1340 S HILL ST 90015

Certificate Information: 1340 S HILL ST 90015

Application / Permit
19010-10000-01133
Plan Check / Job No.
B19LA05507
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NEW 7 STORY ( 5 STORY TYPE III-A OVER 2 STORY TYPE I-A & OVER ONE LEVEL SUBTERREAN PARKING GARAGE) 235 UNIT MIXED USE APARTMENT BUILDING WITH RETAIL SPACE AT GROUND FLOOR & OVER ONE LEVEL TYPE I-A SUBTERREAN PARKING GARAGE ( per DIR-2017-1212-SPR ( set-aside 5% of totalnumber of units to very low income households & 20% to workforce housing income households per DIR-2017-1212-SPR & 12.22.A.29).
Permit Issued
Issued on 7/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 GARO TELMI
Disabled Access Plans Picked Up 4/1/2019 APPLICANT
Corrections Issued 4/22/2019 GARO TELMI
Quality Review Completed 4/25/2019 JOHN FRANCIA
Building Plans Picked Up 4/25/2019 APPLICANT
Applicant returned to address corrections 8/29/2019 GARO TELMI
Applicant returned to address corrections 9/11/2019 GARO TELMI
Applicant returned to address corrections 10/15/2019 GARO TELMI
Applicant returned to address corrections 12/4/2019 GARO TELMI
Applicant returned to address corrections 3/24/2020 GARO TELMI
Applicant returned to address corrections 6/23/2020 GARO TELMI
Applicant returned to address corrections 7/10/2020 GARO TELMI
Green Plans Picked Up 7/21/2020 APPLICANT
Plan Check Approved 6/22/2022 GARO TELMI
Plan Check Approved 6/29/2022 GARO TELMI
Issued 7/1/2022 APPLICANT
TCO Issued (Expire Date: 06-14-2025) 12/16/2024 RAFAEL ESPINOZA
CofO Issued 6/18/2025 ERNESTO CORRAL
Permit Finaled 6/18/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 4/24/2019 ERIK BEASLEY
Permit Cleared 4/24/2019 ERIK BEASLEY
Project located in CRA area Cleared 5/2/2019 JIM URQUHART
Trees in Parkway Cleared 5/7/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 9/10/2019 THOMAS LANG
Driveway location Cleared 11/14/2019 MOHAMMAD HASAN
Internal circulation Cleared 11/14/2019 MOHAMMAD HASAN
Highway dedication Cleared 12/20/2019 ELENA LOPEZ
Bicycle Parking Cleared 1/13/2020 CELINA MORENO
Low Impact Development Cleared 1/22/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/22/2020 JUAN ASHTON
Construction near power lines Cleared 2/10/2020 RIDWAN HARDY
DAS Clearance Cleared 2/25/2020 WAI LAU
Hydrant and Access approval Cleared 2/26/2020 ROBERT DUFF
Food Service Establishment Cleared 3/23/2020 PAWAN VERMA
Green Code Cleared 7/21/2020 GARO TELMI
Fire Marshall Fire Life Safety Cleared 8/10/2020 OSCAR SALGADO JR
Work Adjacent to Public Way Cleared 2/11/2021 ROSA SILVA
Encroachment in public way Cleared 8/13/2021 JEREMY CHOK
DCP conditions approval Cleared 2/17/2022 MICHAEL ZIRBES
Density Bonus 12.22.A.25 Cleared 2/17/2022 MICHAEL ZIRBES
"D" conditions Cleared 3/7/2022 ANNA VIDAL
Miscellaneous Cleared 3/7/2022 ANNA VIDAL
Opn space landscape/Water mgmt Cleared 3/7/2022 ANNA VIDAL
Site Plan review Cleared 3/7/2022 ANNA VIDAL
Excavation more than 5-ft deep Cleared 4/6/2022 CALOSHA APPROVED
Sewer availability Cleared 5/23/2022 STEVE MELGAR
Building over 3-story or 36-ft Cleared 6/22/2022 CALOSHA APPROVED

Contact Information

Architect Chupka,, Vince Gerald; Lic. No.: C23572 2381 ELDEN AVE APT B      COSTA MESA, CA 92627
Contractor C B G Building Company Llc; Lic. No.: 1002329-B 3655 NOBEL DRIVE SUITE 480      SAN DIEGO, CA 92122
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Hassan,, Mohamed Ali; Lic. No.: S5285 3621 HARBOR BLVD #125      SANTA ANA, CA 92704
Engineer Krief,, Dan Dov; Lic. No.: C76041 6420 WILSHIRE BLVD STE 1000      LOS ANGELES, CA 90048

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/1/2022 Partial Inspection NICK DANERI
METHANE-Barrier 8/1/2022 Not Ready for Inspection NICK DANERI
METHANE-Subgrade 8/1/2022 Not Ready for Inspection NICK DANERI
Pre-Inspection 8/5/2022 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 8/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 8/15/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/15/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/16/2022 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 8/16/2022 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 8/16/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 8/18/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/18/2022 Partial Approval NICK DANERI
METHANE-Barrier 8/18/2022 Partial Approval NICK DANERI
METHANE-Subgrade 8/18/2022 Partial Inspection NICK DANERI
Deputy Methane Barrier 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 8/22/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/22/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 8/22/2022 Partial Approval NICK DANERI
METHANE-Barrier 8/22/2022 Partial Inspection NICK DANERI
