
Insulation 5/16/2023 Partial Approval EDWIN GREGORYONA
Insulation 5/24/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 5/30/2023 Partial Approval GREGORY POMISH
Insulation 5/30/2023 Partial Approval GREGORY POMISH
Drywall Nailing 6/27/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/21/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/31/2023 Partial Approval NICK DANERI
Light Gage Steel Frame 9/13/2023 Partial Approval NICK DANERI
Pre-Inspection 2/9/2024 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 7/10/2024 Partial Approval NICK DANERI
Special/Order Compliance 6/17/2026 Corrections Issued JOEY BUCHANAN