4723 S NORMANDIE AVE 90037

Certificate Information: 4723 S NORMANDIE AVE 90037

Application / Permit
19010-10000-01161
Plan Check / Job No.
B19LA05689
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 5 story 43 unit apartment 100% affordable housing per CPC 2019-2592-DB-CU-SIP
Permit Issued
Issued on 10/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 HERNAN ARREOLA
Corrections Issued 4/15/2019 HERNAN ARREOLA
Quality Review Completed 4/15/2019 BILL STUTSMAN
Applicant returned to address corrections 4/10/2020 HERNAN ARREOLA
Applicant returned to address corrections 4/16/2020 HERNAN ARREOLA
Applicant returned to address corrections 5/7/2020 HERNAN ARREOLA
Plan Check Approved 10/21/2020 HERNAN ARREOLA
Issued 10/22/2020 APPLICANT
Permit Closed-Status Void 8/31/2021 JAMES POWERS
Re-Activate Permit 9/2/2021 JAMES POWERS
Building Plans Picked Up 11/9/2021 APPLICANT
TCO Issued (Expire Date: 01-30-2023) 8/3/2022 ERNESTO CORRAL
CofO in Progress 1/26/2023 JAMES POWERS
Permit Finaled 1/26/2023 ERNESTO CORRAL
CofO Issued 1/26/2023 ERNESTO CORRAL
Permit Finaled 1/26/2023 ERNESTO CORRAL

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/24/2020 GEORGE SUCHAND
Low Impact Development Cleared 4/17/2020 AMMAR ELTAWIL
Address approval Cleared 5/4/2020 RENZ SORIANO
Construction near power lines Cleared 5/5/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/5/2020 RENZ SORIANO
Sewer availability Cleared 5/11/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 5/12/2020 RENZ SORIANO
Highway dedication Cleared 5/14/2020 RENZ SORIANO
Green Code Cleared 6/5/2020 HERNAN ARREOLA
Community Plan Implem. Overlay Cleared 6/9/2020 PETE EYRE
Trees in Parkway Cleared 7/14/2020 JOHN KIM
Building over 3-story or 36-ft Cleared 7/30/2020 CALOSHA APPROVED
Density Bonus 12.22.A.31 Cleared 8/12/2020 KENNETH LE
Community Plan Implem. Overlay Cleared 8/24/2020 JOHN KIM
Community Plan Implem. Overlay Cleared 9/3/2020 SAM NAVID
Work Adjacent to Public Way Cleared 9/4/2020 CHIU TAM
Fire Marshall Fire Life Safety Cleared 9/15/2020 MENOA AGHAJANI
Public Housing Cleared 9/30/2020 LUIS ALVAREZ
Public Housing Cleared 9/30/2020 LUIS ALVAREZ
CPC Cleared 10/9/2020 VINCENT QUITORIANO
Community Plan Implem. Overlay Cleared 10/9/2020 VINCENT QUITORIANO
Miscellaneous Cleared 10/9/2020 VINCENT QUITORIANO
Opn space landscape/Water mgmt Cleared 10/9/2020 VINCENT QUITORIANO
Project located in CRA area Cleared 10/9/2020 VINCENT QUITORIANO
ZA Case Cleared 10/9/2020 VINCENT QUITORIANO
DAS Clearance Cleared 10/13/2020 HERNAN ARREOLA

Contact Information

Architect Aliano,, Giuseppe; Lic. No.: C26571 3408 BUENA VISTA AVE      GLENDALE, CA 91208
Contractor Olson R D Construction Inc; Lic. No.: 953845-B 400 SPECTRUM CENTER DR   STE 1200    IRVINE, CA 92618
Engineer Yeh,, Ming-Yang; Lic. No.: S2587 131 WEST GREEN ST      PASADENA, CA 911059886

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/24/2020 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/25/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/11/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/16/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/17/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/17/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/18/2021 Conditional Approval LANNY MERRICK
Reinforced Concrete Frame 3/19/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/22/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/22/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 3/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/31/2021 Partial Approval JAMES POWERS
Green Building Rough 4/1/2021 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 4/1/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 4/1/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 4/6/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/23/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/26/2021 Conditional Approval NICK DANERI
Reinforced Concrete Frame 4/28/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 4/29/2021 Conditional Approval LEOPOLDO MENDOZA
Special/Order Compliance 5/5/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/19/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/19/2021 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 5/21/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/25/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/26/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/27/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/27/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/27/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 6/14/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/28/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/9/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 7/15/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/16/2021 Approved JOEY BUCHANAN
Drywall Nailing 7/16/2021 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Conditional Approval JOEY BUCHANAN
Green Building Rough 7/16/2021 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 8/16/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Partial Approval JAMES POWERS
Structural Steel Frame 8/16/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/31/2021 Partial Approval JAMES POWERS
Drywall Nailing 9/9/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/16/2021 Partial Approval JAMES POWERS
Wood Frame 9/17/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/20/2021 Not Ready for Inspection JAMES POWERS
Wall Anchors 9/20/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 9/20/2021 Partial Approval JAMES POWERS
Wood Frame 9/21/2021 Partial Approval JAMES POWERS
Insulation 9/27/2021 Partial Approval JAMES POWERS
Insulation 10/1/2021 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/6/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval JAMES POWERS
Insulation 10/12/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 10/28/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/28/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/28/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/29/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 11/23/2021 Partial Approval TED RIES
Drywall Nailing 12/6/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/6/2021 Partial Approval JAMES POWERS
Special/Order Compliance 12/6/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/17/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/30/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/13/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 1/13/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 1/20/2022 Partial Approval JAMES POWERS
Special/Order Compliance 2/23/2022 Approved TED RIES
Light Gage Steel Frame 3/8/2022 Partial Approval JAMES POWERS
Special/Order Compliance 3/10/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 3/24/2022 Partial Approval JAMES POWERS
Drywall Nailing 6/27/2022 Approved JAMES POWERS
Final 6/27/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/27/2022 Approved JAMES POWERS
Green Building Final 6/27/2022 Approved JAMES POWERS
Reinforced Masonry Frame 6/27/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Approved JAMES POWERS
Smoke Detectors 6/27/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 6/27/2022 Approved JAMES POWERS
Wood Frame 6/27/2022 Approved JAMES POWERS
Special/Order Compliance 1/4/2023 Approved JAMES POWERS
Final 1/20/2023 Not Ready for Inspection JAMES POWERS
Final 1/26/2023 OK to Issue CofO JAMES POWERS