METHANE-Subgrade 8/22/2022 Partial Inspection NICK DANERI
Deputy Reinf. Concrete 8/23/2022 Conditional Approval NICK DANERI
METHANE-Rough 8/23/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/24/2022 Conditional Approval NICK DANERI
Green Building Rough 8/24/2022 Not Ready for Inspection NICK DANERI
METHANE-Final 8/24/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/24/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/24/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 8/25/2022 Conditional Approval NICK DANERI
Reinforced Concrete Frame 8/25/2022 Partial Approval NICK DANERI
Deputy Other (see comments) 8/26/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 8/26/2022 Conditional Approval NICK DANERI
METHANE-Barrier 8/26/2022 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 8/29/2022 Conditional Approval NICK DANERI
Green Building Rough 8/29/2022 Not Ready for Inspection NICK DANERI
METHANE-Rough 8/29/2022 Partial Inspection NICK DANERI
Reinforced Masonry Frame 8/29/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 8/29/2022 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 8/30/2022 Conditional Approval NICK DANERI
Reinforced Concrete Frame 8/30/2022 Partial Approval NICK DANERI
Deputy Shotcrete 8/31/2022 Conditional Approval NICK DANERI
Structural Steel Frame 8/31/2022 Partial Approval NICK DANERI
Deputy Shotcrete 9/1/2022 Conditional Approval NICK DANERI
Reinforced Concrete Frame 9/1/2022 Partial Approval NICK DANERI
Deputy Shotcrete 9/2/2022 Conditional Approval NICK DANERI
Green Building Rough 9/7/2022 No Access for Inspection GREGORY POMISH
METHANE-Rough 9/7/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 9/7/2022 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 9/7/2022 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 9/8/2022 Conditional Approval NICK DANERI
Deputy Shotcrete 9/8/2022 Conditional Approval NICK DANERI
Structural Steel Frame 9/8/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/9/2022 Conditional Approval NICK DANERI
Deputy Shotcrete 9/9/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/12/2022 Conditional Approval NICK DANERI
Deputy Shotcrete 9/12/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/13/2022 Conditional Approval NICK DANERI
Deputy Shotcrete 9/13/2022 Conditional Approval NICK DANERI
Deputy Methane Barrier 9/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 9/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 9/15/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/15/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/15/2022 Partial Approval NICK DANERI
METHANE-Barrier 9/15/2022 Partial Inspection NICK DANERI
METHANE-Subgrade 9/15/2022 Partial Inspection NICK DANERI
Deputy Methane Barrier 9/16/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/16/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/16/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 9/19/2022 Conditional Approval NICK DANERI
Deputy Methane Barrier 9/20/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/20/2022 Conditional Approval MICHAEL ROSENBERG
METHANE-Barrier 9/20/2022 Partial Approval NICK DANERI
Deputy Methane Barrier 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 9/22/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 9/22/2022 Partial Approval NICK DANERI
METHANE-Barrier 9/22/2022 Partial Approval NICK DANERI
METHANE-Subgrade 9/22/2022 Partial Inspection NICK DANERI
Deputy Methane Barrier 9/23/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/23/2022 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 9/27/2022 Conditional Approval NICK DANERI
Green Building Rough 9/27/2022 Not Ready for Inspection NICK DANERI
METHANE-Rough 9/27/2022 Partial Inspection NICK DANERI
Reinforced Concrete Frame 9/27/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/27/2022 Not Ready for Inspection NICK DANERI
Deputy Methane Barrier 9/29/2022 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/29/2022 Partial Approval DANIEL VARNUM
Masonry Wall/Backfill 9/29/2022 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 9/30/2022 Partial Inspection RAFAEL ESPINOZA
METHANE-Barrier 9/30/2022 Partial Inspection RAFAEL ESPINOZA
METHANE-Subgrade 9/30/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 10/5/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/5/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/5/2022 Partial Approval JAMES POWERS
METHANE-Barrier 10/5/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/5/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/10/2022 Partial Approval DAVID BURKHEAD
METHANE-Barrier 10/10/2022 Partial Approval DAVID BURKHEAD
METHANE-Subgrade 10/10/2022 Partial Approval DAVID BURKHEAD
