142-142 1/2 S CORONADO ST 90057
Certificate Information: 142-142 1/2 S CORONADO ST 90057
- Application / Permit
- 19010-10000-00855
- Plan Check / Job No.
- B19LA04095
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY TWO FAMILY DWELLING AND ROOF DECK AT THE REAR OF THE LOT.
- Permit Issued
- Issued on 9/18/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2019 | MUKUL GUPTA |
| Corrections Issued | 3/11/2019 | MUKUL GUPTA |
| Green Plans Picked Up | 3/14/2019 | APPLICANT |
| Quality Review Completed | 4/1/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 4/2/2019 | APPLICANT |
| Applicant returned to address corrections | 8/6/2019 | KESETE HAREGOT |
| Plan Check Approved | 8/26/2019 | KESETE HAREGOT |
| No Progress | 8/28/2019 | KESETE HAREGOT |
| Plan Check Approved | 8/29/2019 | KESETE HAREGOT |
| Issued | 9/18/2019 | LADBS |
| CofO in Progress | 8/10/2021 | KATHRYN BUTTERWORTH |
| No Progress | 8/19/2021 | RUBEN SALAS |
| CofO in Progress | 9/11/2021 | RUBEN SALAS |
| Permit Finaled | 9/11/2021 | DEROLD HAUFF |
| CofO Issued | 9/11/2021 | DEROLD HAUFF |
| Permit Finaled | 9/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 3/14/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 3/14/2019 | ELAINE LEI |
| Green Code | Cleared | 3/22/2019 | SARAH ABOULHOSN |
| Highway dedication | Cleared | 4/3/2019 | ELENA LOPEZ |
| Permit | Cleared | 4/4/2019 | ELENA LOPEZ |
| Frnt yard landscape/Water mgmt | Cleared | 4/5/2019 | LATANYA ROUX |
| GPI Written Notices | Cleared | 5/14/2019 | MUKUL GUPTA |
| Grading Pre-Inspection | Cleared | 5/14/2019 | MUKUL GUPTA |
| Low Impact Development | Cleared | 5/21/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 5/21/2019 | KARAN PATEL |
| Trees in Parkway | Cleared | 8/5/2019 | JOHN KIM |
| Disturb/Remove Protected Trees | Cleared | 8/14/2019 | ADRIAN SANCHEZ |
Contact Information
| Engineer | Pinzon,, Eduardo A; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
| Engineer | Ventura,, Wilfredo Santo Doming; Lic. No.: C66532 | 27315 JEFFERSON AVE STE J-229 TEMECULA, CA 92590 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/23/2019 | Corrections Issued | ROBERT VORHIS |
| Pre-Inspection | 10/23/2019 | Partial Inspection | ROBERT VORHIS |
| Grading Pre-Inspection | 10/31/2019 | Partial Inspection | ROBERT VORHIS |
| Special/Order Compliance | 10/31/2019 | Partial Approval | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 12/11/2019 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 12/16/2019 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 12/16/2019 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Barrier | 12/16/2019 | Partial Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 12/16/2019 | Not Ready for Inspection | ROBERT VORHIS |
| Piling/Pier/Caisson | 12/16/2019 | Not Ready for Inspection | ROBERT VORHIS |
| Deputy Reinf. Concrete | 1/2/2020 | Conditional Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 1/7/2020 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 1/9/2020 | Approved | ROBERT VORHIS |
| Deputy Wood Construction | 1/23/2020 | Conditional Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2020 | Corrections Issued | ROBERT CORNELL |
| Deputy Wood Construction | 2/5/2020 | Conditional Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2020 | Corrections Issued | ROBERT VORHIS |
| Deputy Wood Construction | 2/25/2020 | Conditional Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Corrections Issued | ROBERT VORHIS |
| Rough-Elec/Plmb/HVAC | 3/6/2020 | Partial Inspection | ROBERT VORHIS |
| Interior/Exterior Lathing | 3/16/2020 | Partial Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 3/18/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Rough | 3/23/2020 | No Access for Inspection | ROBERT VORHIS |
| Deputy Wood Construction | 3/24/2020 | Conditional Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 3/31/2020 | Conditional Approval | ROBERT VORHIS |
| HVAC-Rough | 4/1/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 4/8/2020 | Conditional Approval | ROBERT VORHIS |
| Green Building Rough | 4/8/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 4/8/2020 | Partial Approval | ROBERT VORHIS |
| METHANE-Rough | 4/8/2020 | Approved | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 4/8/2020 | Approved | ROBERT VORHIS |
| Insulation | 4/16/2020 | Approved | ROBERT VORHIS |
| Shower Pan | 4/16/2020 | Approved | ROBERT VORHIS |
| Drywall Nailing | 4/27/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/8/2020 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | ROBERT VORHIS |
| Reinforced Concrete Frame | 9/10/2020 | Approved | ROBERT VORHIS |
| Underground Mechanical | 9/10/2020 | Approved | ROBERT VORHIS |
| Underground Mechanical | 9/18/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Underground Mechanical | 10/19/2020 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Final | 10/29/2020 | Corrections Issued | ROBERT VORHIS |
| PLUMBING-Final | 10/29/2020 | Approved | ROBERT VORHIS |
| Smoke Detectors | 10/29/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 11/5/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| HVAC-Final | 11/5/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| PLUMBING-Final | 11/5/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| ELECTRICAL-Final | 11/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| HVAC-Final | 11/17/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 11/30/2020 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Final | 12/4/2020 | Approved | ROBERT VORHIS |
| ELECTRICAL-Final | 12/9/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 3/15/2021 | Approved | ROBERT VORHIS |
| Green Building Final | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Barrier | 3/15/2021 | Approved | ROBERT VORHIS |
| METHANE-Subgrade | 3/15/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Not Ready | ROBERT VORHIS |
| Service/Power Release | 3/15/2021 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/27/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 7/27/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Final | 7/27/2021 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Final | 7/27/2021 | Not Ready for Inspection | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Not Ready | ROBERT VORHIS |
| Service/Power Release | 7/27/2021 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | OSVALDO PARAMO |
| Final | 8/3/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 8/3/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/3/2021 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 8/3/2021 | Approved | OSVALDO PARAMO |
| HVAC-Final | 8/5/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 8/5/2021 | Approved | OSVALDO PARAMO |
| Final | 8/6/2021 | Not Ready for Inspection | RUBEN SALAS |
| Gas Test | 8/6/2021 | Not Ready for Inspection | RUBEN SALAS |
| Gas Test | 8/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 8/10/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Service/Power Release | 8/10/2021 | Approved | KATHRYN BUTTERWORTH |