4200 W PICO BLVD 90019

Certificate Information: 4200 W PICO BLVD 90019

Application / Permit
19010-10000-01089
Plan Check / Job No.
B19LA05270
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
5 story new construction of 54-units of permanent supportive housing for seniors that will have common areas, and 2500 SF of at grade commercial space. The common area services includes on site property management office, community room, community laundry facilities, and outdoor hardscaped and landscaped courtyards.
Permit Issued
Issued on 10/19/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2019 APPLICANT
Assigned to Plan Check Engineer 4/4/2019 HERNAN ARREOLA
Corrections Issued 4/10/2019 HERNAN ARREOLA
Quality Review Completed 4/11/2019 BILL STUTSMAN
Applicant returned to address corrections 4/16/2020 HERNAN ARREOLA
Applicant returned to address corrections 5/4/2020 HERNAN ARREOLA
Applicant returned to address corrections 7/30/2020 HERNAN ARREOLA
Applicant returned to address corrections 7/31/2020 HERNAN ARREOLA
Plan Check Approved 10/19/2020 HERNAN ARREOLA
Issued 10/19/2020 APPLICANT
Building Plans Picked Up 11/9/2021 APPLICANT
TCO Issued (Expire Date: 04-15-2023) 10/17/2022 ERNESTO CORRAL
TCO Issued (Expire Date: 10-25-2023) 4/28/2023 ERNESTO CORRAL
CofO in Progress 5/15/2023 EDWIN GREGORYONA
Permit Finaled 5/18/2023 TED RIES
CofO Issued 5/18/2023 TED RIES
Permit Finaled 5/18/2023 TED RIES

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/24/2020 GEORGE SUCHAND
Green Code Cleared 3/2/2020 HERNAN ARREOLA
Address approval Cleared 5/4/2020 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 5/4/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 5/4/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/4/2020 EMIL KYUPELYAN
Construction near power lines Cleared 5/5/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/5/2020 EMIL KYUPELYAN
Low Impact Development Cleared 5/19/2020 ANDRES COVARRUBIAS
Community Plan Implem. Overlay Cleared 6/9/2020 PETE EYRE
Trees in Parkway Cleared 7/14/2020 JOHN KIM
Building over 3-story or 36-ft Cleared 7/30/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/30/2020 CALOSHA APPROVED
Community Plan Implem. Overlay Cleared 8/24/2020 JOHN KIM
Density Bonus 12.22.A.31 Cleared 8/25/2020 DORIS KWOK
Fire Marshall Fire Life Safety Cleared 9/2/2020 MENOA AGHAJANI
Work Adjacent to Public Way Cleared 9/3/2020 CHIU TAM
"D" conditions Cleared 9/18/2020 LAUREN PADICK
CPC Cleared 9/18/2020 LAUREN PADICK
Miscellaneous Cleared 9/18/2020 LAUREN PADICK
Opn space landscape/Water mgmt Cleared 9/18/2020 LAUREN PADICK
Project located in CRA area Cleared 9/18/2020 LAUREN PADICK
ZA Case Cleared 9/18/2020 LAUREN PADICK
DAS Clearance Cleared 10/1/2020 HERNAN ARREOLA
Highway dedication Cleared 10/8/2020 CELINA MORENO
Community Plan Implem. Overlay Cleared 10/14/2020 KYLE WINSTON

Contact Information

Architect Aliano,, Giuseppe; Lic. No.: C26571 3408 BUENA VISTA AVE      GLENDALE, CA 91208
Contractor Olson R D Construction Inc; Lic. No.: 953845-B 400 SPECTRUM CENTER DR   STE 1200    IRVINE, CA 92618

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/24/2020 No Access for Inspection EDWIN GREGORYONA
Pre-Inspection 11/30/2020 Partial Approval NICK DANERI
METHANE-Subgrade 2/9/2021 Partial Approval NICK DANERI
Deputy Other (see comments) 2/11/2021 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 2/12/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Barrier 2/12/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 3/4/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 3/5/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 3/9/2021 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 3/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 4/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 4/8/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/8/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/8/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/8/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/8/2021 Partial Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/9/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/21/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/22/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Rough 4/22/2021 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/22/2021 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/22/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 4/23/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/23/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/23/2021 Partial Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 4/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 4/26/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/26/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/27/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/27/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Rough 4/27/2021 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/27/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/27/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 4/28/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/4/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/4/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Rough 5/4/2021 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/4/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/4/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 5/5/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/6/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/10/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 5/19/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/19/2021 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 5/19/2021 Partial Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 5/19/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/19/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 5/27/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/4/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/8/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/9/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/10/2021 Conditional Approval NICK DANERI
Deputy Methane Barrier 6/11/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/14/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 6/15/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 6/15/2021 Approved EDWIN GREGORYONA
Deputy Drilled-In Anchors 6/18/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/18/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/24/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/24/2021 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 6/24/2021 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 6/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/28/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/29/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/30/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 7/30/2021 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 8/3/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/10/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 8/10/2021 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 8/10/2021 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/10/2021 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/10/2021 Partial Inspection EDWIN GREGORYONA
Deputy Wood Construction 8/18/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 8/25/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/26/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/27/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 8/30/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 8/31/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/10/2021 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 9/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 10/6/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 10/21/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 10/28/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/29/2021 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 10/29/2021 Not Ready for Inspection EDWIN GREGORYONA
Insulation 11/3/2021 Partial Approval TIMOTHY BUXTON
Deputy Wood Construction 11/5/2021 Conditional Approval TED RIES
Deputy Wood Construction 11/8/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 11/8/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/15/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/16/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/19/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 11/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/24/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/24/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 11/24/2021 Partial Inspection EDWIN GREGORYONA
Deputy Wood Construction 12/6/2021 Conditional Approval NICK DANERI
Structural Steel Frame 12/6/2021 Partial Approval NICK DANERI
Deputy Wood Construction 12/9/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/9/2021 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Partial Inspection EDWIN GREGORYONA
Green Building Rough 12/9/2021 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/17/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/20/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/21/2021 Approved EDWIN GREGORYONA
Wall Anchors 12/21/2021 Partial Approval EDWIN GREGORYONA
Wood Frame 12/21/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/5/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/7/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/10/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/10/2022 Partial Approval EDWIN GREGORYONA
Insulation 1/24/2022 Partial Inspection EDWIN GREGORYONA
Wood Frame 1/24/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/28/2022 Partial Approval EDWIN GREGORYONA
Insulation 1/28/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/9/2022 Partial Inspection EDWIN GREGORYONA
Wood Frame 2/9/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 2/14/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/23/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 2/23/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/25/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/3/2022 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 3/3/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/24/2022 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 3/24/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/6/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 4/6/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 4/11/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 4/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 4/18/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/21/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 4/26/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 5/2/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/2/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/13/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 5/13/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/25/2022 Approved EDWIN GREGORYONA
Light Gage Steel Frame 6/9/2022 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 6/14/2022 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 6/14/2022 Partial Approval EDWIN GREGORYONA
T-Bar Ceiling 6/14/2022 Approved EDWIN GREGORYONA
Masonry Wall/Backfill 6/17/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/22/2022 Approved EDWIN GREGORYONA
Special/Order Compliance 9/8/2022 Approved EDWIN GREGORYONA
Special/Order Compliance 3/22/2023 Approved EDWIN GREGORYONA
Final 3/24/2023 Conditional Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/24/2023 Approved EDWIN GREGORYONA
Green Building Final 3/24/2023 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 3/24/2023 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 3/24/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 3/24/2023 Approved EDWIN GREGORYONA
Wood Frame 3/24/2023 Approved EDWIN GREGORYONA