Deputy Methane Barrier 10/13/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/13/2022 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 10/13/2022 Approved RAFAEL ESPINOZA
METHANE-Rough 10/13/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/13/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/13/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 10/14/2022 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 10/20/2022 Partial Inspection GREGORY POMISH
METHANE-Barrier 10/20/2022 Not Ready for Inspection GREGORY POMISH
METHANE-Subgrade 10/20/2022 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Not Ready for Inspection GREGORY POMISH
Masonry Wall/Backfill 10/25/2022 Not Ready for Inspection GREGORY POMISH
METHANE-Final 10/27/2022 Not Ready for Inspection GREGORY POMISH
Deputy Methane Barrier 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 10/28/2022 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Partial Approval NICK DANERI
METHANE-Rough 11/1/2022 Partial Inspection NICK DANERI
Reinforced Concrete Frame 11/1/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/1/2022 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 11/2/2022 Partial Approval NICK DANERI
METHANE-Rough 11/7/2022 Approved NICK DANERI
Reinforced Masonry Frame 11/7/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/7/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 11/9/2022 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/9/2022 Conditional Approval NICK DANERI
Reinforced Concrete Frame 11/9/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Reinforced Concrete Frame 11/21/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 11/21/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Reinforced Concrete Frame 12/5/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/5/2022 Partial Inspection NICK DANERI
Reinforced Masonry Frame 12/6/2022 Partial Approval NICK DANERI
Masonry Wall/Backfill 12/7/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/8/2022 Conditional Approval MICHAEL ROSENBERG
Reinforced Concrete Frame 12/12/2022 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 12/12/2022 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 12/15/2022 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/15/2022 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 12/19/2022 Partial Approval JAMES POWERS
Structural Steel Frame 12/20/2022 Partial Approval NICK DANERI
Wood Frame 12/21/2022 Partial Approval NICK DANERI
Reinforced Concrete Frame 12/30/2022 Partial Approval NICK DANERI
Masonry Wall/Backfill 1/3/2023 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 1/3/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 1/3/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/3/2023 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 1/9/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 1/10/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 1/11/2023 Partial Approval NICK DANERI
Reinforced Masonry Frame 1/12/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 1/12/2023 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 1/13/2023 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Partial Approval NICK DANERI
Wood Frame 1/19/2023 Partial Approval NICK DANERI
Masonry Wall/Backfill 1/23/2023 Partial Approval GREGORY POMISH
Reinforced Concrete Frame 1/24/2023 Not Ready for Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 1/25/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/26/2023 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 1/27/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/27/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/27/2023 Conditional Approval NICK DANERI
Structural Steel Frame 1/27/2023 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 1/30/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/30/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/30/2023 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 1/31/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/31/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 1/31/2023 Conditional Approval NICK DANERI
Structural Steel Frame 1/31/2023 Not Ready for Inspection NICK DANERI
Deputy Drilled-In Anchors 2/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/8/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/8/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/8/2023 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 2/9/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/9/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 2/9/2023 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 2/9/2023 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/13/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 2/13/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 2/13/2023 Conditional Approval GREGORY POMISH
