6511 W MARYLAND DR 90048

Certificate Information: 6511 W MARYLAND DR 90048

Application / Permit
19010-10000-01079
Plan Check / Job No.
B19LA05209
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ROOF DECK AT 3RD LEVEL. DETACHED GARAGE ON SEPARATE PERMIT.
Permit Issued
Issued on 6/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 JOE VO
Corrections Issued 3/26/2019 JOE VO
Quality Review Completed 3/28/2019 GARO TELMI
Building Plans Picked Up 4/3/2019 APPLICANT
Green Plans Picked Up 4/15/2019 APPLICANT
Plan Check Approved 6/18/2019 JOE VO
Issued 6/20/2019 LADBS
CofO in Progress 11/17/2020 KENNETH NAGLE
CofO Issued 11/18/2020 VINCENT COTTON
Permit Finaled 11/18/2020 VINCENT COTTON

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/11/2019 ROBERT DUFF
CPC Cleared 4/12/2019 BLAYNE SUTTON-WILLS
CPC Cleared 4/12/2019 BLAYNE SUTTON-WILLS
CPC Cleared 4/12/2019 BLAYNE SUTTON-WILLS
Eng Process Fee Ord 176,300 Cleared 4/12/2019 ELAINE LEI
Low Impact Development Cleared 4/12/2019 RYAN HUDSON
Sewer availability Cleared 4/12/2019 ELAINE LEI
ZI Cleared 4/12/2019 BLAYNE SUTTON-WILLS
Green Code Cleared 4/15/2019 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/23/2019 JEANIE LAM
Construction near power lines Cleared 5/29/2019 WALTER RAMIREZ

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 326 PASEO DE LA PLAYA UNIT B      REDONDO BEACH, CA 90277
Contractor G M E Development; Lic. No.: 917664-B 2731 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Salladay,, David Allan; Lic. No.: C46976 1181 KOVANDA WAY      MILPITAS, CA 95035

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/6/2020 Partial Approval EVAN COOPER
METHANE-Barrier 3/6/2020 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 3/6/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 3/11/2020 Partial Approval EVAN COOPER
METHANE-Barrier 3/12/2020 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 3/12/2020 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/17/2020 Partial Approval EVAN COOPER
METHANE-Barrier 3/17/2020 Approved EVAN COOPER
METHANE-Rough 3/17/2020 Approved EVAN COOPER
Deputy Wood Construction 3/31/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Approval EVAN COOPER
Special/Order Compliance 4/1/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Partial Approval EVAN COOPER
Special/Order Compliance 4/17/2020 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 4/20/2020 Corrections Issued KENNETH NAGLE
Special/Order Compliance 4/20/2020 Partial Inspection KENNETH NAGLE
Drywall Nailing 4/23/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/23/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Corrections Issued EVAN COOPER
HVAC-Rough 4/28/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/28/2020 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 4/29/2020 Corrections Issued EVAN COOPER
Shower Pan 4/30/2020 Approved EVAN COOPER
Special/Order Compliance 5/4/2020 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 5/7/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 5/15/2020 Partial Approval EVAN COOPER
Green Building Rough 5/15/2020 Approved EVAN COOPER
Interior/Exterior Lathing 5/15/2020 Approved EVAN COOPER
Verify Sprinkler Sign Off 5/15/2020 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 5/21/2020 Corrections Issued EVAN COOPER
Insulation 5/26/2020 Approved EVAN COOPER
Drywall Nailing 6/3/2020 Approved CRAIG DAVIS
Interior/Exterior Lathing 6/3/2020 Approved CRAIG DAVIS
BUILDING-Rough-Frame 7/17/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/17/2020 Approved OGANES TARAKHCHYAN
Final 7/17/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 7/17/2020 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 7/17/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Final 7/17/2020 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/17/2020 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 7/17/2020 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 7/17/2020 Approved OGANES TARAKHCHYAN
Final 7/22/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/22/2020 Approved OGANES TARAKHCHYAN
HVAC-Final 7/22/2020 Approved OGANES TARAKHCHYAN
Service/Power Release 7/22/2020 Approved OGANES TARAKHCHYAN
Final 11/4/2020 Conditional Approval KENNETH NAGLE