Reinforced Concrete Frame 2/13/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 2/13/2023 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 2/23/2023 Partial Approval NICK DANERI
METHANE-Barrier 2/23/2023 Approved NICK DANERI
METHANE-Subgrade 2/23/2023 Approved NICK DANERI
Masonry Wall/Backfill 2/23/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/2/2023 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 3/2/2023 Conditional Approval NICK DANERI
Deputy Steel/Welding 3/2/2023 Conditional Approval NICK DANERI
Drywall Nailing 3/2/2023 Partial Approval NICK DANERI
Reinforced Concrete Frame 3/2/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/2/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/8/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 3/10/2023 Partial Approval NICK DANERI
Deputy Steel/Welding 3/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/17/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 3/24/2023 Partial Approval NICK DANERI
Masonry Wall/Backfill 3/24/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Approval NICK DANERI
Masonry Wall/Backfill 4/6/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval NICK DANERI
Drywall Nailing 4/18/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 4/18/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval NICK DANERI
Wood Frame 4/25/2023 Partial Approval NICK DANERI
Deputy Steel/Welding 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Partial Inspection NICK DANERI
Wood Frame 4/28/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval NICK DANERI
Deputy Steel/Welding 5/5/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Partial Approval LARRY ARNICK
Deputy Steel/Welding 5/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Not Ready for Inspection LARRY ARNICK
Deputy Steel/Welding 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval GREGORY POMISH
Light Gage Steel Frame 5/19/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval NICK DANERI
Pre-Inspection 5/24/2023 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval NICK DANERI
Pre-Inspection 6/1/2023 Partial Inspection NICK DANERI
Drywall Nailing 6/5/2023 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval NICK DANERI
Pre-Inspection 6/5/2023 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval NICK DANERI
Deputy Steel/Welding 6/8/2023 Conditional Approval LARRY ARNICK
Drywall Nailing 6/8/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval LARRY ARNICK
Drywall Nailing 6/21/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Partial Approval NICK DANERI
Pre-Inspection 6/27/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Not Ready for Inspection NICK DANERI
Insulation 6/28/2023 Not Ready for Inspection NICK DANERI
Pre-Inspection 6/28/2023 Partial Inspection NICK DANERI
Drywall Nailing 6/30/2023 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 6/30/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Not Ready for Inspection JAMES POWERS
Pre-Inspection 7/5/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 7/5/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/7/2023 Partial Approval GREGORY POMISH
Pre-Inspection 7/7/2023 Partial Inspection GREGORY POMISH
Wood Frame 7/7/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval GREGORY POMISH
Pre-Inspection 7/10/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 7/11/2023 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval GREGORY POMISH
Insulation 7/11/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 7/13/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval GREGORY POMISH
Insulation 7/13/2023 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Partial Approval JULIAN CAPUCETTI
Insulation 7/14/2023 Partial Approval JULIAN CAPUCETTI
Wood Frame 7/14/2023 Partial Approval JULIAN CAPUCETTI
Deputy Steel/Welding 7/18/2023 Conditional Approval GREGORY POMISH
Drywall Nailing 7/18/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Partial Approval GREGORY POMISH
Insulation 7/18/2023 Partial Approval GREGORY POMISH
Pre-Inspection 7/18/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Partial Approval GREGORY POMISH
Insulation 7/21/2023 Partial Approval GREGORY POMISH
Wood Frame 7/21/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Partial Approval GREGORY POMISH
Insulation 7/24/2023 Partial Approval GREGORY POMISH
Insulation 7/25/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 7/25/2023 Partial Approval GREGORY POMISH
Drywall Nailing 7/27/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Approval NICK DANERI
Insulation 7/27/2023 Partial Approval NICK DANERI
Drywall Nailing 7/31/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Conditional Approval NICK DANERI
Wood Frame 7/31/2023 Partial Approval NICK DANERI
Drywall Nailing 8/2/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval NICK DANERI
Insulation 8/2/2023 Partial Approval NICK DANERI
Wood Frame 8/2/2023 Partial Approval NICK DANERI
Drywall Nailing 8/4/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval NICK DANERI
Insulation 8/4/2023 Partial Approval NICK DANERI
Drywall Nailing 8/8/2023 Partial Approval NICK DANERI
Insulation 8/8/2023 Partial Approval NICK DANERI
Wood Frame 8/8/2023 Partial Approval NICK DANERI
Drywall Nailing 8/10/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval NICK DANERI
Insulation 8/10/2023 Partial Approval NICK DANERI
Drywall Nailing 8/15/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Partial Approval NICK DANERI
Insulation 8/15/2023 Partial Approval NICK DANERI
Drywall Nailing 8/18/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval NICK DANERI
Light Gage Steel Frame 8/21/2023 No Access for Inspection MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval NICK DANERI
Insulation 8/23/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Inspection NICK DANERI
Insulation 8/25/2023 Partial Approval NICK DANERI
Light Gage Steel Frame 8/25/2023 Partial Approval NICK DANERI
Insulation 8/29/2023 Partial Approval NICK DANERI
Insulation 9/5/2023 Partial Approval NICK DANERI
Drywall Nailing 9/7/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval NICK DANERI
Insulation 9/7/2023 Partial Approval NICK DANERI
Special/Order Compliance 9/8/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Partial Approval NICK DANERI
Insulation 9/11/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Not Ready for Inspection NICK DANERI
Insulation 9/12/2023 Partial Approval NICK DANERI
Wood Frame 9/12/2023 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval NICK DANERI
Drywall Nailing 9/15/2023 Not Ready for Inspection NICK DANERI
Insulation 9/15/2023 Partial Approval NICK DANERI
Insulation 9/18/2023 Partial Approval GREGORY POMISH
Drywall Nailing 9/19/2023 Partial Approval NICK DANERI
Insulation 9/19/2023 Partial Approval NICK DANERI
Wood Frame 9/20/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 9/22/2023 Partial Approval GREGORY POMISH
Drywall Nailing 9/25/2023 Partial Approval GREGORY POMISH
Drywall Nailing 9/26/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 9/26/2023 Partial Approval GREGORY POMISH
Drywall Nailing 9/28/2023 Partial Approval GREGORY POMISH
Insulation 9/28/2023 Partial Approval GREGORY POMISH
Special/Order Compliance 9/28/2023 Partial Inspection KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 10/2/2023 Partial Inspection GREGORY POMISH
Wood Frame 10/2/2023 Partial Inspection GREGORY POMISH
Interior/Exterior Lathing 10/3/2023 Partial Approval GREGORY POMISH
Wood Frame 10/3/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/4/2023 Partial Inspection GREGORY POMISH
Insulation 10/4/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 10/4/2023 Partial Inspection GREGORY POMISH
Insulation 10/5/2023 Partial Approval NICK DANERI
Wood Frame 10/5/2023 Partial Approval NICK DANERI
Insulation 10/6/2023 Not Ready for Inspection NICK DANERI
Wood Frame 10/6/2023 Partial Approval NICK DANERI
Drywall Nailing 10/10/2023 Partial Approval LARRY ARNICK
Insulation 10/10/2023 Partial Approval LARRY ARNICK
Drywall Nailing 10/11/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/11/2023 Not Ready for Inspection NICK DANERI
Wood Frame 10/11/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/12/2023 Not Ready for Inspection NICK DANERI
Wood Frame 10/12/2023 Partial Approval NICK DANERI
Insulation 10/13/2023 Partial Approval NICK DANERI
Insulation 10/17/2023 Partial Approval NICK DANERI
Pre-Inspection 10/17/2023 Partial Approval NICK DANERI
Drywall Nailing 10/18/2023 Partial Inspection GREGORY POMISH
Insulation 10/18/2023 Partial Approval GREGORY POMISH
Pre-Inspection 10/18/2023 Partial Inspection GREGORY POMISH
Wood Frame 10/18/2023 Partial Inspection GREGORY POMISH
Insulation 10/19/2023 Not Ready for Inspection GREGORY POMISH
Wood Frame 10/19/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 10/20/2023 Partial Approval GREGORY POMISH
Special/Order Compliance 10/20/2023 Partial Approval JACOB MYERS
Drywall Nailing 10/23/2023 Partial Approval GREGORY POMISH
Insulation 10/23/2023 Partial Inspection GREGORY POMISH
Interior/Exterior Lathing 10/23/2023 Not Ready for Inspection GREGORY POMISH
Insulation 10/24/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 10/24/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/25/2023 Partial Approval GREGORY POMISH
Insulation 10/25/2023 Partial Approval GREGORY POMISH
Drywall Nailing 10/27/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/27/2023 Not Ready for Inspection NICK DANERI
Wood Frame 10/27/2023 Partial Approval NICK DANERI
Drywall Nailing 10/30/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 10/30/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/30/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 10/31/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/31/2023 Not Ready for Inspection NICK DANERI
Wood Frame 10/31/2023 Partial Approval NICK DANERI
Insulation 11/1/2023 Partial Inspection NICK DANERI
Interior/Exterior Lathing 11/1/2023 Partial Approval NICK DANERI
Wood Frame 11/1/2023 Partial Approval NICK DANERI
Insulation 11/2/2023 Partial Approval NICK DANERI
T-Bar Ceiling 11/2/2023 Not Ready for Inspection NICK DANERI
Wood Frame 11/3/2023 Partial Approval NICK DANERI
Drywall Nailing 11/6/2023 Conditional Approval NICK DANERI
Insulation 11/6/2023 Conditional Approval NICK DANERI
Wood Frame 11/6/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Partial Inspection NICK DANERI
Smoke Detectors 11/7/2023 Conditional Approval NICK DANERI
Wood Frame 11/7/2023 Partial Approval NICK DANERI
Drywall Nailing 11/8/2023 Partial Approval NICK DANERI
Insulation 11/8/2023 Partial Approval NICK DANERI
Insulation 11/9/2023 Partial Inspection GREGORY POMISH
Wood Frame 11/9/2023 Partial Approval GREGORY POMISH
Drywall Nailing 11/13/2023 Partial Approval NICK DANERI
Insulation 11/13/2023 Not Ready for Inspection NICK DANERI
Wood Frame 11/13/2023 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval RAFAEL ESPINOZA
Insulation 11/14/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/14/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/15/2023 Partial Inspection NICK DANERI
Insulation 11/15/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Partial Approval NICK DANERI
Drywall Nailing 11/17/2023 Partial Approval GREGORY POMISH
Insulation 11/17/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 11/21/2023 Partial Inspection GREGORY POMISH
Wood Frame 11/21/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 11/27/2023 Partial Inspection RAFAEL ESPINOZA
Insulation 11/27/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 11/27/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/28/2023 Partial Approval GREGORY POMISH
Insulation 11/28/2023 Partial Approval GREGORY POMISH
Wood Frame 11/28/2023 Partial Approval GREGORY POMISH
Drywall Nailing 11/29/2023 Partial Inspection NICK DANERI
Insulation 11/29/2023 Partial Inspection NICK DANERI
Wood Frame 11/29/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Approval NICK DANERI
Insulation 11/30/2023 Partial Approval NICK DANERI
Insulation 12/1/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/1/2023 Partial Approval NICK DANERI
Drywall Nailing 12/4/2023 Partial Approval NICK DANERI
Insulation 12/4/2023 Partial Approval NICK DANERI
Wood Frame 12/4/2023 Partial Approval NICK DANERI
Drywall Nailing 12/5/2023 Partial Inspection NICK DANERI
Insulation 12/5/2023 Partial Inspection NICK DANERI
Wood Frame 12/5/2023 Partial Approval NICK DANERI
Drywall Nailing 12/6/2023 Partial Approval NICK DANERI
Insulation 12/6/2023 Partial Inspection NICK DANERI
Interior/Exterior Lathing 12/7/2023 Partial Approval NICK DANERI
Wood Frame 12/7/2023 Partial Approval NICK DANERI
Drywall Nailing 12/8/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/8/2023 Not Ready for Inspection NICK DANERI
Wood Frame 12/8/2023 Partial Approval NICK DANERI
Drywall Nailing 12/11/2023 Not Ready for Inspection NICK DANERI
Wood Frame 12/11/2023 Partial Approval NICK DANERI
Drywall Nailing 12/12/2023 Partial Inspection NICK DANERI
Insulation 12/12/2023 Partial Approval NICK DANERI
Wood Frame 12/12/2023 Partial Approval NICK DANERI
Drywall Nailing 12/13/2023 Not Ready for Inspection NICK DANERI
Insulation 12/13/2023 Partial Approval NICK DANERI
Wood Frame 12/13/2023 Partial Approval NICK DANERI
Drywall Nailing 12/14/2023 Not Ready for Inspection NICK DANERI
Insulation 12/14/2023 Partial Approval NICK DANERI
Wood Frame 12/14/2023 Partial Approval NICK DANERI
Drywall Nailing 12/15/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/15/2023 Not Ready for Inspection NICK DANERI
Wood Frame 12/15/2023 Partial Approval NICK DANERI
Drywall Nailing 12/19/2023 Partial Inspection NICK DANERI
Insulation 12/19/2023 Partial Inspection NICK DANERI
Wood Frame 12/19/2023 Partial Approval NICK DANERI
T-Bar Ceiling 12/21/2023 Not Ready for Inspection NICK DANERI
Wood Frame 12/21/2023 Partial Approval NICK DANERI
Drywall Nailing 12/22/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 12/22/2023 Partial Approval NICK DANERI
Drywall Nailing 12/26/2023 Partial Approval NICK DANERI
Insulation 12/26/2023 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 12/27/2023 Conditional Approval NICK DANERI
Wood Frame 12/27/2023 Partial Approval NICK DANERI
Drywall Nailing 12/29/2023 Partial Approval NICK DANERI
Insulation 12/29/2023 Partial Inspection NICK DANERI
Deputy Drilled-In Anchors 1/2/2024 Conditional Approval NICK DANERI
Wood Frame 1/2/2024 Partial Approval NICK DANERI
Insulation 1/3/2024 Partial Approval NICK DANERI
Drywall Nailing 1/4/2024 Partial Approval NICK DANERI
Insulation 1/4/2024 Partial Approval NICK DANERI
Drywall Nailing 1/5/2024 Partial Approval NICK DANERI
Drywall Nailing 1/8/2024 Partial Approval GREGORY POMISH
Drywall Nailing 1/9/2024 Partial Inspection GREGORY POMISH
Insulation 1/10/2024 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 1/11/2024 Approved JACOB MYERS
Insulation 1/11/2024 Not Ready for Inspection JACOB MYERS
Wood Frame 1/11/2024 Not Ready for Inspection JACOB MYERS
Drywall Nailing 1/12/2024 Partial Approval GREGORY POMISH
Drywall Nailing 1/16/2024 Partial Approval NICK DANERI
Insulation 1/17/2024 Partial Approval JACOB MYERS
Drywall Nailing 1/18/2024 Not Ready for Inspection GREGORY POMISH
Insulation 1/19/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 1/19/2024 Partial Approval GREGORY POMISH
Wood Frame 1/19/2024 Partial Approval GREGORY POMISH
Insulation 1/22/2024 Partial Approval NICK DANERI
Drywall Nailing 1/23/2024 Partial Approval NICK DANERI
Insulation 1/25/2024 Partial Approval NICK DANERI
Insulation 1/26/2024 Partial Approval NICK DANERI
Masonry Wall/Backfill 1/29/2024 Partial Approval GREGORY POMISH
Drywall Nailing 1/30/2024 Partial Inspection GREGORY POMISH
Insulation 1/30/2024 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 1/30/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/1/2024 Partial Approval NICK DANERI
Drywall Nailing 2/2/2024 Partial Approval NICK DANERI
Insulation 2/6/2024 Not Ready for Inspection NICK DANERI
Drywall Nailing 2/7/2024 Partial Approval NICK DANERI
Deputy Reinf. Masonry 2/8/2024 Conditional Approval GREGORY POMISH
Insulation 2/8/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/9/2024 Partial Approval GREGORY POMISH
Insulation 2/9/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/12/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/13/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/14/2024 Partial Approval NICK DANERI
Drywall Nailing 2/16/2024 Partial Approval GREGORY POMISH
Drywall Nailing 2/20/2024 Partial Approval GREGORY POMISH
Insulation 2/22/2024 Conditional Approval NICK DANERI
Drywall Nailing 2/23/2024 Partial Approval NICK DANERI
Insulation 2/26/2024 Partial Approval NICK DANERI
Drywall Nailing 2/27/2024 Not Ready for Inspection NICK DANERI
Drywall Nailing 2/28/2024 Partial Approval NICK DANERI
Insulation 2/29/2024 Partial Approval NICK DANERI
Drywall Nailing 3/4/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/5/2024 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 3/7/2024 Partial Approval JAMES POWERS
Drywall Nailing 3/12/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/18/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 3/18/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 3/20/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 3/20/2024 Not Ready for Inspection NICK DANERI
Drywall Nailing 3/21/2024 Partial Approval JAMES POWERS
Drywall Nailing 3/26/2024 Conditional Approval NICK DANERI
Insulation 3/26/2024 Partial Approval NICK DANERI
Masonry Wall/Backfill 3/26/2024 Partial Inspection NICK DANERI
Wood Frame 3/26/2024 Partial Approval NICK DANERI
Drywall Nailing 3/27/2024 Not Ready for Inspection NICK DANERI
Wood Frame 3/27/2024 Not Ready for Inspection NICK DANERI
Drywall Nailing 3/28/2024 Not Ready for Inspection NICK DANERI
Insulation 3/28/2024 Not Ready for Inspection NICK DANERI
Masonry Wall/Backfill 3/28/2024 Partial Approval NICK DANERI
Drywall Nailing 4/3/2024 Partial Approval NICK DANERI
Drywall Nailing 4/4/2024 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 4/10/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 4/12/2024 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 4/19/2024 Partial Approval NICK DANERI
Insulation 4/23/2024 Partial Approval NICK DANERI
Insulation 4/24/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/24/2024 Not Ready for Inspection JAMES POWERS
Insulation 4/26/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 4/29/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/1/2024 Partial Approval NICK DANERI
Drywall Nailing 5/2/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 5/2/2024 Partial Approval NICK DANERI
Drywall Nailing 5/3/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/3/2024 Partial Approval NICK DANERI
Drywall Nailing 5/7/2024 Partial Approval NICK DANERI
Insulation 5/7/2024 Partial Approval NICK DANERI
Drywall Nailing 5/9/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/9/2024 Partial Inspection NICK DANERI
Drywall Nailing 5/13/2024 Partial Approval NICK DANERI
Drywall Nailing 5/16/2024 Partial Approval NICK DANERI
Insulation 5/21/2024 Partial Approval NICK DANERI
Drywall Nailing 5/23/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 5/23/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 5/29/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/31/2024 Not Ready for Inspection JEROME BLACKWOOD
Pre-Inspection 6/5/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 6/11/2024 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 6/13/2024 Partial Approval NICK DANERI
Special/Order Compliance 6/17/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 6/21/2024 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 7/9/2024 Partial Inspection LARRY ARNICK
Special/Order Compliance 7/12/2024 Partial Inspection NICK DANERI
Drywall Nailing 7/19/2024 Partial Approval NICK DANERI
Insulation 7/29/2024 Partial Inspection NICK DANERI
Special/Order Compliance 7/29/2024 Partial Approval NICK DANERI
Pre-Inspection 7/31/2024 Corrections Issued NICK DANERI
Drywall Nailing 8/2/2024 Not Ready for Inspection JEROME BLACKWOOD
Pre-Inspection 9/30/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 10/11/2024 Partial Inspection NICK DANERI
Final 10/17/2024 Partial Inspection NICK DANERI
Footing/Foundation/Slab 10/17/2024 Not Ready for Inspection NICK DANERI
Green Building Final 10/17/2024 Partial Inspection NICK DANERI
Reinforced Concrete Frame 10/17/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 10/17/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Not Ready NICK DANERI
Smoke Detectors 10/17/2024 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 10/17/2024 Not Ready for Inspection NICK DANERI
Special/Order Compliance 10/21/2024 Partial Inspection NICK DANERI
Interior/Exterior Lathing 10/22/2024 Partial Inspection NICK DANERI
Final 10/23/2024 Partial Inspection NICK DANERI
Footing/Foundation/Slab 10/23/2024 Approved NICK DANERI
Green Building Final 10/23/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 10/23/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 10/23/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Not Ready NICK DANERI
Smoke Detectors 10/23/2024 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 10/23/2024 Not Ready for Inspection NICK DANERI
Drywall Nailing 10/24/2024 Approved NICK DANERI
Pre-Inspection 10/30/2024 Not Ready for Inspection JEFFREY FULTON
Final 11/7/2024 Not Ready for Inspection NICK DANERI
Green Building Final 11/7/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 11/7/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 11/7/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready NICK DANERI
Smoke Detectors 11/7/2024 Approved NICK DANERI
Verify Sprinkler Sign Off 11/7/2024 Conditional Approval NICK DANERI
Final 11/13/2024 Partial Inspection NICK DANERI
Green Building Final 11/13/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 11/13/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 11/13/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Approved NICK DANERI
Verify Sprinkler Sign Off 11/13/2024 Not Ready for Inspection NICK DANERI
Special/Order Compliance 11/19/2024 Partial Approval NICK DANERI
Pre-Inspection 11/21/2024 Partial Inspection NICK DANERI
Pre-Inspection 11/25/2024 Partial Approval NICK DANERI
Final 11/26/2024 Not Ready for Inspection NICK DANERI
Green Building Final 11/26/2024 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 11/26/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 11/26/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 11/26/2024 Not Ready for Inspection NICK DANERI
Special/Order Compliance 12/10/2024 Partial Inspection NICK DANERI
Special/Order Compliance 12/12/2024 Partial Inspection NICK DANERI
Final 12/13/2024 Not Ready for Inspection NICK DANERI
Green Building Final 12/13/2024 Approved NICK DANERI
Reinforced Concrete Frame 12/13/2024 Approved NICK DANERI
Reinforced Masonry Frame 12/13/2024 Approved NICK DANERI
Verify Sprinkler Sign Off 12/13/2024 Approved NICK DANERI
Pre-Inspection 1/17/2025 Partial Inspection RONALD JIMENEZ
Final 4/24/2025 Not Ready for Inspection NICK DANERI
Special/Order Compliance 4/25/2025 Partial Inspection NICK DANERI
Special/Order Compliance 5/21/2025 Conditional Approval NICK DANERI
Final 5/30/2025 Not Ready for Inspection LARRY ARNICK
Final 6/3/2025 Conditional Approval JOEY BUCHANAN